<chapter number="38-1a"><catchline>Preconstruction and Construction Liens</catchline><part number="38-1a-1"><catchline>General Provisions</catchline><section number="38-1a-101"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Title.</catchline><tab/>This chapter is known as "Preconstruction and Construction Liens."
</section><section number="38-1a-102"><histories><history>Amended by Chapter <modchap sess="2022GS">415</modchap>, 2022 General Session</history><modyear>2022</modyear><history>Amended by Chapter <modchap sess="2022GS">429</modchap>, 2022 General Session</history><modyear>2022</modyear></histories><catchline>Definitions.</catchline><tab/>As used in this chapter:<subsection number="38-1a-102(1)">
"Alternate means" means a method of filing a legible and complete notice or other document with the registry other than electronically, as established by the division by rule.</subsection><subsection number="38-1a-102(2)">
"Anticipated improvement" means an improvement:
<subsection number="38-1a-102(2)(a)">
for which preconstruction service is performed; and</subsection><subsection number="38-1a-102(2)(b)">
that is anticipated to follow the performing of preconstruction service.</subsection></subsection><subsection number="38-1a-102(3)">
"Applicable county recorder" means the office of the recorder of each county in which any part of the property on which a claimant claims or intends to claim a preconstruction or construction lien is located.</subsection><subsection number="38-1a-102(4)">
"Bona fide loan" means a loan to an owner or owner-builder by a lender in which the owner or owner-builder has no financial or beneficial interest greater than 5% of the voting shares or other ownership interest.</subsection><subsection number="38-1a-102(5)">
"Claimant" means a person entitled to claim a preconstruction or construction lien.</subsection><subsection number="38-1a-102(6)">
"Compensation" means the payment of money for a service rendered or an expense incurred, whether based on:
<subsection number="38-1a-102(6)(a)">
time and expense, lump sum, stipulated sum, percentage of cost, cost plus fixed or percentage fee, or commission; or</subsection><subsection number="38-1a-102(6)(b)">
a combination of the bases listed in Subsection <xref depth="4" refnumber="38-1a-102(6)(a)" start="0">(6)(a)</xref>.</subsection></subsection><subsection number="38-1a-102(7)">
"Construction lender" means a person who makes a construction loan.</subsection><subsection number="38-1a-102(8)">
"Construction lien" means a lien under this chapter for construction work.</subsection><subsection number="38-1a-102(9)">
"Construction loan" does not include a consumer loan secured by the equity in a consumer's home.</subsection><subsection number="38-1a-102(10)">
"Construction project" means an improvement that is constructed pursuant to an original contract.</subsection><subsection number="38-1a-102(11)">
"Construction work":
<subsection number="38-1a-102(11)(a)">
means labor, service, material, or equipment provided for the purpose and during the process of constructing, altering, or repairing an improvement; and</subsection><subsection number="38-1a-102(11)(b)">
includes scheduling, estimating, staking, supervising, managing, materials testing, inspection, observation, and quality control or assurance involved in constructing, altering, or repairing an improvement.</subsection></subsection><subsection number="38-1a-102(12)">
"Contestable notice" means a notice of preconstruction service under Section <xref depth="3" refnumber="38-1a-401" start="0">38-1a-401</xref>, a preliminary notice under Section <xref depth="3" refnumber="38-1a-501" start="0">38-1a-501</xref>, or a notice of completion under Section <xref depth="3" refnumber="38-1a-506" start="0">38-1a-506</xref>.</subsection><subsection number="38-1a-102(13)">
"Contesting person" means an owner, original contractor, subcontractor, or other interested person.</subsection><subsection number="38-1a-102(14)">
"Designated agent" means the third party the division contracts with as provided in Section <xref depth="3" refnumber="38-1a-202" start="0">38-1a-202</xref> to create and maintain the registry.</subsection><subsection number="38-1a-102(15)">
"Division" means the Division of Professional Licensing created in Section <xref depth="3" refnumber="58-1-103" start="0">58-1-103</xref>.</subsection><subsection number="38-1a-102(16)">
"Entry number" means the reference number that:
<subsection number="38-1a-102(16)(a)">
the designated agent assigns to each notice or other document filed with the registry; and</subsection><subsection number="38-1a-102(16)(b)">
is unique for each notice or other document.</subsection></subsection><subsection number="38-1a-102(17)">
"Final completion" means:
<subsection number="38-1a-102(17)(a)">
the date of issuance of a permanent certificate of occupancy by the local government entity having jurisdiction over a construction project, if a permanent certificate of occupancy is required;</subsection><subsection number="38-1a-102(17)(b)">
the date of the final inspection of construction work by the local government entity having jurisdiction over a construction project, if an inspection is required under a state-adopted building code applicable to the construction work, but no certificate of occupancy is required;</subsection><subsection number="38-1a-102(17)(c)">
unless the owner is holding payment to ensure completion of construction work, the date on which there remains no substantial work to be completed to finish the construction work under the original contract, if a certificate of occupancy is not required and a final inspection is not required under an applicable state-adopted building code; or</subsection><subsection number="38-1a-102(17)(d)">
the last date on which substantial work was performed under the original contract, if, because the original contract is terminated before completion of the construction work defined by the original contract, the local government entity having jurisdiction over a construction project does not issue a certificate of occupancy or perform a final inspection.</subsection></subsection><subsection number="38-1a-102(18)">
"Final lien waiver" means a form that complies with Subsection <xref depth="4" refnumber="38-1a-802(4)(c)" start="0">38-1a-802(4)(c)</xref>.</subsection><subsection number="38-1a-102(19)">
"First preliminary notice filing" means a preliminary notice that:
<subsection number="38-1a-102(19)(a)">
is the earliest preliminary notice filed on a construction project for which the preliminary notice is filed;</subsection><subsection number="38-1a-102(19)(b)">
is filed on a construction project that, at the time the preliminary notice is filed, has not reached final completion; and</subsection><subsection number="38-1a-102(19)(c)">
is not canceled under Section <xref depth="3" refnumber="38-1a-307" start="0">38-1a-307</xref>.</subsection></subsection><subsection number="38-1a-102(20)">
"Government project-identifying information" has the same meaning as defined in Section <xref depth="3" refnumber="38-1b-102" start="0">38-1b-102</xref>.</subsection><subsection number="38-1a-102(21)">
"Improvement" means:
<subsection number="38-1a-102(21)(a)">
a building, infrastructure, utility, or other human-made structure or object constructed on or for and affixed to real property; or</subsection><subsection number="38-1a-102(21)(b)">
a repair, modification, or alteration of a building, infrastructure, utility, or object referred to in Subsection <xref depth="4" refnumber="38-1a-102(21)(a)" start="0">(21)(a)</xref>.</subsection></subsection><subsection number="38-1a-102(22)">
"Interested person" means a person that may be affected by a construction project.</subsection><subsection number="38-1a-102(23)">
"Notice of commencement" means a notice required under Section <xref depth="3" refnumber="38-1b-201" start="0">38-1b-201</xref> for a government project as defined in Section <xref depth="3" refnumber="38-1b-102" start="0">38-1b-102</xref>.</subsection><subsection number="38-1a-102(24)">
"Original contract":
<subsection number="38-1a-102(24)(a)">
means a contract between an owner and an original contractor for preconstruction service or construction work; and</subsection><subsection number="38-1a-102(24)(b)">
does not include a contract between an owner-builder and another person.</subsection></subsection><subsection number="38-1a-102(25)">
"Original contractor" means a person, including an owner-builder, that contracts with an owner to provide preconstruction service or construction work.</subsection><subsection number="38-1a-102(26)">
"Owner" means a person who possesses an interest in a project property and contracts with an original contractor for preconstruction service or construction work.</subsection><subsection number="38-1a-102(27)">
"Owner-builder" means an owner, including an owner who is also an original contractor, who:
<subsection number="38-1a-102(27)(a)">
contracts with one or more other persons for preconstruction service or construction work for an improvement on the owner's real property; and</subsection><subsection number="38-1a-102(27)(b)">
obtains a building permit for the improvement.</subsection></subsection><subsection number="38-1a-102(28)">
"Preconstruction lien" means a lien under this chapter for a preconstruction service.</subsection><subsection number="38-1a-102(29)">
"Preconstruction service":
<subsection number="38-1a-102(29)(a)">
means to plan or design, or to assist in the planning or design of, an improvement or a proposed improvement:<subsection number="38-1a-102(29)(a)(i)">
before construction of the improvement commences; and</subsection><subsection number="38-1a-102(29)(a)(ii)">
for compensation separate from any compensation paid or to be paid for construction work for the improvement; and</subsection></subsection><subsection number="38-1a-102(29)(b)">
includes consulting, conducting a site investigation or assessment, programming, preconstruction cost or quantity estimating, preconstruction scheduling, performing a preconstruction construction feasibility review, procuring construction services, and preparing a study, report, rendering, model, boundary or topographic survey, plat, map, design, plan, drawing, specification, or contract document.</subsection></subsection><subsection number="38-1a-102(30)">
"Private project" means a construction project that is not a government project.</subsection><subsection number="38-1a-102(31)">
"Project property" means the real property interest on or for which preconstruction service or construction work is or will be provided.</subsection><subsection number="38-1a-102(32)">
"Registry" means the State Construction Registry under <xref depth="2" refnumber="38-1a-2" start="2">Part 2, State Construction Registry</xref>.</subsection><subsection number="38-1a-102(33)">
"Required notice" means:
<subsection number="38-1a-102(33)(a)">
a notice of preconstruction service under Section <xref depth="3" refnumber="38-1a-401" start="0">38-1a-401</xref>;</subsection><subsection number="38-1a-102(33)(b)">
a preliminary notice under Section <xref depth="3" refnumber="38-1a-501" start="0">38-1a-501</xref> or Section <xref depth="3" refnumber="38-1b-202" start="0">38-1b-202</xref>;</subsection><subsection number="38-1a-102(33)(c)">
a notice of commencement;</subsection><subsection number="38-1a-102(33)(d)">
a notice of construction loan under Section <xref depth="3" refnumber="38-1a-601" start="0">38-1a-601</xref>;</subsection><subsection number="38-1a-102(33)(e)">
a notice under Section <xref depth="3" refnumber="38-1a-602" start="0">38-1a-602</xref> concerning a construction loan default;</subsection><subsection number="38-1a-102(33)(f)">
a notice of intent to obtain final completion under Section <xref depth="3" refnumber="38-1a-506" start="0">38-1a-506</xref>; or</subsection><subsection number="38-1a-102(33)(g)">
a notice of completion under Section <xref depth="3" refnumber="38-1a-507" start="0">38-1a-507</xref>.</subsection></subsection><subsection number="38-1a-102(34)">
"Subcontractor" means a person that contracts to provide preconstruction service or construction work to:
<subsection number="38-1a-102(34)(a)">
a person other than the owner; or</subsection><subsection number="38-1a-102(34)(b)">
the owner, if the owner is an owner-builder.</subsection></subsection><subsection number="38-1a-102(35)">
"Substantial work" does not include repair work or warranty work.</subsection><subsection number="38-1a-102(36)">
"Supervisory subcontractor" means a person that:
<subsection number="38-1a-102(36)(a)">
is a subcontractor under contract to provide preconstruction service or construction work; and</subsection><subsection number="38-1a-102(36)(b)">
contracts with one or more other subcontractors for the other subcontractor or subcontractors to provide preconstruction service or construction work that the person is under contract to provide.</subsection></subsection></section><section number="38-1a-103"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Government projects not subject to chapter -- Exception.</catchline><tab/>Except as provided in Section <xref depth="3" refnumber="38-1a-102" start="0">38-1a-102</xref>, <xref depth="2" refnumber="38-1a-2" start="2">Part 2, State Construction Registry</xref>, and <xref depth="1" refnumber="38-1b" start="1">Chapter 1b, Government Construction Projects</xref>, this chapter does not apply to a government project, as defined in Section <xref depth="3" refnumber="38-1b-102" start="0">38-1b-102</xref>.
