H.B. 370 Enrolled
1
2
3
4
5
6
7 LONG TITLE
8 General Description:
9 This bill modifies the Water and Irrigation code.
10 Highlighted Provisions:
11 This bill:
12 . modifies the definition of "water conveyance facility";
13 . requires the state engineer, by July 1, 2017, to inventory and maintain a list of all
14 open, human-made water conveyance systems in the state;
15 . requires the state engineer to contract with a local conservation district to provide
16 technical support for a canal owner who is adopting a management plan; and
17 . makes technical changes.
18 Money Appropriated in this Bill:
19 None
20 Other Special Clauses:
21 None
22 Utah Code Sections Affected:
23 AMENDS:
24 73-5-7 , Utah Code Annotated 1953
25 73-10-33 , as enacted by Laws of Utah 2010, Chapter 113
26
27 Be it enacted by the Legislature of the state of Utah:
28 Section 1. Section 73-5-7 is amended to read:
29 73-5-7. Inspection of ditches and diverting works by engineer.
30 (1) (a) The state engineer shall have authority to examine and inspect any ditch or other
31 diverting works, and at the time of such inspection [
32 owners thereof to make any addition or alteration [
33 necessary for the security of such works, the safety of persons, or the protection of property.
34 (b) If any person, firm, copartnership, association, or corporation refuses or neglects to
35 comply with [
36 (1)(a), the state engineer may bring action in the name of the state in the district court to
37 enforce [
38 (2) The state engineer shall, by July 1, 2017, inventory and maintain a list of all open,
39 human-made water conveyance systems that carry 5 cubic feet per second or more in the state,
40 including the following information on each conveyance system:
41 (a) alignment;
42 (b) contact information of the owner;
43 (c) maximum flow capacity in cubic feet per second;
44 (d) whether the conveyance system is used for flood or storm water management; and
45 (e) notice of the adoption of a management plan for the conveyance system as reported
46 to the Division of Water Resources under Section 73-10-33 .
47 (3) The owner of an open, human-made water conveyance system that carries 5 cubic
48 feet per second or more shall inform the state engineer if the information described in
49 Subsection (2) changes.
50 (4) The state engineer:
51 (a) may contract with a local conservation district created in Title 17D, Chapter 3,
52 Conservation District Act, to fulfill the duties described in Subsection (2); and
53 (b) may contract a local conservation district created in Title 17D, Chapter 3,
54 Conservation District Act, to provide technical support for a canal owner who is adopting a
55 management plan, as described in Section 73-10-33 .
56 Section 2. Section 73-10-33 is amended to read:
57 73-10-33. Management plan for water conveyance facilities.
58 (1) As used in this section:
59 (a) "Board" means the Board of Water Resources created by Section 73-10-1.5 .
60 (b) "Conservation district" means a conservation district created under Title 17D,
61 Chapter 3, Conservation District Act.
62 (c) "Division" means the Division of Water Resources created by Section 73-10-18 .
63 (d) "Facility owner or operator" means:
64 (i) a water company as defined in Subsection 73-3-3.5 (1)(b); or
65 (ii) an owner or operator of a water conveyance facility.
66 (e) "Management plan" means a written document meeting the requirements of
67 Subsection (3).
68 (f) "Potential risk" means a condition where, if a water conveyance facility fails, the
69 failure would create a high probability of:
70 (i) causing loss of human life; or
71 (ii) causing extensive economic loss, including damage to critical transportation
72 facilities, utility facilities, or public buildings.
73 (g) "Potential risk location" means a segment of a water conveyance facility that
74 constitutes a potential risk due to:
75 (i) location;
76 (ii) elevation;
77 (iii) soil conditions;
78 (iv) structural instability;
79 (v) water volume or pressure; or
80 (vi) other conditions.
81 (h) (i) "Water conveyance facility" means a water conveyance defined in Section
82 57-13a-101 .
83 (ii) "Water conveyance facility" does not include:
84 (A) a pipeline conveying water for industrial use, or municipal use, within a public
85 water system as defined in Section 19-4-102 ;
86 (B) a natural channel used to convey water for use within a water conveyance facility;
87 or
88 (C) a fully piped[
89 (2) (a) For a water conveyance facility that has a potential risk location, the board or
90 division may issue a grant or loan to the facility owner or operator, and the facility owner or
91 operator may receive state money for water development or water conveyance facility repair or
92 improvements, only if the facility owner or operator promptly adopts a management plan in
93 accordance with this section.
94 (b) For a management plan to be considered to be promptly adopted for purposes of
95 this Subsection (2), the facility owner or operator shall:
96 (i) adopt the management plan by an affirmative vote of the facility owner or operator's
97 board of directors, or persons occupying a similar status or performing similar functions before
98 receiving money under Subsection (2)(a);
99 (ii) (A) adopt the management plan as described in Subsection (2)(b)(i) by no later
100 than:
101 (I) May 1, 2013, for a water conveyance facility in operation on May 11, 2011; or
102 (II) for a water conveyance facility that begins operation after May 11, 2011, one year
103 after the day on which the water conveyance facility begins operation; or
104 (B) (I) adopt the management plan as described in Subsection (2)(b)(i); and
105 (II) provide written justification satisfactory to the board as to why the facility owner or
106 operator was unable to adopt a management plan during the time period provided in Subsection
107 (2)(b)(ii)(A); and
108 (iii) update the management plan adopted under Subsection (2)(b)(i) no less frequently
109 than every 10 years.
