(1) In determining the conversion costs included in the costs and feasibility report
required by Section 54-8-7, the public utility corporations shall be entitled to amounts sufficient
to repay them for the following, as computed and reflected by the uniform system of accounts
approved by the Public Service Commission, Federal Communications Commission, or Federal
Power Commission:
(a) the original costs less depreciation taken of the existing overhead electric and
communication facilities to be removed;
(b) the estimated costs of removing such overhead electric and communication facilities,
less the salvage value of the facilities removed;
(c) if the estimated cost of constructing underground facilities exceeds the original cost
of existing overhead electric and communication facilities, then the cost difference between the
two; and
(d) the cost of obtaining new easements when technical considerations make it
reasonably necessary to utilize easements for the underground facilities different from those used
for aboveground facilities, or where the pre-existing easements are insufficient for the
underground facilities.
(2) Notwithstanding Subsection (1), if conversion costs are included in tariffs, rules, or
regulations filed with or promulgated by the Public Service Commission such conversion costs
shall be the costs included in the costs and feasibility report.