</section><section number="38-1a-104"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Owner-builder original contract -- Owner-builder as original contractor.</catchline><tab/>For purposes of this chapter:<subsection number="38-1a-104(1)">
an original contract is considered to exist between an owner-builder as owner and the owner-builder as original contractor; and</subsection><subsection number="38-1a-104(2)">
in addition to being an owner, an owner-builder is considered to be an original contractor.</subsection></section><section number="38-1a-105"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>No waiver of rights -- Exception.</catchline><subsection number="38-1a-105(1)"><subsection number="38-1a-105(1)(a)">
A right or privilege under this chapter may not be waived or limited by contract.</subsection><subsection number="38-1a-105(1)(b)">
A provision of a contract purporting to waive or limit a right or privilege under this chapter is void.</subsection></subsection><subsection number="38-1a-105(2)">
Notwithstanding Subsection <xref depth="4" refnumber="38-1a-105(1)" start="0">(1)</xref>, a claimant may waive or limit, in whole or in part, a lien right under this chapter in consideration of payment as provided in Section <xref depth="3" refnumber="38-1a-802" start="0">38-1a-802</xref>.</subsection></section></part><part number="38-1a-2"><catchline>State Construction Registry</catchline><section number="38-1a-201"><histories><history>Amended by Chapter <modchap sess="2013GS">278</modchap>, 2013 General Session</history><modyear>2013</modyear></histories><catchline>Establishment of State Construction Registry -- Filing index.</catchline><subsection number="38-1a-201(1)">
Subject to receiving adequate funding through a legislative appropriation and contracting with an approved third party vendor as provided in Section <xref depth="3" refnumber="38-1a-202" start="0">38-1a-202</xref>, the division shall establish and maintain the State Construction Registry to:
<subsection number="38-1a-201(1)(a)"><subsection number="38-1a-201(1)(a)(i)">
assist in protecting public health, safety, and welfare; and</subsection><subsection number="38-1a-201(1)(a)(ii)">
promote a fair working environment;</subsection></subsection><subsection number="38-1a-201(1)(b)">
be overseen by the division with the assistance of the designated agent;</subsection><subsection number="38-1a-201(1)(c)">
provide a central repository for all required notices;</subsection><subsection number="38-1a-201(1)(d)">
make accessible, by way of an Internet website:<subsection number="38-1a-201(1)(d)(i)">
the filing and review of required notices; and</subsection><subsection number="38-1a-201(1)(d)(ii)">
the transmitting of building permit information under Subsection <xref depth="4" refnumber="38-1a-205(1)" start="0">38-1a-205(1)</xref> and the reviewing of that information;</subsection></subsection><subsection number="38-1a-201(1)(e)">
accommodate:<subsection number="38-1a-201(1)(e)(i)">
electronic filing of required notices and electronic transmitting of building permit information described in Subsection <xref depth="4" refnumber="38-1a-201(1)(d)(ii)" start="0">(1)(d)(ii)</xref>; and</subsection><subsection number="38-1a-201(1)(e)(ii)">
the filing of required notices by alternate means, including United States mail, telefax, or any other method as the division provides by rule;</subsection></subsection><subsection number="38-1a-201(1)(f)"><subsection number="38-1a-201(1)(f)(i)">
provide electronic notification for up to three email addresses for each interested person who requests to receive notification under Section <xref depth="3" refnumber="38-1a-204" start="0">38-1a-204</xref> from the designated agent; and</subsection><subsection number="38-1a-201(1)(f)(ii)">
provide alternate means of providing notification to a person who makes a filing by alternate means, including United States mail, telefax, or any other method as the division prescribes by rule; and</subsection></subsection><subsection number="38-1a-201(1)(g)">
provide hard-copy printing of electronic receipts for an individual filing evidencing the date and time of the individual filing and the content of the individual filing.</subsection></subsection><subsection number="38-1a-201(2)">
The designated agent shall index filings in the registry by:
<subsection number="38-1a-201(2)(a)">
the name of the owner;</subsection><subsection number="38-1a-201(2)(b)">
the name of the original contractor;</subsection><subsection number="38-1a-201(2)(c)">
subdivision, development, or other project name, if any;</subsection><subsection number="38-1a-201(2)(d)">
lot or parcel number;</subsection><subsection number="38-1a-201(2)(e)">
the address of the project property;</subsection><subsection number="38-1a-201(2)(f)">
entry number;</subsection><subsection number="38-1a-201(2)(g)">
the name of the county in which the project property is located;</subsection><subsection number="38-1a-201(2)(h)">
for private projects:<subsection number="38-1a-201(2)(h)(i)">
the tax parcel identification number of each parcel included in the project property; and</subsection><subsection number="38-1a-201(2)(h)(ii)">
the building permit number;</subsection></subsection><subsection number="38-1a-201(2)(i)">
for government projects, the government project-identifying information; and</subsection><subsection number="38-1a-201(2)(j)">
any other identifier that the division considers reasonably appropriate in collaboration with the designated agent.</subsection></subsection></section><section number="38-1a-202"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear><history>Amended by Chapter <modchap sess="2012GS">347</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Contract to establish and maintain registry -- Designated agent -- Rules -- Duties of designated agent -- Limit of liability.</catchline><subsection number="38-1a-202(1)"><subsection number="38-1a-202(1)(a)">
The division shall contract, in accordance with <xref depth="1" refnumber="63G-6a" start="0">Title 63G, Chapter 6a, Utah Procurement Code</xref>, with a third party to establish and maintain the registry for the purposes established under this part.</subsection><subsection number="38-1a-202(1)(b)">
The designated agent is not an agency, instrumentality, or political subdivision of the state.</subsection></subsection><subsection number="38-1a-202(2)"><subsection number="38-1a-202(2)(a)">
The third party under contract under this section is the division's designated agent, and shall develop and maintain a registry from the information provided by:<subsection number="38-1a-202(2)(a)(i)">
local government entities issuing building permits;</subsection><subsection number="38-1a-202(2)(a)(ii)">
original contractors;</subsection><subsection number="38-1a-202(2)(a)(iii)">
subcontractors;</subsection><subsection number="38-1a-202(2)(a)(iv)">
construction lenders; and</subsection><subsection number="38-1a-202(2)(a)(v)">
other interested persons.</subsection></subsection><subsection number="38-1a-202(2)(b)">
The registry shall accommodate filings by third parties on behalf of clients.</subsection></subsection><subsection number="38-1a-202(3)"><subsection number="38-1a-202(3)(a)">
The division shall make rules and develop procedures for:<subsection number="38-1a-202(3)(a)(i)">
the division to oversee and enforce this chapter and <xref depth="1" refnumber="38-1b" start="1">Chapter 1b, Government Construction Projects</xref>;</subsection><subsection number="38-1a-202(3)(a)(ii)">
the designated agent to administer this chapter and <xref depth="1" refnumber="38-1b" start="1">Chapter 1b, Government Construction Projects</xref>; and</subsection><subsection number="38-1a-202(3)(a)(iii)">
the form of submission of a filing by alternate means, which may include procedures for rejecting an illegible or incomplete filing.</subsection></subsection><subsection number="38-1a-202(3)(b)">
If this chapter directs or authorizes the division to make a rule or adopt a procedure to implement the provisions of this chapter or <xref depth="1" refnumber="38-1b" start="1">Chapter 1b, Government Construction Projects</xref>, the division shall make the rule or adopt the procedure in accordance with <xref depth="1" refnumber="63G-3" start="0">Title 63G, Chapter 3, Utah Administrative Rulemaking Act</xref>.</subsection></subsection><subsection number="38-1a-202(4)"><subsection number="38-1a-202(4)(a)">
The designated agent shall archive computer data files at least semiannually for auditing purposes.</subsection><subsection number="38-1a-202(4)(b)">
The division shall make rules to allow the designated agent to periodically archive projects from the registry.</subsection><subsection number="38-1a-202(4)(c)">
The designated agent may not archive a project earlier than:<subsection number="38-1a-202(4)(c)(i)">
one year after the day on which a notice of completion is filed for a construction project;</subsection><subsection number="38-1a-202(4)(c)(ii)">
if no notice of completion is filed, two years after the last filing activity for a project; or</subsection><subsection number="38-1a-202(4)(c)(iii)">
one year after the day on which a contestable notice is cancelled under Section <xref depth="3" refnumber="38-1a-307" start="0">38-1a-307</xref>.</subsection></subsection><subsection number="38-1a-202(4)(d)">
The division may audit the designated agent's administration of the registry as often as the division considers necessary.</subsection></subsection><subsection number="38-1a-202(5)">
The designated agent shall carry errors and omissions insurance in the amounts that the division establishes by rule.</subsection><subsection number="38-1a-202(6)"><subsection number="38-1a-202(6)(a)">
The designated agent shall make reasonable efforts to assure the accurate entry into the registry of information provided by alternate means.</subsection><subsection number="38-1a-202(6)(b)">
The designated agent shall meet or exceed standards established by the division for the accuracy of data entry for information on documents filed by alternate means.</subsection></subsection><subsection number="38-1a-202(7)">
The designated agent is not liable for the correctness of the information contained in a document filed by alternate means which the registered agent enters into the database.</subsection></section><section number="38-1a-203"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Filings with the registry.</catchline><subsection number="38-1a-203(1)">
The division and the designated agent need not determine the timeliness of any notice before filing the notice in the registry.</subsection><subsection number="38-1a-203(2)">
A notice filed by a third party on behalf of another is considered to be filed by the person on whose behalf the notice is filed.</subsection><subsection number="38-1a-203(3)">
A person filing a notice of commencement, preliminary notice, or notice of completion is responsible for verifying the accuracy of information entered into the registry, whether the person files electronically, by alternate means, or through a third party.</subsection><subsection number="38-1a-203(4)">
Each notice or other document submitted for inclusion in the registry and for which this chapter does not specify information required to be included in the notice or other document shall contain:
<subsection number="38-1a-203(4)(a)">
the name of the county in which the project property to which the notice or other document applies is located;</subsection><subsection number="38-1a-203(4)(b)">
for a private project:<subsection number="38-1a-203(4)(b)(i)">
the tax parcel identification number of each parcel included in the project property; or</subsection><subsection number="38-1a-203(4)(b)(ii)">
the number of the building permit for the construction project on the project property; and</subsection></subsection><subsection number="38-1a-203(4)(c)">
for a government project, the government project-identifying information.</subsection></subsection></section><section number="38-1a-204"><histories><history>Amended by Chapter <modchap sess="2013GS">464</modchap>, 2013 General Session</history><modyear>2013</modyear></histories><catchline>Notification of filings with the registry.</catchline><subsection number="38-1a-204(1)">
The designated agent shall provide notification of the filing of a required notice relating to an anticipated improvement or construction project to:
<subsection number="38-1a-204(1)(a)">
the person filing the required notice, unless the person indicates to the division or designated agent that the person does not want to receive notification; and</subsection><subsection number="38-1a-204(1)(b)">
each person that requests notification of the filing of a required notice for that anticipated improvement or construction project.</subsection></subsection><subsection number="38-1a-204(2)"><subsection number="38-1a-204(2)(a)">
A person may request the designated agent to provide the person notification of the filing of a required notice for any anticipated improvement or construction project.</subsection><subsection number="38-1a-204(2)(b)">
A person requesting notification under Subsection <xref depth="4" refnumber="38-1a-204(2)(a)" start="0">(2)(a)</xref> is responsible:<subsection number="38-1a-204(2)(b)(i)">
to provide an email address, mailing address, or telefax number to which notification may be sent; and</subsection><subsection number="38-1a-204(2)(b)(ii)">
for the accuracy of the email address, mailing address, or telefax number.</subsection></subsection><subsection number="38-1a-204(2)(c)">
A person is considered to have requested notification under Subsection <xref depth="4" refnumber="38-1a-204(2)(a)" start="0">(2)(a)</xref> if the person files, with respect to the same anticipated improvement or construction project that relates to the required notice that is the subject of the notification:<subsection number="38-1a-204(2)(c)(i)">
a notice of preconstruction service;</subsection><subsection number="38-1a-204(2)(c)(ii)">
a notice of commencement;</subsection><subsection number="38-1a-204(2)(c)(iii)">
a preliminary notice;</subsection><subsection number="38-1a-204(2)(c)(iv)">
a notice of construction loan; or</subsection><subsection number="38-1a-204(2)(c)(v)">
a notice of completion.</subsection></subsection></subsection><subsection number="38-1a-204(3)">
The designated agent fulfills the notification requirement under Subsection <xref depth="4" refnumber="38-1a-204(1)" start="0">(1)</xref> by sending the notification to the email address, mailing address, or telefax number that the person provides to the designated agent, whether or not the person actually receives the notification.</subsection></section><section number="38-1a-205"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Building permit -- Transmission to registry -- Posting at project site.</catchline><subsection number="38-1a-205(1)"><subsection number="38-1a-205(1)(a)">
A county, city, or town issuing a building permit for a private project:<subsection number="38-1a-205(1)(a)(i)">
shall, no later than 15 days after issuing the permit, input the building permit application and transmit the building permit information to the registry electronically by way of the Internet or computer modem or by any other means; and</subsection><subsection number="38-1a-205(1)(a)(ii)">
may collect a building permit fee related to the issuance of the building permit, but may not spend or otherwise use the building permit fee until the county, city, or town complies with Subsection <xref depth="4" refnumber="38-1a-205(1)(a)(i)" start="0">(1)(a)(i)</xref> with respect to the building permit for which the fee is charged.</subsection></subsection><subsection number="38-1a-205(1)(b)">
The person to whom a building permit, filed under Subsection <xref depth="4" refnumber="38-1a-205(1)(a)" start="0">(1)(a)</xref>, is issued is responsible for the accuracy of the information in the building permit.</subsection><subsection number="38-1a-205(1)(c)">
For the purposes of classifying a record under <xref depth="1" refnumber="63G-2" start="0">Title 63G, Chapter 2, Government Records Access and Management Act</xref>, the division shall classify in the registry building permit information transmitted from a county, city, or town to the registry notwithstanding the classification of the building permit information by the county, city, or town.</subsection></subsection><subsection number="38-1a-205(2)">
At the time a building permit is obtained, each original contractor for construction service shall conspicuously post at the project site a copy of the building permit obtained for the project.</subsection></section><section number="38-1a-206"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Registry fees.</catchline><subsection number="38-1a-206(1)">
In accordance with the process required by Section <xref depth="3" refnumber="63J-1-504" start="0">63J-1-504</xref>, the division shall establish the fees for:
<subsection number="38-1a-206(1)(a)">
required notices, whether filed electronically or by alternate means;</subsection><subsection number="38-1a-206(1)(b)">
a request for notification under Section <xref depth="3" refnumber="38-1a-204" start="0">38-1a-204</xref>;</subsection><subsection number="38-1a-206(1)(c)">
providing notification of a required notice, whether electronically or by alternate means;</subsection><subsection number="38-1a-206(1)(d)">
a duplicate receipt of a filing; and</subsection><subsection number="38-1a-206(1)(e)">
account setup for a person who wishes to be billed periodically for filings with the registry.</subsection></subsection><subsection number="38-1a-206(2)">
The fees allowed under Subsection <xref depth="4" refnumber="38-1a-206(1)" start="0">(1)</xref> may not in the aggregate exceed the amount reasonably necessary to create and maintain the registry.</subsection><subsection number="38-1a-206(3)">
The fees established by the division may vary by method of filing if one form or means of filing is more costly to process than another form or means of filing.</subsection><subsection number="38-1a-206(4)">
The division may provide by contract that the designated agent may retain all fees collected by the designated agent, except that the designated agent shall remit to the division the cost of the division's oversight.</subsection><subsection number="38-1a-206(5)"><subsection number="38-1a-206(5)(a)">
A person who is delinquent on the payment of a fee established under this section may not file a notice with the registry.</subsection><subsection number="38-1a-206(5)(b)">
The division shall make a determination whether a person is delinquent on the payment of a fee for filing established under this section in accordance with <xref depth="1" refnumber="63G-4" start="0">Title 63G, Chapter 4, Administrative Procedures Act</xref>.</subsection><subsection number="38-1a-206(5)(c)">
Any order that the division issues in a proceeding described in Subsection <xref depth="4" refnumber="38-1a-206(5)(b)" start="0">(5)(b)</xref> may prescribe the method of that person's payment of fees for filing notices with the registry after issuance of the order.</subsection></subsection></section><section number="38-1a-207"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Registry classification.</catchline><subsection number="38-1a-207(1)">
The registry is classified as a public record under <xref depth="1" refnumber="63G-2" start="0">Title 63G, Chapter 2, Government Records Access and Management Act</xref>, unless the division classifies it otherwise.</subsection><subsection number="38-1a-207(2)">
A request for information submitted to the designated agent is not subject to <xref depth="1" refnumber="63G-2" start="0">Title 63G, Chapter 2, Government Records Access and Management Act</xref>.</subsection><subsection number="38-1a-207(3)">
A person desiring information contained in a public record in the registry shall request the information from the designated agent.</subsection><subsection number="38-1a-207(4)">
The designated agent may charge a commercially reasonable fee allowed by the designated agent's contract with the division for providing information under Subsection <xref depth="4" refnumber="38-1a-207(3)" start="0">(3)</xref>.</subsection><subsection number="38-1a-207(5)">
Notwithstanding <xref depth="1" refnumber="63G-2" start="0">Title 63G, Chapter 2, Government Records Access and Management Act</xref>, if information is available in a public record contained in the registry, a person may not request the information from the division.</subsection><subsection number="38-1a-207(6)"><subsection number="38-1a-207(6)(a)">
A person may request information that is not a public record contained in the registry from the division in accordance with <xref depth="1" refnumber="63G-2" start="0">Title 63G, Chapter 2, Government Records Access and Management Act</xref>.</subsection><subsection number="38-1a-207(6)(b)">
The division shall inform the designated agent of how to direct an inquiry made to the designated agent for information that is not a public record contained in the registry.</subsection></subsection></section><section number="38-1a-208"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Actions that are not adjudicative proceedings.</catchline><tab/>None of the following is an adjudicative proceeding under <xref depth="1" refnumber="63G-4" start="0">Title 63G, Chapter 4, Administrative Procedures Act</xref>:<subsection number="38-1a-208(1)">
the filing of a notice permitted or required by this chapter;</subsection><subsection number="38-1a-208(2)">
the rejection of a filing permitted or required by this chapter; or</subsection><subsection number="38-1a-208(3)">
other action by the designated agent in connection with a filing of any notice permitted or required by this chapter.</subsection></section><section number="38-1a-209"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Abuse of registry -- Penalty.</catchline><subsection number="38-1a-209(1)">
As used in this section, "third party" means an owner, an original contractor, a subcontractor, or any interested party.</subsection><subsection number="38-1a-209(2)">
A person abuses the registry if that person files a notice in the registry:
<subsection number="38-1a-209(2)(a)">
without a good faith basis for doing so;</subsection><subsection number="38-1a-209(2)(b)">
with the intent to exact more than is due from the owner or any other interested party; or</subsection><subsection number="38-1a-209(2)(c)">
to procure an unjustified advantage or benefit.</subsection></subsection><subsection number="38-1a-209(3)">
A person who abuses the registry as described in Subsection <xref depth="4" refnumber="38-1a-209(2)" start="0">(2)</xref> is liable to a third party who is affected by the notice for twice the amount of the actual damages incurred by the third party or $2,000, whichever is greater.</subsection></section><section number="38-1a-210"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Limitation of liability.</catchline><subsection number="38-1a-210(1)">
The state and the state's agencies, instrumentalities, political subdivisions, and an employee of a governmental entity are immune from suit for any injury resulting from the registry.</subsection><subsection number="38-1a-210(2)">
The designated agent and its principals, agents, and employees are not liable to any person for the accuracy, coherence, suitability, completeness, or legal effectiveness of information filed or searched in the registry if the designated agent:
<subsection number="38-1a-210(2)(a)">
develops and maintains the registry in compliance with reliability, availability, and security standards established by the division; and</subsection><subsection number="38-1a-210(2)(b)">
meets data entry accuracy standards established by the division under Subsection <xref depth="4" refnumber="38-1a-202(6)(b)" start="0">38-1a-202(6)(b)</xref>.</subsection></subsection><subsection number="38-1a-210(3)">
The designated agent and its principals, agents, and employees are not liable for their inability to perform obligations under this chapter to the extent performance of those obligations is prevented by:
<subsection number="38-1a-210(3)(a)">
a storm, earthquake, or other act of God;</subsection><subsection number="38-1a-210(3)(b)">
a fire;</subsection><subsection number="38-1a-210(3)(c)">
an accident;</subsection><subsection number="38-1a-210(3)(d)">
governmental interference; or</subsection><subsection number="38-1a-210(3)(e)">
any other event or cause beyond the designated agent's control.</subsection></subsection></section><section number="38-1a-211"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Limit on notice effect of document filing in the registry.</catchline><tab/>The filing of a document in the registry is not intended to give notice to all persons of the content of the document within the meaning of Section <xref depth="3" refnumber="57-3-102" start="0">57-3-102</xref> and does not constitute constructive notice of matters relating to real property to purchasers for value and without knowledge.
