Title 38
Chapter 1a
Part 7
Section 701
| Index | Utah Code |
| Title 38 | Liens |
| Chapter 1a | Preconstruction and Construction Liens |
| Part 7 | Enforcement of Preconstruction and Construction Liens |
| Section 701 | Action to enforce lien -- Time for filing action -- Notice of pendency of action -- Action involving a residence. |
38-1a-701.
Action to enforce lien -- Time for filing action -- Notice of pendency of action -- Action involving a residence.
| (1) |
As used in this section:
| (a) |
"Owner" has the same meaning as defined in Section 38-11-102. |
| (b) |
"Residence" has the same meaning as defined in Section 38-11-102. |
|
| (2) |
In order to enforce a preconstruction lien or construction lien, a claimant shall file an action to enforce the lien:
| (a) |
except as provided in Subsection (2)(b), within 180 days after the day on which the claimant files:
| (i) |
a notice of preconstruction lien under Section 38-1a-402, for a preconstruction lien; or |
| (ii) |
a notice of construction lien under Section 38-1a-502, for a construction lien; or |
|
| (b) |
if an owner files for protection under the bankruptcy laws of the United States before the expiration of the 180-day period under Subsection (2)(a), within 90 days after the automatic stay under the bankruptcy proceeding is lifted or expires. |
|
| (3) |
| (a) |
| (i) |
Within the time period provided in Subsection (2) for filing an action, a claimant shall file for record with each applicable county recorder a notice of the pendency of the action, in the manner provided for actions affecting the title or right to possession of real property. |
| (ii) |
If a claimant fails to file for record a notice of the pendency of the action, as required in Subsection (3)(a)(i), the preconstruction lien or construction lien, as applicable, is void, except as to persons who have been made parties to the action and persons having actual knowledge of the commencement of the action. |
|
| (b) |
The burden of proof is upon the claimant and those claiming under the claimant to show actual knowledge under Subsection (3)(a)(ii). |
|
| (4) |
| (a) |
A preconstruction lien or construction lien is automatically and immediately void if an action to enforce the lien is not filed within the time required by this section. |
| (b) |
Notwithstanding Section 78B-2-111, a court has no subject matter jurisdiction to adjudicate a preconstruction or construction lien that becomes void under Subsection (4)(a). |
|
| (5) |
This section may not be interpreted to impair or affect the right of any person to whom a debt may be due for any preconstruction service or construction work to maintain a personal action to recover the debt. |
| (6) |
| (a) |
If a claimant files an action to enforce a preconstruction or construction lien involving a residence, the claimant shall include with the service of the complaint on the owner of the residence:
|
| (b) |
The instructions and form required by Subsection (6)(a) shall meet the requirements established by the division by rule. |
| (c) |
If a claimant fails to provide to the owner of the residence the instructions and form required by Subsection (6)(a), the claimant is barred from maintaining or enforcing the preconstruction or construction lien upon the residence. |
| (e) |
An owner applying for a certificate of compliance under Subsection (6)(d) shall send by certified mail to all claimants:
| (i) |
a copy of the application for a certificate of compliance; and |
| (ii) |
all materials filed in connection with the application. |
|
| (f) |
The division shall notify all claimants listed in an owner's application for a certificate of compliance under Subsection (6)(d) of the issuance or denial of a certificate of compliance. |
|
Renumbered and Amended by Chapter
278, 2012 General Session