Download Zipped Enrolled WP 8.0 HB0042.ZIP 5,392 Bytes
[Introduced][Amended][Status][Bill Documents][Fiscal Note][Bills Directory]

H.B. 42 Enrolled

                 

BIDDING PROCESS FOR SCHOOL DISTRICT CONSTRUCTION

                 
2000 GENERAL SESSION

                 
STATE OF UTAH

                 
Sponsor: Gordon E. Snow

                  AN ACT RELATING TO PUBLIC SCHOOLS; PROVIDING THAT IF A LOCAL SCHOOL
                  BOARD DETERMINES TO USE A CONSTRUCTION MANAGER/GENERAL
                  CONTRACTOR AS ITS METHOD OF CONSTRUCTION CONTRACTING MANAGEMENT
                  ON PROJECTS WHERE THE TOTAL ESTIMATED ACCUMULATIVE COST EXCEEDS
                  $80,000, IT SHALL USE ONE OF THE SOURCE SELECTION METHODS PROVIDED FOR
                  IN SECTIONS 63-56-20 THROUGH 63-56-36 .
                  This act affects sections of Utah Code Annotated 1953 as follows:
                  AMENDS:
                      53A-20-101, as last amended by Chapter 51, Laws of Utah 1998
                  Be it enacted by the Legislature of the state of Utah:
                      Section 1. Section 53A-20-101 is amended to read:
                       53A-20-101. Construction and alteration of schools and plants -- Advertising for bids
                  -- Payment and performance bonds -- Contracts -- Bidding limitations on local school boards
                  -- Interest of local school board members.
                      (1) (a) Prior to the construction of any school or the alteration of any existing school plant,
                  if the total estimated accumulative building project cost exceeds $80,000, a local school board shall
                  advertise for bids on the project at least ten days before the bid due date.
                      (b) The board shall have the advertisement published in a newspaper having general
                  circulation throughout the state and in appropriate construction trade publications that offer free
                  listings.
                      (c) A similar advertisement is required in a newspaper published or having general
                  circulation in any city or county that would be affected by the proposed project.
                      (d) The advertisement shall:
                      (i) require sealed proposals for the building project in accordance with plans and
                  specifications furnished by the local school board;


                      (ii) state where and when the proposals will be opened and shall reserve the right of the board
                  to reject any and all proposals; and
                      (iii) require a certified check or bid bond of not less than 5% of the bid to accompany the bid.
                      (2) (a) The board shall meet at the time and place specified in the advertisement and publicly
                  open and read all received proposals.
                      (b) If satisfactory bids are received, the board shall award the contract to the lowest
                  responsible bidder.
                      (c) If none of the proposals are satisfactory, all shall be rejected.
                      (d) The board shall again advertise in the manner provided in this section.
                      (e) If, after advertising a second time no satisfactory bid is received, the board may proceed
                  under its own direction with the required project.
                      (3) (a) The check or bond required under Subsection (1)(d) shall be drawn in favor of the
                  local school board.
                      (b) If the successful bidder fails or refuses to enter into the contract and furnish the additional
                  bonds required under this section, then the bidder's check or bond is forfeited to the district.
                      (4) A local school board shall require payment and performance bonds of the successful
                  bidder as required in Section 63-56-38 .
                      (5) (a) A local school board may require in the proposed contract that at least 10% of the
                  contract price be withheld until the project is completed and accepted by the board.
                      (b) If money is withheld, the board shall place it in an interest bearing account, and the
                  interest accrues for the benefit of the contractor and subcontractors.
                      (c) This money shall be paid upon completion of the project and acceptance by the board.
                      (6) (a) A local school board may not bid on projects within the district if the total
                  accumulative estimated cost exceeds $80,000.
                      (b) The board may use its resources if no satisfactory bids are received under this section.
                      (7) If the local school board determines in accordance with Section 63-56-36 to use a
                  construction manager/general contractor as its method of construction contracting management on
                  projects where the total estimated accumulative cost exceeds $80,000, it shall select the construction

- 2 -


                  manager/general contractor using one of the source selection methods provided for in Sections
                  63-56-20 through 63-56-36 .
                      [(7)] (8) A local school board member may not have a direct or indirect financial interest in
                  the construction project contract.

- 3 -


[Bill Documents][Bills Directory]