</section></part><part number="38-1a-3"><catchline>Provisions Applicable to Preconstruction Liens and Construction Liens</catchline><section number="38-1a-301"><histories><history>Amended by Chapter <modchap sess="2022GS">429</modchap>, 2022 General Session</history><modyear>2022</modyear></histories><catchline>Those entitled to lien -- What may be attached.</catchline><subsection number="38-1a-301(1)">
Except as provided in Section <xref depth="3" refnumber="38-11-107" start="0">38-11-107</xref>, a person who provides preconstruction service or construction work on or for a project property has a lien on the project property for the reasonable value of the preconstruction service or construction work, respectively, as provided in this chapter.</subsection><subsection number="38-1a-301(2)">
A person may claim a preconstruction lien and a separate construction lien on the same project property.</subsection><subsection number="38-1a-301(3)"><subsection number="38-1a-301(3)(a)">
A construction lien may include an amount claimed for a preconstruction service.</subsection><subsection number="38-1a-301(3)(b)">
A preconstruction lien may not include an amount claimed for construction work.</subsection></subsection><subsection number="38-1a-301(4)"><subsection number="38-1a-301(4)(a)">
A preconstruction or construction lien attaches only to the interest that the owner has in the project property that is the subject of the lien.</subsection><subsection number="38-1a-301(4)(b)">
If an owner possesses an interest in the project property that is less than fee simple, a preconstruction or construction lien attaches only to the lesser interest of the owner and does not attach to the fee simple interest.</subsection><subsection number="38-1a-301(4)(c)">
Notwithstanding Subsection <xref depth="4" refnumber="38-1a-301(4)(b)" start="0">(4)(b)</xref>, a preconstruction or construction lien may attach to the fee simple interest in the project property, if the person who provides preconstruction service or construction work can demonstrate that the preconstruction service or construction work:<subsection number="38-1a-301(4)(c)(i)">
was authorized by the person possessing the fee simple interest in the project property; and</subsection><subsection number="38-1a-301(4)(c)(ii)">
provides a substantial benefit to the person who owns the fee simple interest beyond the time period of the lesser interest possessed by the owner.</subsection></subsection></subsection></section><section number="38-1a-302"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Land covered by lien -- Multiple lots occupied by improvement -- What a lien attaches to.</catchline><subsection number="38-1a-302(1)">
A preconstruction or construction lien extends to and covers as much of the land on which the improvement is made as necessary for the convenient use and occupation of the land.</subsection><subsection number="38-1a-302(2)">
If an improvement occupies two or more lots or other subdivisions of land, the lots or subdivisions are considered as one for the purposes of this chapter.</subsection><subsection number="38-1a-302(3)">
A preconstruction or construction lien attaches to all franchises, privileges, appurtenances, machinery, and fixtures pertaining to or used in connection with the improvement.</subsection></section><section number="38-1a-303"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Limits on attachment, garnishment, and execution levy -- Subcontractor lien not affected by payments, debts, offsets, and counterclaims involving other parties.</catchline><subsection number="38-1a-303(1)">
An assignment, attachment, or garnishment of or encumbrance or execution levy on money that an owner owes to an original contractor is not valid as against a subcontractor's preconstruction or construction lien.</subsection><subsection number="38-1a-303(2)">
An assignment, attachment, or garnishment of or encumbrance or execution levy on money that an original contractor owes to a subcontractor is not valid as against a lien of a laborer employed by the day or piece.</subsection><subsection number="38-1a-303(3)">
The preconstruction or construction lien of a subcontractor may not be diminished, impaired, or otherwise affected by:
<subsection number="38-1a-303(3)(a)">
a payment, whether in cash or in-kind, to the original contractor or another subcontractor;</subsection><subsection number="38-1a-303(3)(b)">
a debt owed by the original contractor to the owner;</subsection><subsection number="38-1a-303(3)(c)">
a debt owed by another subcontractor to the original contractor or to a third subcontractor; or</subsection><subsection number="38-1a-303(3)(d)">
an offset or counterclaim in favor of the owner against the original contractor, or in favor of the original contractor against another subcontractor, or in favor of another subcontractor against a third subcontractor.</subsection></subsection></section><section number="38-1a-304"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Liens on multiple properties in one claim.</catchline><subsection number="38-1a-304(1)">
A claimant may claim a preconstruction or construction lien against two or more improvements owned by the same person.</subsection><subsection number="38-1a-304(2)">
If a claimant claims a preconstruction or construction lien against two or more improvements owned by the same person, the claimant shall designate the amount claimed to be due on each of the improvements.</subsection></section><section number="38-1a-305"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Payments applied first to preconstruction lien.</catchline><tab/>Unless an agreement waiving or limiting a right under a preconstruction or construction lien expressly provides that a payment is required to be applied to a specific lien, mortgage, or encumbrance, a payment to a person claiming both a preconstruction lien and a construction lien shall be applied first to the preconstruction lien until paid in full.
</section><section number="38-1a-306"><histories><history>Amended by Chapter <modchap sess="2013GS">464</modchap>, 2013 General Session</history><modyear>2013</modyear></histories><catchline>Substantial compliance.</catchline><subsection number="38-1a-306(1)">
Substantial compliance with the requirements of this chapter is sufficient to claim, as applicable, a preconstruction lien or a construction lien.</subsection><subsection number="38-1a-306(2)">
Subsection <xref depth="4" refnumber="38-1a-306(1)" start="0">(1)</xref> may not be construed to excuse compliance with or affect the requirement to file:
<subsection number="38-1a-306(2)(a)">
a notice of preconstruction service as provided in Section <xref depth="3" refnumber="38-1a-401" start="0">38-1a-401</xref> in order to claim a preconstruction lien; or</subsection><subsection number="38-1a-306(2)(b)">
a preliminary notice as provided in Section <xref depth="3" refnumber="38-1a-501" start="0">38-1a-501</xref> in order to claim a construction lien.</subsection></subsection></section><section number="38-1a-307"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Contesting certain notices.</catchline><subsection number="38-1a-307(1)">
A contesting person who believes that a contestable notice lacks proper basis and is therefore invalid may request from the person who filed the notice evidence establishing the validity of the notice.</subsection><subsection number="38-1a-307(2)">
Within 10 days after receiving a request under Subsection <xref depth="4" refnumber="38-1a-307(1)" start="0">(1)</xref>, the person who filed the contestable notice shall provide the requesting person evidence that the notice is valid.</subsection><subsection number="38-1a-307(3)">
If the person who filed the notice does not provide timely evidence of the validity of the contestable notice, the person who filed the notice shall immediately cancel the notice from the registry in the manner prescribed by the division by rule.</subsection></section><section number="38-1a-308"><histories><history>Amended by Chapter <modchap sess="2026GS">310</modchap>, 2026 General Session</history><modyear>2026</modyear></histories><catchline>Intentional submission of excessive lien notice -- Criminal and civil liability.</catchline><subsection number="38-1a-308(1)">As used in this section, "residential project" means a project on real property:<subsection number="38-1a-308(1)(a)">for which a preconstruction service or construction work is provided; and</subsection><subsection number="38-1a-308(1)(b)">that consists of:<subsection number="38-1a-308(1)(b)(i)">one single-family residence; or</subsection><subsection number="38-1a-308(1)(b)(ii)">one multi-family residence that contains no more than four units.</subsection></subsection></subsection><subsection number="38-1a-308(2)">A person is guilty of a class B misdemeanor if:<subsection number="38-1a-308(2)(a)">the person intentionally submits for recording a notice of preconstruction lien or notice of construction lien against any property containing a greater demand than the sum due; and</subsection><subsection number="38-1a-308(2)(b)">by submitting the notice, the person intends:<subsection number="38-1a-308(2)(b)(i)">to cloud the title;</subsection><subsection number="38-1a-308(2)(b)(ii)">to exact from the owner or person liable by means of the excessive notice of preconstruction or construction lien more than is due; or</subsection><subsection number="38-1a-308(2)(b)(iii)">to procure any unjustified advantage or benefit.</subsection></subsection></subsection><subsection number="38-1a-308(3)"><subsection number="38-1a-308(3)(a)">As used in this Subsection <xref depth="4" refnumber="38-1a-308(3)">(3)</xref>, "third party" means an owner, original contractor, or subcontractor.</subsection><subsection number="38-1a-308(3)(b)">In addition to any criminal penalty under Subsection <xref depth="4" refnumber="38-1a-308(2)">(2)</xref>, a person who submits a notice of preconstruction lien or notice of construction lien as described in Subsection <xref depth="4" refnumber="38-1a-308(2)">(2)</xref> is liable to a third party who is affected by the notice of preconstruction lien or the notice of construction lien for twice the amount by which the lien notice exceeds the amount actually due or the actual damages incurred by the owner, original contractor, or subcontractor, whichever is greater.</subsection></subsection><subsection number="38-1a-308(4)">The parties to a claim described in Subsection <xref depth="4" refnumber="38-1a-308(3)(b)">(3)(b)</xref> who agree to arbitrate the claim shall arbitrate in accordance with Subsections <xref depth="4" refnumber="38-1a-308(5)">(5)</xref> through <xref depth="4" refnumber="38-1a-308(15)">(15)</xref> if the notice of preconstruction lien, or the notice of construction lien, that is the subject of the claim is:<subsection number="38-1a-308(4)(a)">for a residential project; and</subsection><subsection number="38-1a-308(4)(b)">for $50,000 or less.</subsection></subsection><subsection number="38-1a-308(5)"><subsection number="38-1a-308(5)(a)">Unless otherwise agreed to by the parties, a claim that is submitted to arbitration under this section shall be resolved by a single arbitrator.</subsection><subsection number="38-1a-308(5)(b)">All parties shall agree on the single arbitrator described in Subsection <xref depth="4" refnumber="38-1a-308(5)(a)">(5)(a)</xref> within 60 days after the day on which an answer is filed.</subsection><subsection number="38-1a-308(5)(c)">If the parties are unable to agree on a single arbitrator as required under Subsection <xref depth="4" refnumber="38-1a-308(5)(b)">(5)(b)</xref>, the parties shall select a panel of three arbitrators.</subsection><subsection number="38-1a-308(5)(d)">If the parties select a panel of three arbitrators under Subsection <xref depth="4" refnumber="38-1a-308(5)(c)">(5)(c)</xref>:<subsection number="38-1a-308(5)(d)(i)">each side shall select one arbitrator; and</subsection><subsection number="38-1a-308(5)(d)(ii)">the arbitrators selected under Subsection <xref depth="4" refnumber="38-1a-308(5)(d)(i)">(5)(d)(i)</xref> shall select one additional arbitrator to be included in the panel.</subsection></subsection></subsection><subsection number="38-1a-308(6)">Unless otherwise agreed to in writing:<subsection number="38-1a-308(6)(a)">each party shall pay an equal share of the fees and costs of the arbitrator selected under Subsection <xref depth="4" refnumber="38-1a-308(5)(b)">(5)(b)</xref>; or</subsection><subsection number="38-1a-308(6)(b)">if an arbitration panel is selected under Subsection <xref depth="4" refnumber="38-1a-308(5)(d)">(5)(d)</xref>:<subsection number="38-1a-308(6)(b)(i)">each party shall pay the fees and costs of that party's selected arbitrator; and</subsection><subsection number="38-1a-308(6)(b)(ii)">each party shall pay an equal share of the fees and costs of the arbitrator selected under Subsection <xref depth="4" refnumber="38-1a-308(5)(d)(ii)">(5)(d)(ii)</xref>.</subsection></subsection></subsection><subsection number="38-1a-308(7)">Except as otherwise provided in this section or otherwise agreed to by the parties, an arbitration proceeding conducted under this section shall be governed by Title 78B, Chapter 11, Utah Uniform Arbitration Act.</subsection><subsection number="38-1a-308(8)"><subsection number="38-1a-308(8)(a)">Subject to the provisions of this section, the Utah Rules of Civil Procedure and the Utah Rules of Evidence shall apply to an arbitration proceeding under this section.</subsection><subsection number="38-1a-308(8)(b)">The Utah Rules of Civil Procedure and the Utah Rules of Evidence shall be applied liberally with the intent of resolving the claim in a timely and cost-efficient manner.</subsection><subsection number="38-1a-308(8)(c)">Subject to the provisions of this section, the parties shall conduct discovery in accordance with Rules 26 through 37 of the Utah Rules of Civil Procedure.</subsection><subsection number="38-1a-308(8)(d)">Unless otherwise agreed to by the parties or ordered by the court, discovery in an arbitration proceeding under this section shall be limited to the discovery available in a tier 1 case under Rule 26 of the Utah Rules of Civil Procedure.</subsection></subsection><subsection number="38-1a-308(9)">A written decision by a single arbitrator or by a majority of the arbitration panel shall constitute a final decision.</subsection><subsection number="38-1a-308(10)">An arbitration award issued under this section:<subsection number="38-1a-308(10)(a)">shall be the final resolution of all excessive notice claims described in Subsection <xref depth="4" refnumber="38-1a-308(3)(b)">(3)(b)</xref> that are:<subsection number="38-1a-308(10)(a)(i)">between the parties;</subsection><subsection number="38-1a-308(10)(a)(ii)">for a residential project; and</subsection><subsection number="38-1a-308(10)(a)(iii)">for $50,000 or less; and</subsection></subsection><subsection number="38-1a-308(10)(b)">may be reduced to judgment by the court upon motion and notice, unless:<subsection number="38-1a-308(10)(b)(i)">any party, within 20 days after the day on which the arbitration award is served, files a notice requesting a trial de novo in a court with jurisdiction under <xref depth="3" refnumber="Title 78A, Judiciary and Judicial Administration">Title 78A, Judiciary and Judicial Administration</xref>; or</subsection><subsection number="38-1a-308(10)(b)(ii)">the arbitration award has been satisfied.