Fiscal Note - State of Utah - 2014 General Session
HB0044S02 - Interstate Electric Transmission Lines
State Government (UCA 36-12-13(2)(b)):
Enactment of this bill could cost the Office of Energy Development $9,500 per year for staff time to review agreements or to provide certificates of in-state need. This cost will be offset by fees that are authorized in the bill.
State Budget Detail Table | FY 2014 | FY 2015 | FY 2016 |
Revenue: | |||
Dedicated Credits | $0 | $9,500 | $9,500 |
Total Revenue | $0 | $9,500 | $9,500 |
Expenditure: | |||
Dedicated Credits | $0 | $9,500 | $9,500 |
Total Expenditure | $0 | $9,500 | $9,500 |
Net Impact, All Funds (Rev.-Exp.) | $0 | $0 | $0 |
Net Impact, General/Education Funds (Rev.-Exp.) | $0 | $0 | $0 |
Local Governments (UCA 36-12-13(2)(c)):
Enactment of this bill likely will not result in direct, measurable costs for local governments.
Direct Expenditures by Utah Residents and Businesses (UCA 36-12-13(2)(d)):
The Office of Energy Development anticipates charging a fee to applicants between $1,000 to $5,000 (depending on the complexity) per agreement reviewed or certificate issued.
Performance Note Required? (Joint Rule 4-2-404): No
2/26/2014, 10:14:22 AM, Lead Analyst: Oh, A./Attny: VA | Office of the Legislative Fiscal Analyst |