Public Utilities
Siting of High Voltage Power Line Act
Section 302
Public workshops.
     54-18-302.   Public workshops.
     After a public utility files the notice of intent in accordance with Subsection 54-18-301(3) and before it files a land use application, the public utility shall:
     (1) conduct informal public workshops at locations along the proposed corridor to provide information about:
     (a) the high voltage power line; and
     (b) the process for obtaining a land use permit; and
     (2) provide notice of the public workshops at least 14 days before a public workshop to:
     (a) a newspaper of general circulation in the target study area;
     (b) radio stations in the target study area; and
     (c) an affected entity.

Enacted by Chapter 316, 2009 General Session
Download Code Section Zipped WordPerfect 54_18_030200.ZIP 1,934 Bytes