</subsection></subsection></subsection><subsection number="38-1a-308(11)"><subsection number="38-1a-308(11)(a)">Upon filing a notice requesting a trial de novo under Subsection <xref depth="4" refnumber="38-1a-308(10)(b)(i)">(10)(b)(i)</xref>:<subsection number="38-1a-308(11)(a)(i)">unless otherwise stipulated to by the parties or ordered by the court, the parties are allowed an additional 60 days for discovery; and</subsection><subsection number="38-1a-308(11)(a)(ii)">the claim shall proceed through litigation in accordance with the Utah Rules of Civil Procedure and the Utah Rules of Evidence.</subsection></subsection><subsection number="38-1a-308(11)(b)">The additional discovery time described in Subsection <xref depth="4" refnumber="38-1a-308(11)(a)(i)">(11)(a)(i)</xref> shall run from the day on which the notice requesting a trial de novo is filed.</subsection></subsection><subsection number="38-1a-308(12)">If the plaintiff, as the moving party in a trial de novo requested under Subsection <xref depth="4" refnumber="38-1a-308(10)(b)(i)">(10)(b)(i)</xref>, does not obtain a verdict that is at least 10% greater than the arbitration award, the plaintiff is responsible for all of the nonmoving party's costs, including expert witness fees.</subsection><subsection number="38-1a-308(13)">If a defendant, as the moving party in a trial de novo requested under Subsection <xref depth="4" refnumber="38-1a-308(10)(b)(i)">(10)(b)(i)</xref>, does not obtain a verdict that is at least 10% less than the arbitration award, the defendant is responsible for all of the nonmoving party's costs, including expert witness fees.</subsection><subsection number="38-1a-308(14)">Upon a motion of the nonmoving party, the court may award reasonable attorney fees to the nonmoving party if the court determines that the moving party requested a trial de novo to harass, cause unreasonable delay, needlessly increase the cost of litigation, or abuse the judicial process.</subsection><subsection number="38-1a-308(15)">All arbitration awards issued under this section shall bear postjudgment interest in accordance with Section <xref depth="3" refnumber="15-1-4">15-1-4</xref>.</subsection></section><section number="38-1a-309"><histories><history>Amended by Chapter <modchap sess="2017GS">373</modchap>, 2017 General Session</history><modyear>2017</modyear></histories><catchline>Interest rate -- Preconstruction service or construction contract -- Lien.</catchline><subsection number="38-1a-309(1)">
Subject to Subsection <xref depth="4" refnumber="38-1a-309(2)" start="0">(2)</xref>, the interest rate that applies to a lawful contract for preconstruction service or construction work on or for a project property, or to a lien claimed under this chapter against the project property, is, unless otherwise provided in the lawful contract, the rate described in Subsection <xref depth="4" refnumber="15-1-1(2)" start="0">15-1-1(2)</xref>.</subsection><subsection number="38-1a-309(2)">
If a person that claims a lien against project property under this chapter is not in privity of contract with the owner or owner-builder, the interest rate that applies to the person's lien may not exceed the rate described in Subsection <xref depth="4" refnumber="15-1-1(2)" start="0">15-1-1(2)</xref>.</subsection></section></part><part number="38-1a-4"><catchline>Preconstruction Lien Provisions</catchline><section number="38-1a-401"><histories><history>Amended by Chapter <modchap sess="2013GS">464</modchap>, 2013 General Session</history><modyear>2013</modyear></histories><catchline>Notice of preconstruction service.</catchline><subsection number="38-1a-401(1)"><subsection number="38-1a-401(1)(a)">
A person that desires to claim a preconstruction lien on real property shall file a notice of preconstruction service with the registry no later than 20 days after the person commences providing preconstruction service for the anticipated improvement on the real property.</subsection><subsection number="38-1a-401(1)(b)">
A person that fails to file a timely notice of preconstruction service as required in this section may not claim a valid preconstruction lien.</subsection><subsection number="38-1a-401(1)(c)">
A timely filed notice of preconstruction service is effective as to each preconstruction service that the person filing the notice provides for the anticipated improvement under a single original contract, including preconstruction service that the person provides to more than one supervising subcontractor under that original contract.</subsection><subsection number="38-1a-401(1)(d)">
A notice of preconstruction service filed for preconstruction service provided or to be provided under an original contract for an anticipated improvement on real property is not valid for preconstruction service provided or to be provided under a separate original contract for an anticipated improvement on the same real property.</subsection><subsection number="38-1a-401(1)(e)">
A notice of preconstruction service that is timely filed with the database with respect to an anticipated improvement is considered to have been filed at the same time as the earliest timely filed notice of preconstruction service for that anticipated improvement.</subsection><subsection number="38-1a-401(1)(f)">
A notice of preconstruction service shall include:<subsection number="38-1a-401(1)(f)(i)">
the name, address, telephone number, and email address of the person providing the preconstruction service;</subsection><subsection number="38-1a-401(1)(f)(ii)">
the name, address, telephone number, and email address of the person that employed the person providing the preconstruction service;</subsection><subsection number="38-1a-401(1)(f)(iii)">
a general description of the preconstruction service the person provided or will provide;</subsection><subsection number="38-1a-401(1)(f)(iv)">
the name of the record or reputed owner;</subsection><subsection number="38-1a-401(1)(f)(v)">
the name of the county in which the property on which the anticipated improvement will occur is located;</subsection><subsection number="38-1a-401(1)(f)(vi)"><subsection number="38-1a-401(1)(f)(vi)(A)">
the tax parcel identification number of each parcel included in that property; or</subsection><subsection number="38-1a-401(1)(f)(vi)(B)">
the entry number of a previously filed notice of preconstruction service that includes the tax parcel identification number of each parcel included in that property; and</subsection></subsection><subsection number="38-1a-401(1)(f)(vii)">
a statement that the person filing the notice intends to claim a preconstruction lien if the person is not paid for the preconstruction service the person provides.</subsection></subsection><subsection number="38-1a-401(1)(g)"><subsection number="38-1a-401(1)(g)(i)">
A claimant who is an original contractor or a supervisory subcontractor may include in a notice of preconstruction service the name, address, and telephone number of each subcontractor who is under contract with the claimant to provide preconstruction service that the claimant is under contract to provide.</subsection><subsection number="38-1a-401(1)(g)(ii)">
The inclusion of a subcontractor in a notice of preconstruction service filed by another claimant is not a substitute for the subcontractor's own submission of a notice of preconstruction service.</subsection></subsection></subsection><subsection number="38-1a-401(2)">
The burden is on the person filing the notice of preconstruction service to prove that the person has substantially complied with the requirements of this section.</subsection><subsection number="38-1a-401(3)"><subsection number="38-1a-401(3)(a)">
Subject to Subsection <xref depth="4" refnumber="38-1a-401(3)(b)" start="0">(3)(b)</xref>, a person required by this section to file a notice of preconstruction service is required to give only one notice for each anticipated improvement.</subsection><subsection number="38-1a-401(3)(b)">
A person that provides preconstruction service under more than one original contract for the same anticipated improvement and desires to claim a preconstruction lien for preconstruction service provided under each original contract shall file a separate notice of preconstruction service for preconstruction service provided under each original contract.</subsection></subsection><subsection number="38-1a-401(4)">
A person filing a notice of preconstruction service by alternate means is responsible for verifying and changing any incorrect information in the notice of preconstruction service before the expiration of the period during which the notice is required to be filed.</subsection></section><section number="38-1a-402"><histories><history>Amended by Chapter <modchap sess="2013GS">464</modchap>, 2013 General Session</history><modyear>2013</modyear></histories><catchline>Notice of preconstruction lien -- Requirements.</catchline><subsection number="38-1a-402(1)">
Within 90 days after completing a preconstruction service for which a claimant is not paid in full, a claimant who desires to claim a preconstruction lien shall submit for recording with each applicable county recorder a notice of preconstruction lien.</subsection><subsection number="38-1a-402(2)">
A claimant who fails to submit a notice of preconstruction lien as provided in Subsection <xref depth="4" refnumber="38-1a-402(1)" start="0">(1)</xref> may not claim a preconstruction lien.</subsection><subsection number="38-1a-402(3)"><subsection number="38-1a-402(3)(a)">
A notice of preconstruction service lien shall include:<subsection number="38-1a-402(3)(a)(i)">
the claimant's name, mailing address, and telephone number;</subsection><subsection number="38-1a-402(3)(a)(ii)">
a statement that the claimant claims a preconstruction lien;</subsection><subsection number="38-1a-402(3)(a)(iii)">
the date the claimant's notice of preconstruction service was filed;</subsection><subsection number="38-1a-402(3)(a)(iv)">
the name of the person that employed the claimant;</subsection><subsection number="38-1a-402(3)(a)(v)">
a general description of the preconstruction service provided by the claimant;</subsection><subsection number="38-1a-402(3)(a)(vi)">
the date that the claimant last provided preconstruction service;</subsection><subsection number="38-1a-402(3)(a)(vii)">
the name, if known, of the reputed owner or, if not known, the name of the record owner;</subsection><subsection number="38-1a-402(3)(a)(viii)">
a description of the project property sufficient for identification;</subsection><subsection number="38-1a-402(3)(a)(ix)">
the principal amount, excluding interest, costs, and attorney fees, claimed by the claimant;</subsection><subsection number="38-1a-402(3)(a)(x)">
the claimant's signature or the signature of the claimant's authorized agent;</subsection><subsection number="38-1a-402(3)(a)(xi)">
an acknowledgment or certificate as required under <xref depth="1" refnumber="57-3" start="0">Title 57, Chapter 3, Recording of Documents</xref>; and</subsection><subsection number="38-1a-402(3)(a)(xii)">
if the lien is against an owner-occupied residence, as defined in Section <xref depth="3" refnumber="38-11-102" start="0">38-11-102</xref>, a statement meeting the requirements that the division has established by rule, describing the steps the owner of the owner-occupied residence may take to require a claimant to remove the lien as provided in Section <xref depth="3" refnumber="38-11-107" start="0">38-11-107</xref>.</subsection></subsection><subsection number="38-1a-402(3)(b)"><subsection number="38-1a-402(3)(b)(i)">
A claimant who is an original contractor or a supervising subcontractor may include in a notice of preconstruction lien the name, address, and telephone number of each subcontractor who is under contract with the claimant to provide preconstruction service that the claimant is under contract to provide.</subsection><subsection number="38-1a-402(3)(b)(ii)">
The inclusion of a subcontractor in a notice of preconstruction lien filed by another claimant is not a substitute for the subcontractor's own submission of a notice of preconstruction lien.</subsection></subsection></subsection><subsection number="38-1a-402(4)"><subsection number="38-1a-402(4)(a)">
A county recorder:<subsection number="38-1a-402(4)(a)(i)">
shall record each notice of preconstruction lien in an index maintained for that purpose; and</subsection><subsection number="38-1a-402(4)(a)(ii)">
need not verify that a valid notice of preconstruction service is filed with respect to the claimed preconstruction lien.</subsection></subsection><subsection number="38-1a-402(4)(b)">
All persons are considered to have notice of a notice of preconstruction lien from the time it is recorded.</subsection></subsection><subsection number="38-1a-402(5)"><subsection number="38-1a-402(5)(a)">
Within 30 days after a claimant's notice of preconstruction lien is recorded, the claimant shall send by certified mail a copy of the notice to the reputed or record owner.</subsection><subsection number="38-1a-402(5)(b)">
If the record owner's address is not readily available to the claimant, the claimant may mail a copy of the notice to the owner's last-known address as it appears on the last completed assessment roll of the county in which the property is located.</subsection><subsection number="38-1a-402(5)(c)">
A claimant's failure to mail a copy of the notice as required in this Subsection <xref depth="4" refnumber="38-1a-402(5)" start="0">(5)</xref> precludes the claimant from being awarded costs and attorney fees against the reputed or record owner in an action to enforce the lien.</subsection></subsection><subsection number="38-1a-402(6)">
Nothing in this section may be construed to prohibit a claimant from recording a notice of preconstruction lien before completing the preconstruction service the claimant contracted to provide.</subsection></section><section number="38-1a-403"><histories><history>Amended by Chapter <modchap sess="2013GS">464</modchap>, 2013 General Session</history><modyear>2013</modyear></histories><catchline>Effective time and priority of preconstruction lien -- Subordination to bona fide loan.</catchline><subsection number="38-1a-403(1)">
Except as otherwise provided in this chapter, a preconstruction lien:
<subsection number="38-1a-403(1)(a)">
relates back to and takes effect as of the time of filing of the earliest timely filed notice of preconstruction service under Section <xref depth="3" refnumber="38-1a-401" start="0">38-1a-401</xref> for the anticipated improvement for which the preconstruction lien is claimed; and</subsection><subsection number="38-1a-403(1)(b)">
has priority over:<subsection number="38-1a-403(1)(b)(i)">
any lien, mortgage, or other encumbrance that attaches after the earliest timely filed notice of preconstruction service is filed; and</subsection><subsection number="38-1a-403(1)(b)(ii)">
any lien, mortgage, or other encumbrance of which the claimant had no notice and that was unrecorded at the time the earliest timely filed notice of preconstruction service is filed.</subsection></subsection></subsection><subsection number="38-1a-403(2)">
A preconstruction lien is subordinate to an interest securing a bona fide loan if and to the extent that the lien covers preconstruction service provided after the interest securing a bona fide loan is recorded.</subsection></section><section number="38-1a-404"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>When preconstruction service considered complete.</catchline><tab/>Preconstruction service is considered complete for any project, project phase, or bid package as of the date that construction work for that project, project phase, or bid package, respectively, commences.
