54-18-302. Public workshops. After a public utility files the notice of intent in accordance with Subsection 54-18-301(3) and before it files a land use application, the public utility shall: (1) conduct informal public workshops at locations along the proposed corridor to provide information about: (a) the high voltage power line; and (b) the process for obtaining a land use permit; and (2) provide notice of the public workshops at least 14 days before a public workshop to: (a) a newspaper of general circulation in the target study area; (b) radio stations in the target study area; and (c) an affected entity.