110 (3) A management plan described in Subsection (2) shall include at least the following:
111 (a) a GIS coverage or drawing of each potential risk location of a water conveyance
112 facility identifying any:
113 (i) existing canal and lateral alignment of the canal facility;
114 (ii) point of diversion;
115 (iii) bridge;
116 (iv) culvert;
117 (v) screen or trash rack; and
118 (vi) spill point;
119 (b) an evaluation of any potential slope instability that may cause a potential risk,
120 including:
121 (i) failure of the facility;
122 (ii) land movement that might result in failure of the facility; or
123 (iii) land movement that might result from failure of the facility;
124 (c) proof of insurance coverage or other means of financial responsibility against
125 liability resulting from failure of the water conveyance facility;
126 (d) a maintenance and improvement plan;
127 (e) a schedule for implementation of a maintenance and improvement plan;
128 (f) an emergency response plan that:
129 (i) is developed after consultation with local emergency response officials;
130 (ii) is updated annually; and
131 (iii) includes, in the case of an emergency, how a first responder can:
132 (A) contact the facility owner or operator; and
133 (B) obtain information described in Subsection (3)(a);
134 (g) any potential source of financing for maintenance and improvements under a
135 maintenance and improvement plan;
136 (h) identification of each municipality or county through which water is conveyed or
137 delivered by the water conveyance facility;
138 (i) a statement concerning whether storm water enters the water conveyance facility;
139 and
140 (j) if storm water enters the water conveyance facility:
141 (i) an estimate of the maximum volume and flow of all water present in the water
142 conveyance facility as a result of a six-hour, 25-year storm event;
143 (ii) on the basis of information provided in accordance with Subsection (4),
144 identification of the points at which any storm structures introduce water into the water
145 conveyance facility and the anticipated flow that may occur at each structure; and
146 (iii) the name of each governmental agency that has responsibility for storm water
147 management within the area from which storm water drains into the water conveyance facility.
148 (4) A private or public entity that introduces storm water into a water conveyance
149 facility shall provide the facility owner or operator with an estimate of the maximum volume
150 and flow of water that may occur at each structure that introduces storm water into the water
151 conveyance facility.
152 (5) (a) A facility owner or operator of a water conveyance facility shall provide a
153 municipality or county in which is located a potential risk location of the water conveyance
154 facility an outline of the information provided in Subsection (3)(f).
155 (b) A facility owner or operator shall give notice to the planning and zoning
156 department of each municipality and county identified in Subsection (3)(h) outlining the
157 information provided in Subsections (3)(f), (i), and (j).
158 (c) An outline of information provided under this Subsection (5) is a protected record
159 under Section 63G-2-305 .
160 (6) (a) The division may provide information and technical resources to a facility
161 owner or operator of a water conveyance facility, regardless of whether the water conveyance
162 facility has a potential risk location.
163 (b) In providing the information and resources described in Subsection [
164 division may coordinate with efforts of any association of conservation districts that may
165 provide similar information and technical resources.
166 (c) The information and technical resources described in Subsection [
167 include:
168 (i) engaging state and local water users in voluntary completion of a management plan;
169 (ii) developing standard guidelines, checklists, or templates that may be used by a
170 facility owner or operator;
171 (iii) using conservation districts as points of contact with a facility owner or operator;
172 (iv) providing training to help a facility owner or operator to adopt a management plan;
173 and
174 (v) assisting, at the request and under the direction of, a facility owner or operator with
175 efforts to adopt or implement a management plan.
176 (7) (a) A facility owner or operator of a water conveyance facility that has a potential
177 risk location shall provide the board or division upon request:
178 (i) written certification signed under oath by a person authorized to act for the board of
179 directors or persons occupying a similar status or performing similar functions, certifying that
180 the management plan complies with this section; and
181 (ii) an opportunity to review a management plan.
182 (b) A management plan received by the board or division under this section is a
183 protected record under Section 63G-2-305 .
184 (8) The board shall report concerning compliance with this section to the Natural
185 Resources, Agriculture, and Environment Interim Committee of the Legislature before
186 November 30, 2013.
187 (9) The division and board may make rules, in accordance with Title 63G, Chapter 3,
188 Utah Administrative Rulemaking Act, concerning the requirements of this section.
189 (10) This section does not:
190 (a) create a private right of action for a violation of this section; or
191 (b) limit, impair, or enlarge a person's right to sue and recover damages from a facility
192 owner or operator in a civil action for a cause of action that is not based on a violation of this
193 section.
194 (11) The following may not be introduced as evidence in any civil litigation on the
195 issue of negligence, injury, or the calculation of damages:
196 (a) a management plan prepared in accordance with this section;
197 (b) the failure to prepare or adopt a management plan in accordance with this section;
198 or
199 (c) the failure to update a management plan in accordance with this section.
[Bill Documents][Bills Directory]