</section><section number="38-1a-405"><histories><history>Enacted by Chapter <modchap sess="2013GS">464</modchap>, 2013 General Session</history><modyear>2013</modyear></histories><catchline>Preconstruction liens on equal footing.</catchline><subsection number="38-1a-405(1)">
Each preconstruction lien on a project property is on equal footing with every other preconstruction lien on the project property, regardless of:
<subsection number="38-1a-405(1)(a)">
when the claimant submitted the claimant's notice of preconstruction service for recording;</subsection><subsection number="38-1a-405(1)(b)">
when the claimant submitted the claimant's notice of preconstruction lien for recording; or</subsection><subsection number="38-1a-405(1)(c)">
when the preconstruction service related to the lien occurs.</subsection></subsection><subsection number="38-1a-405(2)">
Subsection <xref depth="4" refnumber="38-1a-405(1)" start="0">(1)</xref> does not affect the priority of a construction lender's mortgage or trust deed, as established under this chapter.</subsection></section></part><part number="38-1a-5"><catchline>Construction Lien Provisions</catchline><section number="38-1a-501"><histories><history>Amended by Chapter <modchap sess="2014GS">293</modchap>, 2014 General Session</history><modyear>2014</modyear></histories><catchline>Preliminary notice.</catchline><subsection number="38-1a-501(1)"><subsection number="38-1a-501(1)(a)">
A person who desires to claim a construction lien on real property shall file a preliminary notice with the registry no later than 20 days after the day on which the person commences providing construction work on the real property.</subsection><subsection number="38-1a-501(1)(b)">
Subject to Subsection <xref depth="4" refnumber="38-1a-501(1)(c)" start="0">(1)(c)</xref>, a preliminary notice is effective as to all construction work that the person filing the notice provides to the construction project under a single original contract, including construction work that the person provides to more than one supervisory subcontractor under that original contract.</subsection><subsection number="38-1a-501(1)(c)"><subsection number="38-1a-501(1)(c)(i)">
A person who desires to claim a construction lien on real property but fails to file a timely preliminary notice within the period specified in Subsection <xref depth="4" refnumber="38-1a-501(1)(a)" start="0">(1)(a)</xref> may, subject to Subsection <xref depth="4" refnumber="38-1a-501(1)(d)" start="0">(1)(d)</xref>, file a preliminary notice with the registry after the period specified in Subsection <xref depth="4" refnumber="38-1a-501(1)(a)" start="0">(1)(a)</xref>.</subsection><subsection number="38-1a-501(1)(c)(ii)">
A person who files a preliminary notice under Subsection <xref depth="4" refnumber="38-1a-501(1)(c)(i)" start="0">(1)(c)(i)</xref> may not claim a construction lien for construction work the person provides to the construction project before the date that is five days after the preliminary notice is filed.</subsection></subsection><subsection number="38-1a-501(1)(d)">
Notwithstanding Subsections <xref depth="4" refnumber="38-1a-501(1)(a)" start="0">(1)(a)</xref> and <xref depth="4" refnumber="38-1a-501(1)(c)" start="0">(c)</xref>, a preliminary notice has no effect if it is filed more than 10 days after the filing of a notice of completion under Section <xref depth="3" refnumber="38-1a-507" start="0">38-1a-507</xref> for the construction project for which the preliminary notice is filed.</subsection><subsection number="38-1a-501(1)(e)">
A person who fails to file a preliminary notice as required in this section may not claim a construction lien.</subsection><subsection number="38-1a-501(1)(f)">
A preliminary notice that is filed with the registry as provided in this section is considered to be filed at the time of the first preliminary notice filing.</subsection><subsection number="38-1a-501(1)(g)">
If a preliminary notice filed with the registry includes the tax parcel identification number of a parcel not previously associated in the registry with a construction project, the designated agent shall promptly notify the person who filed the preliminary notice that:<subsection number="38-1a-501(1)(g)(i)">
the preliminary notice includes a tax parcel identification number of a parcel not previously associated in the registry with a construction project; and</subsection><subsection number="38-1a-501(1)(g)(ii)">
the likely explanation is that:
<subsection number="38-1a-501(1)(g)(ii)(A)">
the preliminary notice is the first filing for the project; or</subsection><subsection number="38-1a-501(1)(g)(ii)(B)">
the tax parcel identification number is incorrectly stated in the preliminary notice.</subsection></subsection></subsection><subsection number="38-1a-501(1)(h)">
A preliminary notice shall include:<subsection number="38-1a-501(1)(h)(i)">
the name, address, telephone number, and email address of the person providing the construction work for which the preliminary notice is filed;</subsection><subsection number="38-1a-501(1)(h)(ii)">
the name and address of the person who contracted with the claimant for the construction work;</subsection><subsection number="38-1a-501(1)(h)(iii)">
the name of the record or reputed owner;</subsection><subsection number="38-1a-501(1)(h)(iv)">
the name of the original contractor for construction work under which the claimant is providing or will provide construction work;</subsection><subsection number="38-1a-501(1)(h)(v)">
the address of the project property or a description of the location of the project;</subsection><subsection number="38-1a-501(1)(h)(vi)">
the name of the county in which the project property is located; and</subsection><subsection number="38-1a-501(1)(h)(vii)"><subsection number="38-1a-501(1)(h)(vii)(A)">
the tax parcel identification number of each parcel included in the project property;</subsection><subsection number="38-1a-501(1)(h)(vii)(B)">
the entry number of a previously filed notice of construction loan under Section <xref depth="3" refnumber="38-1a-601" start="0">38-1a-601</xref> on the same project;</subsection><subsection number="38-1a-501(1)(h)(vii)(C)">
the entry number of a previously filed preliminary notice on the same project that includes the tax parcel identification number of each parcel included in the project property; or</subsection><subsection number="38-1a-501(1)(h)(vii)(D)">
the entry number of the building permit issued for the project.</subsection></subsection></subsection><subsection number="38-1a-501(1)(i)">
A preliminary notice may include:<subsection number="38-1a-501(1)(i)(i)">
the subdivision, development, or other project name applicable to the construction project for which the preliminary notice is filed; and</subsection><subsection number="38-1a-501(1)(i)(ii)">
the lot or parcel number of each lot or parcel that is included in the project property.</subsection></subsection></subsection><subsection number="38-1a-501(2)"><subsection number="38-1a-501(2)(a)">
Except as provided in Subsection <xref depth="4" refnumber="38-1a-501(2)(b)" start="0">(2)(b)</xref>, the burden is upon the person filing the preliminary notice to prove that the person has substantially complied with the requirements of this section.</subsection><subsection number="38-1a-501(2)(b)">
A person has substantially complied with the requirements of this section if the person files a preliminary notice that links, within the registry, to a preliminary notice filed by an original contractor for the same construction project, using the entry number assigned to the original contractor's preliminary notice.</subsection><subsection number="38-1a-501(2)(c)">
Substantial compliance with the requirements of Subsections <xref depth="4" refnumber="38-1a-501(1)(h)(iii)" start="0">(1)(h)(iii)</xref> through <xref depth="4" refnumber="38-1a-501(1)(h)(vii)" start="0">(vii)</xref> may be established by a person's reasonable reliance on information in the registry provided by a previously filed:<subsection number="38-1a-501(2)(c)(i)">
notice of construction loan under Section <xref depth="3" refnumber="38-1a-601" start="0">38-1a-601</xref>;</subsection><subsection number="38-1a-501(2)(c)(ii)">
preliminary notice; or</subsection><subsection number="38-1a-501(2)(c)(iii)">
building permit.</subsection></subsection></subsection><subsection number="38-1a-501(3)"><subsection number="38-1a-501(3)(a)">
Subject to Subsection <xref depth="4" refnumber="38-1a-501(3)(b)" start="0">(3)(b)</xref>, a person required by this section to give preliminary notice is required to give only one notice for each construction project.</subsection><subsection number="38-1a-501(3)(b)">
If the construction work is provided pursuant to contracts under more than one original contract for construction work, the notice requirements shall be met with respect to the construction work provided under each original contract.</subsection></subsection><subsection number="38-1a-501(4)">
A person filing a preliminary notice by alternate means is responsible for verifying and changing any incorrect information in the preliminary notice before the expiration of the time period during which the notice is required to be filed.</subsection><subsection number="38-1a-501(5)">
A person who files a preliminary notice that contains inaccurate or incomplete information may not be held liable for damages suffered by any other person who relies on the inaccurate or incomplete information in filing a preliminary notice.</subsection></section><section number="38-1a-502"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Notice of construction lien -- Contents -- Recording -- Service on owner.</catchline><subsection number="38-1a-502(1)"><subsection number="38-1a-502(1)(a)">
A person who desires to claim a construction lien shall submit for recording in the office of each applicable county recorder a notice of construction lien no later than, except as provided in Subsection <xref depth="4" refnumber="38-1a-502(1)(b)" start="0">(1)(b)</xref>:<subsection number="38-1a-502(1)(a)(i)">
180 days after the date on which final completion of the original contract occurs, if no notice of completion is filed under Section <xref depth="3" refnumber="38-1a-507" start="0">38-1a-507</xref>; or</subsection><subsection number="38-1a-502(1)(a)(ii)">
90 days after the date on which a notice of completion is filed under Section <xref depth="3" refnumber="38-1a-507" start="0">38-1a-507</xref>, but not later than 180 days after the date on which final completion of the original contract occurs.</subsection></subsection><subsection number="38-1a-502(1)(b)">
A subcontractor who provides substantial work after a certificate of occupancy is issued or a required final inspection is completed and desires to claim a construction lien shall submit for recording in the office of each applicable county recorder a notice of construction lien no later than 180 days after final completion of that subcontractor's work.</subsection></subsection><subsection number="38-1a-502(2)">
A notice of construction lien shall contain:
<subsection number="38-1a-502(2)(a)">
the name of the reputed owner if known or, if not known, the name of the record owner;</subsection><subsection number="38-1a-502(2)(b)">
the name of the person by whom the claimant was employed or to whom the claimant provided construction work;</subsection><subsection number="38-1a-502(2)(c)">
the time when the claimant first and last provided construction work;</subsection><subsection number="38-1a-502(2)(d)">
a description of the project property, sufficient for identification;</subsection><subsection number="38-1a-502(2)(e)">
the name, current address, and current phone number of the claimant;</subsection><subsection number="38-1a-502(2)(f)">
the amount claimed under the construction lien;</subsection><subsection number="38-1a-502(2)(g)">
the signature of the claimant or the claimant's authorized agent;</subsection><subsection number="38-1a-502(2)(h)">
an acknowledgment or certificate as required under <xref depth="1" refnumber="57-3" start="0">Title 57, Chapter 3, Recording of Documents</xref>; and</subsection><subsection number="38-1a-502(2)(i)">
if the construction lien is on an owner-occupied residence, as defined in Section <xref depth="3" refnumber="38-11-102" start="0">38-11-102</xref>, a statement describing what steps an owner, as defined in Section <xref depth="3" refnumber="38-11-102" start="0">38-11-102</xref>, may take to require a lien claimant to remove the lien in accordance with Section <xref depth="3" refnumber="38-11-107" start="0">38-11-107</xref>.</subsection></subsection><subsection number="38-1a-502(3)"><subsection number="38-1a-502(3)(a)">
A county recorder:<subsection number="38-1a-502(3)(a)(i)">
shall record each notice of construction lien in an index maintained for that purpose; and</subsection><subsection number="38-1a-502(3)(a)(ii)">
need not verify that a valid preliminary notice is filed with respect to the claimed construction lien.</subsection></subsection><subsection number="38-1a-502(3)(b)">
All persons are considered to have notice of a notice of construction lien from the time it is recorded.</subsection></subsection><subsection number="38-1a-502(4)"><subsection number="38-1a-502(4)(a)">
Within 30 days after filing a notice of construction lien, the claimant shall deliver or mail by certified mail a copy of the notice to the reputed owner or the record owner.</subsection><subsection number="38-1a-502(4)(b)">
If the record owner's current address is not readily available to the claimant, the claimant may mail a copy of the notice to the last known address of the record owner, using the names and addresses appearing on the last completed real property assessment rolls of the county where the project property is located.</subsection><subsection number="38-1a-502(4)(c)">
Failure to deliver or mail the notice of lien to the reputed owner or record owner precludes the claimant from an award of costs and attorney fees against the reputed owner or record owner in an action to enforce the construction lien.</subsection></subsection><subsection number="38-1a-502(5)">
The division shall make rules governing the form of the statement required under Subsection <xref depth="4" refnumber="38-1a-502(2)(i)" start="0">(2)(i)</xref>.</subsection></section><section number="38-1a-503"><histories><history>Amended by Chapter <modchap sess="2014GS">293</modchap>, 2014 General Session</history><modyear>2014</modyear></histories><catchline>Relation back and priority of liens.</catchline><subsection number="38-1a-503(1)">
A construction lien relates back to, and takes effect as of, the time of the first preliminary notice filing.</subsection><subsection number="38-1a-503(2)"><subsection number="38-1a-503(2)(a)">
Subject to Subsection <xref depth="4" refnumber="38-1a-503(2)(b)" start="0">(2)(b)</xref>, a construction lien has priority over:<subsection number="38-1a-503(2)(a)(i)">
any lien, mortgage, or other encumbrance that attaches after the first preliminary notice filing; and</subsection><subsection number="38-1a-503(2)(a)(ii)">
any lien, mortgage, or other encumbrance of which the claimant had no notice and which was unrecorded at the time of the first preliminary notice filing.</subsection></subsection><subsection number="38-1a-503(2)(b)">
A recorded mortgage or trust deed that secures a construction loan attaches immediately before the first preliminary notice filing for the construction project if each claimant that has a preliminary notice on file on the construction project before the mortgage or trust deed was recorded receives full payment for all construction work the claimant performed before the mortgage or trust deed was recorded, regardless of whether the claimant receives full payment before or after the day on which the mortgage or trust deed is recorded.</subsection></subsection></section><section number="38-1a-504"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Construction liens on equal footing.</catchline><subsection number="38-1a-504(1)">
Construction liens on a project property are on an equal footing with one another, regardless of when the notices of construction lien relating to the construction liens are submitted for recording and regardless of when construction work for which the liens are claimed is provided.</subsection><subsection number="38-1a-504(2)">
Subsection <xref depth="4" refnumber="38-1a-504(1)" start="0">(1)</xref> relates to the relationship between claimants' construction liens and does not affect the priority of a construction lender's mortgage or trust deed, as established under this chapter.</subsection></section><section number="38-1a-505"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Materials for a construction project not subject to process -- Exception.</catchline><subsection number="38-1a-505(1)">
Materials provided for use in a construction project are not subject to attachment, execution, or other legal process to enforce a debt owed by the purchaser of the materials, if the materials are in good faith about to be applied to the construction, alteration, or repair of an improvement that is the subject of the construction project.</subsection><subsection number="38-1a-505(2)">
Subsection <xref depth="4" refnumber="38-1a-505(1)" start="0">(1)</xref> does not apply to an attachment, execution, or other legal process to enforce a debt incurred to purchase the materials described in Subsection <xref depth="4" refnumber="38-1a-505(1)" start="0">(1)</xref>.</subsection></section><section number="38-1a-506"><histories><history>Amended by Chapter <modchap sess="2022GS">429</modchap>, 2022 General Session</history><modyear>2022</modyear></histories><catchline>Notice of intent to obtain final completion.</catchline><subsection number="38-1a-506(1)">
An owner of a nonresidential construction project that is registered with the registry, or an original contractor of a commercial nonresidential construction project that is registered with the registry under Section <xref depth="3" refnumber="38-1a-501" start="0">38-1a-501</xref>, shall file with the registry a notice of intent to obtain final completion as provided in this section if:
<subsection number="38-1a-506(1)(a)">
the completion of performance time under the original contract for construction work is greater than 120 days;</subsection><subsection number="38-1a-506(1)(b)">
the total original construction contract price exceeds $500,000; and</subsection><subsection number="38-1a-506(1)(c)">
the original contractor or owner has not obtained a payment bond in accordance with Section <xref depth="3" refnumber="14-2-1" start="0">14-2-1</xref>.</subsection></subsection><subsection number="38-1a-506(2)">
The notice of intent described in Subsection <xref depth="4" refnumber="38-1a-506(1)" start="0">(1)</xref> shall be filed at least 45 days before the day on which the owner or original contractor of a commercial nonresidential construction project files or could have filed a notice of completion under Section <xref depth="3" refnumber="38-1a-507" start="0">38-1a-507</xref>.</subsection><subsection number="38-1a-506(3)">
A person who provides construction work to an owner or original contractor who files a notice of intent in accordance with Subsection <xref depth="4" refnumber="38-1a-506(1)" start="0">(1)</xref> shall file an amendment to the person's preliminary notice previously filed by the person as required in Section <xref depth="3" refnumber="38-1a-501" start="0">38-1a-501</xref>:
<subsection number="38-1a-506(3)(a)">
that includes:<subsection number="38-1a-506(3)(a)(i)">
a good faith estimate of the total amount remaining due to complete the contract, purchase order, or agreement relating to the person's approved construction work;</subsection><subsection number="38-1a-506(3)(a)(ii)">
the identification of each original contractor or subcontractor with whom the person has a contract or contracts for providing construction work; and</subsection><subsection number="38-1a-506(3)(a)(iii)">
a separate statement of all known amounts or categories of work in dispute; and</subsection></subsection><subsection number="38-1a-506(3)(b)">
no later than 20 days after the day on which the owner or original contractor files a notice of intent.</subsection></subsection><subsection number="38-1a-506(4)"><subsection number="38-1a-506(4)(a)">
A person described in Subsection <xref depth="4" refnumber="38-1a-506(3)" start="0">(3)</xref> may demand a statement of adequate assurance from the owner, original contractor, or subcontractor with whom the person has privity of contract no later than 10 days after the day on which the person files a balance statement in accordance with Subsection <xref depth="4" refnumber="38-1a-506(3)" start="0">(3)</xref> from an owner, original contractor, or subcontractor who is in privity of contract with the person.</subsection><subsection number="38-1a-506(4)(b)">
A demand for adequate assurance as described in Subsection <xref depth="4" refnumber="38-1a-506(4)(a)" start="0">(4)(a)</xref> may include a request for a statement from the owner, original contractor, or subcontractor that the owner, original contractor, or subcontractor has sufficient funds dedicated and available to pay for all sums due to the person filing for the adequate assurances or that will become due in order to complete a construction project.</subsection><subsection number="38-1a-506(4)(c)">
A person who demands adequate assurance under Subsection <xref depth="4" refnumber="38-1a-506(4)(a)" start="0">(4)(a)</xref> shall deliver copies of the demand to the owner and original contractor:<subsection number="38-1a-506(4)(c)(i)">
by hand delivery with a responsible party's acknowledgment of receipt;</subsection><subsection number="38-1a-506(4)(c)(ii)">
by certified mail with a return receipt; or</subsection><subsection number="38-1a-506(4)(c)(iii)">
as provided under Rule 4, Utah Rules of Civil Procedure.</subsection></subsection></subsection><subsection number="38-1a-506(5)"><subsection number="38-1a-506(5)(a)">
A person described in Subsection <xref depth="4" refnumber="38-1a-506(3)" start="0">(3)</xref> may bring a legal action against a party with whom the person is in privity of contract, including a request for injunctive or declaratory relief, to determine the adequacy of the funds of the owner, original contractor, or subcontractor with whom the demanding person contracted if, after the person demands adequate assurance in accordance with the requirements of this section:<subsection number="38-1a-506(5)(a)(i)">
the owner, original contractor, or subcontractor fails to provide adequate assurance that the owner, original contractor, or subcontractor has sufficient available funds, or access to financing or other sufficient available funds, to pay for the completion of the demanding person's approved work on the construction project; or</subsection><subsection number="38-1a-506(5)(a)(ii)">
the parties disagree, in good faith, as to whether there are adequate funds, or access to financing or other sufficient available funds, to pay for the completion of the demanding person's approved work on the construction project.</subsection></subsection><subsection number="38-1a-506(5)(b)">
If a court finds that an owner, original contractor, or subcontractor has failed to provide adequate assurance in accordance with Subsection <xref depth="4" refnumber="38-1a-506(4)(a)" start="0">(4)(a)</xref>, the court may require the owner, original contractor, or subcontractor to post adequate security with the court sufficient to assure timely payment of the remaining contract balance for the approved work of the person seeking adequate assurance, including:<subsection number="38-1a-506(5)(b)(i)">
cash;</subsection><subsection number="38-1a-506(5)(b)(ii)">
a bond;</subsection><subsection number="38-1a-506(5)(b)(iii)">
an irrevocable letter of credit;</subsection><subsection number="38-1a-506(5)(b)(iv)">
property;</subsection><subsection number="38-1a-506(5)(b)(v)">
financing; or</subsection><subsection number="38-1a-506(5)(b)(vi)">
another form of security approved by the court.</subsection></subsection></subsection><subsection number="38-1a-506(6)"><subsection number="38-1a-506(6)(a)">
A person is subject to the civil penalty described in Subsection <xref depth="4" refnumber="38-1a-506(6)(b)" start="0">(6)(b)</xref>, if the person files a balance statement described in Subsection <xref depth="4" refnumber="38-1a-506(3)" start="0">(3)</xref> that misrepresents the amount due under the contract with the intent to:<subsection number="38-1a-506(6)(a)(i)">
charge an owner, original contractor, or subcontractor more than the actual amount due; or</subsection><subsection number="38-1a-506(6)(a)(ii)">
procure any other unfair advantage or benefit on the person's behalf.</subsection></subsection><subsection number="38-1a-506(6)(b)">
The civil penalty described in Subsection <xref depth="4" refnumber="38-1a-506(6)(a)" start="0">(6)(a)</xref> is the greater of:<subsection number="38-1a-506(6)(b)(i)">
twice the amount by which the balance statement filed under Subsection <xref depth="4" refnumber="38-1a-506(3)" start="0">(3)</xref> exceeds the amount actually remaining due under the contract for completion of construction; and</subsection><subsection number="38-1a-506(6)(b)(ii)">
the actual damages incurred by the owner, original contractor, or subcontractor.</subsection></subsection></subsection><subsection number="38-1a-506(7)">
A court shall award reasonable attorney fees to a prevailing party for an action brought under this section.</subsection><subsection number="38-1a-506(8)">
Failure to comply with the requirements established in this section does not affect any other requirement or right under this chapter.</subsection><subsection number="38-1a-506(9)">
A person who has not filed a preliminary notice as required under Section <xref depth="3" refnumber="38-1a-501" start="0">38-1a-501</xref> is not entitled to a right or a remedy provided in this section.</subsection><subsection number="38-1a-506(10)">
This section does not create a cause of action against a person with whom the demanding party is not in privity of contract.</subsection></section><section number="38-1a-507"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Notice of completion.</catchline><subsection number="38-1a-507(1)"><subsection number="38-1a-507(1)(a)">
Upon final completion of a construction project, a notice of completion may be filed with the registry by:<subsection number="38-1a-507(1)(a)(i)">
an owner;</subsection><subsection number="38-1a-507(1)(a)(ii)">
an original contractor for construction work;</subsection><subsection number="38-1a-507(1)(a)(iii)">
a lender that has provided financing for the construction project;</subsection><subsection number="38-1a-507(1)(a)(iv)">
a surety that has provided bonding for the construction project; or</subsection><subsection number="38-1a-507(1)(a)(v)">
a title company issuing a title insurance policy on the construction project.</subsection></subsection><subsection number="38-1a-507(1)(b)">
A notice of completion shall include:<subsection number="38-1a-507(1)(b)(i)">
the name, address, telephone number, and email address of the person filing the notice of completion;</subsection><subsection number="38-1a-507(1)(b)(ii)">
the name of the county in which the project property is located;</subsection><subsection number="38-1a-507(1)(b)(iii)">
for a private project:
<subsection number="38-1a-507(1)(b)(iii)(A)">
the tax parcel identification number of each parcel included in the project property;</subsection><subsection number="38-1a-507(1)(b)(iii)(B)">
the entry number of a preliminary notice on the same project that includes the tax parcel identification number of each parcel included in the project property; or</subsection><subsection number="38-1a-507(1)(b)(iii)(C)">
the entry number of the building permit issued for the project;</subsection></subsection><subsection number="38-1a-507(1)(b)(iv)">
for a government project, the government project-identifying information;</subsection><subsection number="38-1a-507(1)(b)(v)">
the date on which final completion is alleged to have occurred; and</subsection><subsection number="38-1a-507(1)(b)(vi)">
the method used to determine final completion.</subsection></subsection></subsection><subsection number="38-1a-507(2)">
A person filing a notice of completion by alternate means is responsible for verifying and changing any incorrect information in the notice of completion before the expiration of the time period during which the notice is required to be filed.</subsection></section></part><part number="38-1a-6"><catchline>Construction Loans</catchline><section number="38-1a-601"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Notice of construction loan.</catchline><subsection number="38-1a-601(1)">
After recording a mortgage or trust deed securing a construction loan on a private project, the construction lender on the loan shall promptly, in conjunction with the closing of the construction loan, file with the registry a notice of construction loan.</subsection><subsection number="38-1a-601(2)">
A notice under Subsection <xref depth="4" refnumber="38-1a-601(1)" start="0">(1)</xref> shall accurately state:
<subsection number="38-1a-601(2)(a)">
the lender's name, address, and telephone number;</subsection><subsection number="38-1a-601(2)(b)">
the name of the trustor on the trust deed securing the loan;</subsection><subsection number="38-1a-601(2)(c)">
the tax parcel identification number of each parcel included or to be included in the construction project for which the loan was given;</subsection><subsection number="38-1a-601(2)(d)">
the address of the project property; and</subsection><subsection number="38-1a-601(2)(e)">
the name of the county in which the project property is located.</subsection></subsection><subsection number="38-1a-601(3)">
A construction lender that files a notice of construction loan containing incomplete or inaccurate information may not be held liable for damages suffered by any other person who relies on the inaccurate or incomplete information in filing a preliminary notice.</subsection></section><section number="38-1a-602"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Notice concerning construction loan default.</catchline><subsection number="38-1a-602(1)">
Within five business days after a notice of default is filed for recording under Section <xref depth="3" refnumber="57-1-24" start="0">57-1-24</xref> with respect to a trust deed on the project property securing a construction loan, the construction lender under the loan shall file a notice with the registry.</subsection><subsection number="38-1a-602(2)">
A notice under Subsection <xref depth="4" refnumber="38-1a-602(1)" start="0">(1)</xref> shall:
<subsection number="38-1a-602(2)(a)">
include:<subsection number="38-1a-602(2)(a)(i)">
the information required to be included in a notice of construction loan under Subsection <xref depth="4" refnumber="38-1a-601(2)" start="0">38-1a-601(2)</xref>; and</subsection><subsection number="38-1a-602(2)(a)(ii)">
the entry number of the notice of construction loan;</subsection></subsection><subsection number="38-1a-602(2)(b)">
state that a notice of default with respect to the construction loan has been recorded; and</subsection><subsection number="38-1a-602(2)(c)">
state the date that the notice of default was recorded.</subsection></subsection></section><section number="38-1a-603"><histories><history>Enacted by Chapter <modchap sess="2019GS">250</modchap>, 2019 General Session</history><modyear>2019</modyear></histories><catchline>Notice of intent to finance.</catchline><subsection number="38-1a-603(1)">
An owner may file with the registry a notice of intent to finance.</subsection><subsection number="38-1a-603(2)">
A notice of intent to finance under Subsection <xref depth="4" refnumber="38-1a-603(1)" start="0">(1)</xref> shall state:
<subsection number="38-1a-603(2)(a)">
the anticipated date on which financing will occur;</subsection><subsection number="38-1a-603(2)(b)">
the anticipated lender's name, address, and telephone number;</subsection><subsection number="38-1a-603(2)(c)">
the name of the trustor on the trust deed securing the anticipated loan;</subsection><subsection number="38-1a-603(2)(d)">
the tax parcel identification number of each parcel included in the project property; and</subsection><subsection number="38-1a-603(2)(e)">
the name of the county in which the project property is located.</subsection></subsection><subsection number="38-1a-603(3)">
If an owner chooses to file a notice of intent to finance, the owner shall file the notice of intent to finance no less than 14 days before the date on which the financing is anticipated to occur.</subsection><subsection number="38-1a-603(4)">
If the financing does not occur within 30 days after the anticipated date specified in the notice of intent to finance, the notice of intent to finance shall automatically have no effect and shall be removed from the registry.</subsection></section><section number="38-1a-604"><histories><history>Enacted by Chapter <modchap sess="2019GS">250</modchap>, 2019 General Session</history><modyear>2019</modyear></histories><catchline>Notice of final lien waiver.</catchline><subsection number="38-1a-604(1)">
After a notice of intent to finance is filed under Section <xref depth="3" refnumber="38-1a-603" start="0">38-1a-603</xref> on a project property, each subcontractor that has filed a preliminary notice pertaining to the project property may file with the registry a final lien waiver.</subsection><subsection number="38-1a-604(2)">
The final lien waiver described in Subsection <xref depth="4" refnumber="38-1a-604(1)" start="0">(1)</xref> may be filed on the registry even if no notice of intent to finance was filed on the registry.</subsection></section></part><part number="38-1a-7"><catchline>Enforcement of Preconstruction and Construction Liens</catchline><section number="38-1a-701"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Action to enforce lien -- Time for filing action -- Notice of pendency of action -- Action involving a residence.</catchline><subsection number="38-1a-701(1)">
As used in this section:
<subsection number="38-1a-701(1)(a)">
"Owner" has the same meaning as defined in Section <xref depth="3" refnumber="38-11-102" start="0">38-11-102</xref>.</subsection><subsection number="38-1a-701(1)(b)">
"Residence" has the same meaning as defined in Section <xref depth="3" refnumber="38-11-102" start="0">38-11-102</xref>.</subsection></subsection><subsection number="38-1a-701(2)">
In order to enforce a preconstruction lien or construction lien, a claimant shall file an action to enforce the lien:
<subsection number="38-1a-701(2)(a)">
except as provided in Subsection <xref depth="4" refnumber="38-1a-701(2)(b)" start="0">(2)(b)</xref>, within 180 days after the day on which the claimant files:<subsection number="38-1a-701(2)(a)(i)">
a notice of preconstruction lien under Section <xref depth="3" refnumber="38-1a-402" start="0">38-1a-402</xref>, for a preconstruction lien; or</subsection><subsection number="38-1a-701(2)(a)(ii)">
a notice of construction lien under Section <xref depth="3" refnumber="38-1a-502" start="0">38-1a-502</xref>, for a construction lien; or</subsection></subsection><subsection number="38-1a-701(2)(b)">
if an owner files for protection under the bankruptcy laws of the United States before the expiration of the 180-day period under Subsection <xref depth="4" refnumber="38-1a-701(2)(a)" start="0">(2)(a)</xref>, within 90 days after the automatic stay under the bankruptcy proceeding is lifted or expires.</subsection></subsection><subsection number="38-1a-701(3)"><subsection number="38-1a-701(3)(a)"><subsection number="38-1a-701(3)(a)(i)">
Within the time period provided in Subsection <xref depth="4" refnumber="38-1a-701(2)" start="0">(2)</xref> for filing an action, a claimant shall file for record with each applicable county recorder a notice of the pendency of the action, in the manner provided for actions affecting the title or right to possession of real property.</subsection><subsection number="38-1a-701(3)(a)(ii)">
If a claimant fails to file for record a notice of the pendency of the action, as required in Subsection <xref depth="4" refnumber="38-1a-701(3)(a)(i)" start="0">(3)(a)(i)</xref>, the preconstruction lien or construction lien, as applicable, is void, except as to persons who have been made parties to the action and persons having actual knowledge of the commencement of the action.</subsection></subsection><subsection number="38-1a-701(3)(b)">
The burden of proof is upon the claimant and those claiming under the claimant to show actual knowledge under Subsection <xref depth="4" refnumber="38-1a-701(3)(a)(ii)" start="0">(3)(a)(ii)</xref>.</subsection></subsection><subsection number="38-1a-701(4)"><subsection number="38-1a-701(4)(a)">
A preconstruction lien or construction lien is automatically and immediately void if an action to enforce the lien is not filed within the time required by this section.</subsection><subsection number="38-1a-701(4)(b)">
Notwithstanding Section <xref depth="3" refnumber="78B-2-111" start="0">78B-2-111</xref>, a court has no subject matter jurisdiction to adjudicate a preconstruction or construction lien that becomes void under Subsection <xref depth="4" refnumber="38-1a-701(4)(a)" start="0">(4)(a)</xref>.</subsection></subsection><subsection number="38-1a-701(5)">
This section may not be interpreted to impair or affect the right of any person to whom a debt may be due for any preconstruction service or construction work to maintain a personal action to recover the debt.</subsection><subsection number="38-1a-701(6)"><subsection number="38-1a-701(6)(a)">
If a claimant files an action to enforce a preconstruction or construction lien involving a residence, the claimant shall include with the service of the complaint on the owner of the residence:<subsection number="38-1a-701(6)(a)(i)">
instructions to the owner of the residence relating to the owner's rights under <xref depth="1" refnumber="38-11" start="0">Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act</xref>; and</subsection><subsection number="38-1a-701(6)(a)(ii)">
a form to enable the owner of the residence to specify the grounds upon which the owner may exercise available rights under <xref depth="1" refnumber="38-11" start="0">Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act</xref>.</subsection></subsection><subsection number="38-1a-701(6)(b)">
The instructions and form required by Subsection <xref depth="4" refnumber="38-1a-701(6)(a)" start="0">(6)(a)</xref> shall meet the requirements established by the division by rule.</subsection><subsection number="38-1a-701(6)(c)">
If a claimant fails to provide to the owner of the residence the instructions and form required by Subsection <xref depth="4" refnumber="38-1a-701(6)(a)" start="0">(6)(a)</xref>, the claimant is barred from maintaining or enforcing the preconstruction or construction lien upon the residence.</subsection><subsection number="38-1a-701(6)(d)">
A court shall stay an action to determine the rights and liabilities of an owner of a residence under this chapter, <xref depth="1" refnumber="38-11" start="0">Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act</xref>, and <xref depth="1" refnumber="14-2" start="0">Title 14, Chapter 2, Private Contracts</xref>, until after the owner is given a reasonable period of time to:<subsection number="38-1a-701(6)(d)(i)">
establish compliance with Subsections <xref depth="4" refnumber="38-11-204(4)(a)" start="0">38-11-204(4)(a)</xref> and <xref depth="4" refnumber="38-11-204(4)(b)" start="0">(4)(b)</xref> through an informal proceeding, as set forth in <xref depth="1" refnumber="63G-4" start="0">Title 63G, Chapter 4, Administrative Procedures Act</xref>, commenced at the division within 30 days after the owner is served with summons in the foreclosure action; and</subsection><subsection number="38-1a-701(6)(d)(ii)">
obtain a certificate of compliance or denial of certificate of compliance, as defined in Section <xref depth="3" refnumber="38-11-102" start="0">38-11-102</xref>.</subsection></subsection><subsection number="38-1a-701(6)(e)">
An owner applying for a certificate of compliance under Subsection <xref depth="4" refnumber="38-1a-701(6)(d)" start="0">(6)(d)</xref> shall send by certified mail to all claimants:<subsection number="38-1a-701(6)(e)(i)">
a copy of the application for a certificate of compliance; and</subsection><subsection number="38-1a-701(6)(e)(ii)">
all materials filed in connection with the application.</subsection></subsection><subsection number="38-1a-701(6)(f)">
The division shall notify all claimants listed in an owner's application for a certificate of compliance under Subsection <xref depth="4" refnumber="38-1a-701(6)(d)" start="0">(6)(d)</xref> of the issuance or denial of a certificate of compliance.</subsection></subsection></section><section number="38-1a-702"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Parties -- Consolidation of separate actions.</catchline><subsection number="38-1a-702(1)">
In an action under this part, subject to the time restrictions under Subsection <xref depth="4" refnumber="38-1a-701(2)" start="0">38-1a-701(2)</xref>:
<subsection number="38-1a-702(1)(a)">
a claimant who is not contesting the claim of another claimant may join as a plaintiff;</subsection><subsection number="38-1a-702(1)(b)">
a claimant who fails or refuses to become a plaintiff may be made a defendant; and</subsection><subsection number="38-1a-702(1)(c)">
a claimant who is not made a party may intervene at any time before the final hearing.</subsection></subsection><subsection number="38-1a-702(2)">
If separate actions are commenced under this part to enforce preconstruction or construction liens on the same property, the court may consolidate the actions and make all claimants parties to the consolidated action.</subsection></section><section number="38-1a-703"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Order of satisfaction if multiple liens on same property.</catchline><tab/>If liens are claimed against the same property the decree shall provide for their satisfaction in the following order:<subsection number="38-1a-703(1)">
subcontractors who are laborers or mechanics working by the day or piece, but who have not furnished materials;</subsection><subsection number="38-1a-703(2)">
all other subcontractors and all materialmen; and</subsection><subsection number="38-1a-703(3)">
original contractors.</subsection></section><section number="38-1a-704"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Sale of property -- Redemption -- Disposition of proceeds.</catchline><subsection number="38-1a-704(1)">
The court shall cause the property to be sold in satisfaction of the liens and costs as in the case of a foreclosure of a mortgage, subject to the same right of redemption.</subsection><subsection number="38-1a-704(2)">
If the proceeds of sale after the payment of costs are not sufficient to satisfy the whole amount of liens included in the decree, then the proceeds shall be paid in the order designated in Section <xref depth="3" refnumber="38-1a-703" start="0">38-1a-703</xref>, and pro rata to the persons claiming in each class if the sum realized is insufficient to pay the persons of the class in full.</subsection><subsection number="38-1a-704(3)">
Any excess sale proceeds remaining after the payment of all liens and costs shall be paid to the owner.</subsection></section><section number="38-1a-705"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Deficiency judgment.</catchline><tab/>A claimant whose preconstruction or construction lien is not paid in full through an enforcement action as provided in this part may:<subsection number="38-1a-705(1)">
have judgment for the unpaid balance entered against the person liable; and</subsection><subsection number="38-1a-705(2)">
execute on the judgment in the same manner as execution on judgments generally.</subsection></section><section number="38-1a-706"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Apportionment of costs -- Costs and attorney fees to subcontractor.</catchline><subsection number="38-1a-706(1)">
Except as provided in Section <xref depth="3" refnumber="38-11-107" start="0">38-11-107</xref>, the court shall apportion costs between the owner and original contractor according to the right of the case.</subsection><subsection number="38-1a-706(2)">
The court shall award a subcontractor with a valid preconstruction or construction lien:
<subsection number="38-1a-706(2)(a)">
all of the subcontractor's costs, including the costs of preparing and recording the notice of preconstruction or construction lien; and</subsection><subsection number="38-1a-706(2)(b)">
the subcontractor's reasonable attorney fees incurred in preparing and recording the notice of preconstruction or construction lien.</subsection></subsection></section><section number="38-1a-707"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Attorney fees -- Offer of judgment.</catchline><subsection number="38-1a-707(1)">
Except as provided in Section <xref depth="3" refnumber="38-11-107" start="0">38-11-107</xref> and in Subsection <xref depth="4" refnumber="38-1a-707(2)" start="0">(2)</xref>, in any action brought to enforce any lien under this chapter the successful party shall be entitled to recover reasonable attorney fees, to be fixed by the court, which shall be taxed as costs in the action.</subsection><subsection number="38-1a-707(2)">
A person who files a wrongful lien as provided in Section <xref depth="3" refnumber="38-1a-308" start="0">38-1a-308</xref> may not recover attorney fees under Subsection <xref depth="4" refnumber="38-1a-707(1)" start="0">(1)</xref>.</subsection><subsection number="38-1a-707(3)"><subsection number="38-1a-707(3)(a)">
A person against whom an action is brought to enforce a preconstruction or construction lien may make an offer of judgment pursuant to Rule 68 of the Utah Rules of Civil Procedure.</subsection><subsection number="38-1a-707(3)(b)">
If the offer is not accepted and the judgment finally obtained by the offeree is not more favorable than the offer, the offeree shall pay the costs and attorney fees incurred by the offeror after the offer was made.</subsection></subsection></section></part><part number="38-1a-8"><catchline>Actions Affecting Preconstruction and Construction Liens</catchline><section number="38-1a-801"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Preconstruction and construction liens assignable -- Action by assignee to enforce lien.</catchline><subsection number="38-1a-801(1)">
A preconstruction lien or construction lien is assignable as any other chose in action.</subsection><subsection number="38-1a-801(2)">
An assignee of a preconstruction lien or construction lien may, in the assignee's own name, commence and prosecute an action on the lien as provided in <xref depth="2" refnumber="38-1a-7" start="2">Part 7, Enforcement of Preconstruction and Construction Liens</xref>.</subsection></section><section number="38-1a-802"><histories><history>Renumbered and Amended by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear><history>Amended by Chapter <modchap sess="2012GS">347</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Waiver or limitation of a lien right -- Forms -- Scope.</catchline><subsection number="38-1a-802(1)">
As used in this section:
<subsection number="38-1a-802(1)(a)">
"Check" means a payment instrument on a depository institution including:<subsection number="38-1a-802(1)(a)(i)">
a check;</subsection><subsection number="38-1a-802(1)(a)(ii)">
a draft;</subsection><subsection number="38-1a-802(1)(a)(iii)">
an order; or</subsection><subsection number="38-1a-802(1)(a)(iv)">
other instrument.</subsection></subsection><subsection number="38-1a-802(1)(b)">
"Depository institution" is as defined in Section <xref depth="3" refnumber="7-1-103" start="0">7-1-103</xref>.</subsection><subsection number="38-1a-802(1)(c)">
"Receives payment" means, in the case of a restrictive endorsement, a payee has endorsed a check and the check is presented to and paid by the depository institution on which it is drawn.</subsection></subsection><subsection number="38-1a-802(2)">
Notwithstanding Section <xref depth="3" refnumber="38-1a-105" start="0">38-1a-105</xref>, a claimant's written consent that waives or limits the claimant's lien rights is enforceable only if the claimant:
<subsection number="38-1a-802(2)(a)"><subsection number="38-1a-802(2)(a)(i)">
executes a waiver and release that is signed by the claimant or the claimant's authorized agent; or</subsection><subsection number="38-1a-802(2)(a)(ii)">
for a restrictive endorsement on a check, includes a restrictive endorsement on a check that is:
<subsection number="38-1a-802(2)(a)(ii)(A)">
signed by the claimant or the claimant's authorized agent; and</subsection><subsection number="38-1a-802(2)(a)(ii)(B)">
in substantially the same form set forth in Subsection <xref depth="4" refnumber="38-1a-802(4)(d)" start="0">(4)(d)</xref>; and</subsection></subsection></subsection><subsection number="38-1a-802(2)(b)">
receives payment of the amount identified in the waiver and release or check that includes the restrictive endorsement:<subsection number="38-1a-802(2)(b)(i)">
including payment by a joint payee check; and</subsection><subsection number="38-1a-802(2)(b)(ii)">
for a progress payment, only to the extent of the payment.</subsection></subsection></subsection><subsection number="38-1a-802(3)"><subsection number="38-1a-802(3)(a)">
Notwithstanding the language of a waiver and release described in Subsection <xref depth="4" refnumber="38-1a-802(2)" start="0">(2)</xref>, Subsection <xref depth="4" refnumber="38-1a-802(3)(b)" start="0">(3)(b)</xref> applies if:<subsection number="38-1a-802(3)(a)(i)">
the payment given in exchange for any waiver and release of lien is made by check; and</subsection><subsection number="38-1a-802(3)(a)(ii)">
the check fails to clear the depository institution on which it is drawn for any reason.</subsection></subsection><subsection number="38-1a-802(3)(b)">
If the conditions of Subsection <xref depth="4" refnumber="38-1a-802(3)(a)" start="0">(3)(a)</xref> are met:<subsection number="38-1a-802(3)(b)(i)">
the waiver and release described in Subsection <xref depth="4" refnumber="38-1a-802(3)(a)" start="0">(3)(a)</xref> is void; and</subsection><subsection number="38-1a-802(3)(b)(ii)">
the following will not be affected by the claimant's execution of the waiver and release:
<subsection number="38-1a-802(3)(b)(ii)(A)">
any lien;</subsection><subsection number="38-1a-802(3)(b)(ii)(B)">
any lien right;</subsection><subsection number="38-1a-802(3)(b)(ii)(C)">
any bond right;</subsection><subsection number="38-1a-802(3)(b)(ii)(D)">
any contract right; or</subsection><subsection number="38-1a-802(3)(b)(ii)(E)">
any other right to recover payment afforded to the claimant in law or equity.</subsection></subsection></subsection></subsection><subsection number="38-1a-802(4)"><subsection number="38-1a-802(4)(a)">
A waiver and release given by a claimant meets the requirements of this section if it is in substantially the form provided in this Subsection <xref depth="4" refnumber="38-1a-802(4)" start="0">(4)</xref> for the circumstance provided in this Subsection <xref depth="4" refnumber="38-1a-802(4)" start="0">(4)</xref>.</subsection><subsection number="38-1a-802(4)(b)">
A waiver and release may be in substantially the following form if the claimant is required to execute a waiver and release in exchange for or to induce the payment of a progress billing:<eol/><center>"UTAH CONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT</center><eol/>Property Name: _____________________________________________________________<eol/>Property Location: ___________________________________________________________<eol/>Undersigned's Customer: _____________________________________________________<eol/>Invoice/Payment Application Number: __________________________________________<eol/>Payment Amount: ___________________________________________________________<eol/>Payment Period: ____________________________________________________________<eol/><tab/>To the extent provided below, this document becomes effective to release and the undersigned is considered to waive any notice of lien or right under Utah Code Ann., <xref depth="1" refnumber="38-1a" start="0">Title 38, Chapter 1a, Preconstruction and Construction Liens</xref>, or any bond right under Utah Code Ann., <xref depth="0" refnumber="14" start="0">Title 14, Contractors' Bonds</xref>, or Section <xref depth="3" refnumber="63G-6a-1103" start="0">63G-6a-1103</xref> related to payment rights the undersigned has on the above described Property once:<eol/><tab/>(1)  the undersigned endorses a check in the above referenced Payment Amount payable to the undersigned; and<eol/><tab/>(2)  the check is paid by the depository institution on which it is drawn.<eol/><tab/>This waiver and release applies to a progress payment for the work, materials, equipment, or a combination of work, materials, and equipment furnished by the undersigned to the Property or to the Undersigned's Customer which are the subject of the Invoice or Payment Application, but only to the extent of the Payment Amount.  This waiver and release does not apply to any retention withheld; any items, modifications, or changes pending approval; disputed items and claims; or items furnished or invoiced after the Payment Period.<eol/><tab/>The undersigned warrants that the undersigned either has already paid or will use the money the undersigned receives from this progress payment promptly to pay in full all the undersigned's laborers, subcontractors, materialmen, and suppliers for all work, materials, equipment, or combination of work, materials, and equipment that are the subject of this waiver and release.<eol/>Dated: ________________________<eol/>___________________________________________________________(Company Name)<eol/>_____________________________________________________By:__________________<eol/>_____________________________________________________Its:__________________"</subsection><subsection number="38-1a-802(4)(c)">
A waiver and release may be in substantially the following form if the lien claimant is required to execute a waiver and release in exchange for or to induce the payment of a final billing:<eol/><center>"UTAH WAIVER AND RELEASE UPON FINAL PAYMENT</center><eol/>Property Name: ____________________________________________________________<eol/>Property Location: __________________________________________________________<eol/>Undersigned's Customer: _____________________________________________________<eol/>Invoice/Payment Application Number: __________________________________________<eol/>Payment Amount: ___________________________________________________________<eol/><tab/>To the extent provided below, this document becomes effective to release and the undersigned is considered to waive any notice of lien or right under Utah Code Ann., <xref depth="1" refnumber="38-1a" start="0">Title 38, Chapter 1a, Preconstruction and Construction Liens</xref>, or any bond right under Utah Code Ann., <xref depth="0" refnumber="14" start="0">Title 14, Contractors' Bonds</xref>, or Section <xref depth="3" refnumber="63G-6a-1103" start="0">63G-6a-1103</xref> related to payment rights the undersigned has on the above described Property once:<eol/><tab/>(1)  the undersigned endorses a check in the above referenced Payment Amount payable to the undersigned; and<eol/><tab/>(2)  the check is paid by the depository institution on which it is drawn.<eol/><tab/>This waiver and release applies to the final payment for the work, materials, equipment, or combination of work, materials, and equipment furnished by the undersigned to the Property or to the Undersigned's Customer.<eol/><tab/>The undersigned warrants that the undersigned either has already paid or will use the money the undersigned receives from the final payment promptly to pay in full all the undersigned's laborers, subcontractors, materialmen, and suppliers for all work, materials, equipment, or combination of work, materials, and equipment that are the subject of this waiver and release.<eol/>Dated: ________________________<eol/>___________________________________________________________(Company Name)<eol/>_____________________________________________________By:__________________<eol/>_____________________________________________________Its:__________________"</subsection><subsection number="38-1a-802(4)(d)">
A restrictive endorsement placed on a check to effectuate a waiver and release described in this Subsection <xref depth="4" refnumber="38-1a-802(4)" start="0">(4)</xref> meets the requirements of this section if it is in substantially the following form:<eol/><tab/>"This check is a progress/ final payment for property described on this check sufficient for identification.  Endorsement of this check is an acknowledgment by the endorser that the waiver and release to which the payment applies is effective to the extent provided in Utah Code Ann. Subsection <xref depth="4" refnumber="38-1a-802(4)(b)" start="0">38-1a-802(4)(b)</xref> or <xref depth="4" refnumber="38-1a-802(4)(c)" start="0">(c)</xref> respectively."</subsection><subsection number="38-1a-802(4)(e)"><subsection number="38-1a-802(4)(e)(i)">
If using a restrictive endorsement under Subsection <xref depth="4" refnumber="38-1a-802(4)(d)" start="0">(4)(d)</xref>, the person preparing the check shall indicate whether the check is for a progress payment or a final payment by circling the word "progress" if the check is for a progress payment, or the word "final" if the check is for a final payment.</subsection><subsection number="38-1a-802(4)(e)(ii)">
If a restrictive endorsement does not indicate whether the check is for a progress payment or a final payment, it is considered to be for a progress payment.</subsection></subsection></subsection><subsection number="38-1a-802(5)"><subsection number="38-1a-802(5)(a)">
If the conditions of Subsection <xref depth="4" refnumber="38-1a-802(5)(b)" start="0">(5)(b)</xref> are met, this section does not affect the enforcement of:<subsection number="38-1a-802(5)(a)(i)">
an accord and satisfaction regarding a bona fide dispute; or</subsection><subsection number="38-1a-802(5)(a)(ii)">
an agreement made in settlement of an action pending in any court or arbitration.</subsection></subsection><subsection number="38-1a-802(5)(b)">
Pursuant to Subsection <xref depth="4" refnumber="38-1a-802(5)(a)" start="0">(5)(a)</xref>, this section does not affect enforcement of an accord and satisfaction or settlement described in Subsection <xref depth="4" refnumber="38-1a-802(5)(a)" start="0">(5)(a)</xref> if the accord and satisfaction or settlement:<subsection number="38-1a-802(5)(b)(i)">
is in a writing signed by the claimant; and</subsection><subsection number="38-1a-802(5)(b)(ii)">
specifically references the lien rights waived or impaired.</subsection></subsection></subsection></section><section number="38-1a-803"><histories><history>Enacted by Chapter <modchap sess="2012GS">278</modchap>, 2012 General Session</history><modyear>2012</modyear></histories><catchline>Cancellation of preconstruction or construction lien -- Penalty for failure to cancel timely.</catchline><subsection number="38-1a-803(1)">
After the full amount owing under a preconstruction or construction lien, including costs and cancellation fees, has been paid, a person interested in the property that is the subject of the lien may request the claimant to submit for recording with the office of each applicable county recorder a cancellation of the lien.</subsection><subsection number="38-1a-803(2)">
Within 10 days after receiving a request under Subsection <xref depth="4" refnumber="38-1a-803(1)" start="0">(1)</xref>, the claimant shall submit to the office of each applicable county recorder a cancellation of the preconstruction or construction lien, as applicable.</subsection><subsection number="38-1a-803(3)">
A claimant who fails to submit a cancellation within the time prescribed in Subsection <xref depth="4" refnumber="38-1a-803(2)" start="0">(2)</xref> is liable to the person who requested the cancellation for $100 for each day after the time prescribed in Subsection <xref depth="4" refnumber="38-1a-803(2)" start="0">(2)</xref> that the cancellation is not submitted, or the person's actual damages, whichever is greater.</subsection></section><section number="38-1a-804"><histories><history>Amended by Chapter <modchap sess="2024GS">158</modchap>, 2024 General Session</history><modyear>2024</modyear></histories><catchline>Notice of release of lien and substitution of alternate security.</catchline><subsection number="38-1a-804(1)">The owner of any interest in a project property that is subject to a recorded preconstruction or construction lien, or any original contractor or subcontractor affected by the lien, who disputes the correctness or validity of the lien may submit for recording a notice of release of lien and substitution of alternate security:<subsection number="38-1a-804(1)(a)">that meets the requirements of Subsection (2);</subsection><subsection number="38-1a-804(1)(b)">in the office of each applicable county recorder where the lien was recorded; and</subsection><subsection number="38-1a-804(1)(c)">at any time before the date that is 180 days after the first summons is served in an action to foreclose the preconstruction or construction lien for which the notice under this section is submitted for recording.</subsection></subsection><subsection number="38-1a-804(2)">A notice of release of lien and substitution of alternate security recorded under Subsection (1) shall:<subsection number="38-1a-804(2)(a)">meet the requirements for the recording of documents in Title 57, Chapter 3, Recording of Documents;</subsection><subsection number="38-1a-804(2)(b)">reference the preconstruction or construction lien sought to be released, including the applicable entry number, book number, and page number; and</subsection><subsection number="38-1a-804(2)(c)">have as an attachment a surety bond or evidence of a cash deposit that:<subsection number="38-1a-804(2)(c)(i)"><subsection number="38-1a-804(2)(c)(i)(A)">if a surety bond, is executed by a surety company that is treasury listed, A-rated by AM Best Company, and authorized to issue surety bonds in this state; or</subsection><subsection number="38-1a-804(2)(c)(i)(B)">if evidence of a cash deposit, meets the requirements established by rule by the Department of Commerce in accordance with Title 63G, Chapter 3, Utah Administrative Rulemaking Act;</subsection></subsection><subsection number="38-1a-804(2)(c)(ii)">is in an amount equal to:<subsection number="38-1a-804(2)(c)(ii)(A)">150% of the amount claimed by the claimant under the preconstruction or construction lien or as determined under Subsection (7), if the lien claim is for $25,000 or more;</subsection><subsection number="38-1a-804(2)(c)(ii)(B)">175% of the amount claimed by the claimant under the preconstruction or construction lien or as determined under Subsection (7), if the lien claim is for at least $15,000 but less than $25,000; or</subsection><subsection number="38-1a-804(2)(c)(ii)(C)">200% of the amount claimed by the claimant under the preconstruction or construction lien or as determined under Subsection (7), if the lien claim is for less than $15,000;</subsection></subsection><subsection number="38-1a-804(2)(c)(iii)">is made payable to the claimant;</subsection><subsection number="38-1a-804(2)(c)(iv)">is conditioned for the payment of:<subsection number="38-1a-804(2)(c)(iv)(A)">the judgment that would have been rendered, or has been rendered against the project property in the action to enforce the lien; and</subsection><subsection number="38-1a-804(2)(c)(iv)(B)">any costs and attorney fees awarded by the court; and</subsection></subsection><subsection number="38-1a-804(2)(c)(v)">has as principal:<subsection number="38-1a-804(2)(c)(v)(A)">the owner of the interest in the project property; or</subsection><subsection number="38-1a-804(2)(c)(v)(B)">the original contractor or subcontractor affected by the lien.</subsection></subsection></subsection></subsection><subsection number="38-1a-804(3)"><subsection number="38-1a-804(3)(a)">Upon the recording of the notice of release of lien and substitution of alternate security under Subsection (1), the real property described in the notice shall be released from the preconstruction lien or construction lien to which the notice applies.</subsection><subsection number="38-1a-804(3)(b)">A recorded notice of release of lien and substitution of alternate security is effective as to any amendment to the preconstruction or construction lien being released if the bond amount remains enough to satisfy the requirements of Subsection (2)(c)(ii).</subsection></subsection><subsection number="38-1a-804(4)"><subsection number="38-1a-804(4)(a)">Upon the recording of a notice of release of lien and substitution of alternate security under Subsection (1), the person recording the notice shall serve a copy of the notice, together with any attachments, within 30 days upon the claimant.</subsection><subsection number="38-1a-804(4)(b)">If a suit is pending to foreclose the preconstruction or construction lien at the time the notice is served upon the claimant under Subsection (4)(a), the claimant shall, within 90 days after the receipt of the notice, institute proceedings to add the alternate security as a party to the lien foreclosure suit.</subsection></subsection><subsection number="38-1a-804(5)">The alternate security attached to a notice of release of lien shall be discharged and released upon:<subsection number="38-1a-804(5)(a)">the failure of the claimant to commence a suit against the alternate security within the same time as an action to enforce the lien under Section <xref depth="3" refnumber="38-1a-701">38-1a-701</xref>;</subsection><subsection number="38-1a-804(5)(b)">the failure of the lien claimant to institute proceedings to add the alternate security as a party to a lien foreclosure suit within the time required by Subsection (4)(b);</subsection><subsection number="38-1a-804(5)(c)">the dismissal with prejudice of the lien foreclosure suit or suit against the alternate security as to the claimant; or</subsection><subsection number="38-1a-804(5)(d)">the entry of judgment against the claimant in:<subsection number="38-1a-804(5)(d)(i)">a lien foreclosure suit; or</subsection><subsection number="38-1a-804(5)(d)(ii)">suit against the alternate security.</subsection></subsection></subsection><subsection number="38-1a-804(6)">If a copy of the notice of release of lien and substitution of alternate security is not served upon the claimant as provided in Subsection (4)(a), the claimant has six months after the discovery of the notice to commence an action against the alternate security, except that no action may be commenced against the alternate security after two years from the date the notice was recorded.</subsection><subsection number="38-1a-804(7)"><subsection number="38-1a-804(7)(a)"><subsection number="38-1a-804(7)(a)(i)">The owner of any interest in a project property that is subject to a recorded preconstruction or construction lien, or an original contractor or subcontractor affected by the lien, who disputes the amount claimed under a preconstruction or construction lien may petition a court with jurisdiction under Title 78A, Judiciary and Judicial Administration, for a summary determination of the correct amount owing under the lien for the sole purpose of providing alternate security.</subsection><subsection number="38-1a-804(7)(a)(ii)">Notwithstanding Title 78B, Chapter 3a, Venue for Civil Actions, a person shall bring a petition described in Subsection (7)(a)(i) in the county in which the notice of lien is recorded if the person brings the petition in the district court.</subsection></subsection><subsection number="38-1a-804(7)(b)">A petition under this Subsection (7) shall:<subsection number="38-1a-804(7)(b)(i)">state with specificity the factual and legal bases for disputing the amount claimed under the preconstruction or construction lien; and</subsection><subsection number="38-1a-804(7)(b)(ii)">be supported by a sworn affidavit and any other evidence supporting the petition.</subsection></subsection><subsection number="38-1a-804(7)(c)">A petitioner under Subsection (7)(a) shall, as provided in Utah Rules of Civil Procedure, Rule 4, serve on the claimant:<subsection number="38-1a-804(7)(c)(i)">a copy of the petition; and</subsection><subsection number="38-1a-804(7)(c)(ii)">a notice of hearing if a hearing is scheduled.</subsection></subsection><subsection number="38-1a-804(7)(d)">If a court finds a petition under Subsection (7)(a) insufficient, the court may dismiss the petition without a hearing.</subsection><subsection number="38-1a-804(7)(e)">If a court finds a petition under Subsection (7)(a) sufficient, the court shall schedule a hearing within 10 days to determine the correct amount claimed under the preconstruction or construction lien for the sole purpose of providing alternate security.</subsection><subsection number="38-1a-804(7)(f)">A claimant may:<subsection number="38-1a-804(7)(f)(i)">attend a hearing held under this Subsection (7); and</subsection><subsection number="38-1a-804(7)(f)(ii)">contest the petition.</subsection></subsection><subsection number="38-1a-804(7)(g)">A determination under this section is limited to a determination of the amount claimed under a preconstruction or construction lien for the sole purpose of providing alternate security and does not conclusively establish:<subsection number="38-1a-804(7)(g)(i)">the amount to which the claimant is entitled;</subsection><subsection number="38-1a-804(7)(g)(ii)">the validity of the claim; or</subsection><subsection number="38-1a-804(7)(g)(iii)">any person's right to any other legal remedy.</subsection></subsection><subsection number="38-1a-804(7)(h)">If a court, in a proceeding under this Subsection (7), determines that the amount claimed under a preconstruction or construction lien is excessive, the court shall set the amount for the sole purpose of providing alternate security.</subsection><subsection number="38-1a-804(7)(i)">In an order under Subsection (7)(h), the court shall include a legal description of the project property.</subsection><subsection number="38-1a-804(7)(j)">A petitioner under this Subsection (7) may record a certified copy of any order issued under this Subsection (7) in the county in which the lien is recorded.</subsection><subsection number="38-1a-804(7)(k)">A court may not award attorney fees for a proceeding under this Subsection (7), but shall consider those attorney fees in any award of attorney fees under any other provision of this chapter.</subsection></subsection></section><section number="38-1a-805"><histories><history>Amended by Chapter <modchap sess="2024GS">158</modchap>, 2024 General Session</history><modyear>2024</modyear></histories><catchline>Failure to file notice -- Petition to nullify preconstruction or construction lien -- Expedited proceeding.</catchline><subsection number="38-1a-805(1)"><subsection number="38-1a-805(1)(a)">An owner of an interest in a project property that is subject to a recorded preconstruction lien or a recorded construction lien may petition a court with jurisdiction under Title 78A, Judiciary and Judicial Administration, for summary relief to nullify the preconstruction lien or the construction lien if:<subsection number="38-1a-805(1)(a)(i)">the owner claims that the preconstruction lien or the construction lien is invalid because:<subsection number="38-1a-805(1)(a)(i)(A)">the lien claimant did not timely file a notice of preconstruction service under Section <xref depth="3" refnumber="38-1a-401">38-1a-401</xref>; or</subsection><subsection number="38-1a-805(1)(a)(i)(B)">the lien claimant did not timely file a preliminary notice under Section <xref depth="3" refnumber="38-1a-501">38-1a-501</xref>;</subsection></subsection><subsection number="38-1a-805(1)(a)(ii)">the owner sent the lien claimant a written request to withdraw in accordance with Subsection (2); and</subsection><subsection number="38-1a-805(1)(a)(iii)">the lien claimant did not withdraw the preconstruction lien or the construction lien within 10 business days after the day on which the owner sent the written request to withdraw.</subsection></subsection><subsection number="38-1a-805(1)(b)">Notwithstanding Title 78B, Chapter 3a, Venue for Civil Actions, a person shall bring a petition described in Subsection (1)(a) in the county in which the project property is located if the person brings the petition in the district court.</subsection></subsection><subsection number="38-1a-805(2)">A written request to withdraw described in Subsection (1) shall:<subsection number="38-1a-805(2)(a)">be delivered by certified mail to the lien claimant at the lien claimant's address provided in the recorded preconstruction lien or the recorded construction lien;</subsection><subsection number="38-1a-805(2)(b)">state the owner's name, address, and telephone number;</subsection><subsection number="38-1a-805(2)(c)">contain:<subsection number="38-1a-805(2)(c)(i)"><subsection number="38-1a-805(2)(c)(i)(A)">the name of the county in which the property that is subject to the preconstruction lien or the construction lien is located; and</subsection><subsection number="38-1a-805(2)(c)(i)(B)">the tax parcel identification number of each parcel that is subject to the preconstruction lien or the construction lien; or</subsection></subsection><subsection number="38-1a-805(2)(c)(ii)">a legal description of the property that is subject to the preconstruction lien or the construction lien;</subsection></subsection><subsection number="38-1a-805(2)(d)">state that the lien claimant has failed to timely file:<subsection number="38-1a-805(2)(d)(i)">a notice of preconstruction service under Section <xref depth="3" refnumber="38-1a-401">38-1a-401</xref>; or</subsection><subsection number="38-1a-805(2)(d)(ii)">a preliminary notice under Section <xref depth="3" refnumber="38-1a-501">38-1a-501</xref>;</subsection></subsection><subsection number="38-1a-805(2)(e)">request that the lien claimant withdraw the lien claimant's preconstruction lien or construction lien within 10 business days after the day on which the written request to withdraw is sent; and</subsection><subsection number="38-1a-805(2)(f)">state that if the lien claimant does not withdraw the preconstruction lien or the construction lien within 10 business days after the day on which the written request to withdraw is sent, the owner may petition a court to nullify the lien in an expedited proceeding under this section.</subsection></subsection><subsection number="38-1a-805(3)">A petition under Subsection (1) shall:<subsection number="38-1a-805(3)(a)">state with specificity that:<subsection number="38-1a-805(3)(a)(i)">the lien claimant's preconstruction lien or the lien claimant's construction lien is invalid because the lien claimant did not file a notice of preconstruction service or a preliminary notice, as applicable;</subsection><subsection number="38-1a-805(3)(a)(ii)">the petitioner sent the lien claimant a written request to withdraw in accordance with Subsection (2); and</subsection><subsection number="38-1a-805(3)(a)(iii)">the lien claimant did not withdraw the preconstruction lien or the construction lien within 10 business days after the day on which the owner sent the written request to withdraw;</subsection></subsection><subsection number="38-1a-805(3)(b)">be supported by a sworn affidavit of the petitioner; and</subsection><subsection number="38-1a-805(3)(c)">be served on the lien claimant, in accordance with the Rules of Civil Procedure, within three business days after the day on which the petitioner files the petition in the court.</subsection></subsection><subsection number="38-1a-805(4)"><subsection number="38-1a-805(4)(a)">If the court finds that a petition does not meet the requirements described in Subsection (3), the court may dismiss the petition without a hearing.</subsection><subsection number="38-1a-805(4)(b)">If the court finds that a petition meets the requirements described in Subsection (3), the court shall schedule an expedited hearing to determine whether the preconstruction lien or the construction lien is invalid because the lien claimant failed to file a notice of preconstruction service or a preliminary notice, as applicable.</subsection></subsection><subsection number="38-1a-805(5)"><subsection number="38-1a-805(5)(a)">If the court grants a hearing, within three business days after the day on which the court schedules the hearing and at least seven business days before the day on which the hearing is scheduled, the petitioner shall serve on the lien claimant, in accordance with the Rules of Civil Procedure, a copy of the petition, notice of the hearing, and a copy of the court's order granting the expedited hearing.</subsection><subsection number="38-1a-805(5)(b)">The lien claimant may attend the hearing and contest the petition.</subsection></subsection><subsection number="38-1a-805(6)">An expedited proceeding under this section may only determine:<subsection number="38-1a-805(6)(a)">whether the lien claimant filed a notice of preconstruction service or a preliminary notice; and</subsection><subsection number="38-1a-805(6)(b)">if the lien claimant failed to file a notice of preconstruction service or a preliminary notice, whether the lien claimant's preconstruction lien or construction lien is valid.</subsection></subsection><subsection number="38-1a-805(7)"><subsection number="38-1a-805(7)(a)">If, following a hearing, the court determines that the preconstruction lien or the construction lien is invalid, the court shall issue an order that:<subsection number="38-1a-805(7)(a)(i)">contains a legal description of the property;</subsection><subsection number="38-1a-805(7)(a)(ii)">declares the preconstruction lien or the construction lien void ab initio;</subsection><subsection number="38-1a-805(7)(a)(iii)">releases the property from the lien; and</subsection><subsection number="38-1a-805(7)(a)(iv)">awards costs and reasonable attorney fees to the petitioner.</subsection></subsection><subsection number="38-1a-805(7)(b)">The petitioner may submit a copy of an order issued under Subsection (7)(a) to the county recorder for recording.</subsection></subsection><subsection number="38-1a-805(8)"><subsection number="38-1a-805(8)(a)">If, following a hearing, the court determines that the preconstruction lien or the construction lien is valid, the court shall:<subsection number="38-1a-805(8)(a)(i)">dismiss the petition; and</subsection><subsection number="38-1a-805(8)(a)(ii)">award costs and reasonable attorney fees to the lien claimant.</subsection></subsection><subsection number="38-1a-805(8)(b)">The dismissal order shall contain a legal description of the property.</subsection><subsection number="38-1a-805(8)(c)">The lien claimant may submit a copy of the dismissal order to the county recorder for recording.</subsection></subsection><subsection number="38-1a-805(9)">If a petition under this section contains a claim for damages, the proceedings related to the claim for damages may not be expedited under this section.</subsection></section></part></chapter>