1     
NONUSE APPLICATION AMENDMENTS

2     
2016 GENERAL SESSION

3     
STATE OF UTAH

4     
Chief Sponsor: Timothy D. Hawkes

5     
Senate Sponsor: Margaret Dayton

6     

7     LONG TITLE
8     General Description:
9          This bill deals with nonuse applications.
10     Highlighted Provisions:
11          This bill:
12          ▸     states that approval of one or more nonuse applications, or successive overlapping
13     nonuse applications, does not protect a water right that is already subject to
14     forfeiture, nor does the approval of one or more nonuse applications constitute
15     beneficial use of water; and
16          ▸     makes technical changes.
17     Money Appropriated in this Bill:
18          None
19     Other Special Clauses:
20          None
21     Utah Code Sections Affected:
22     AMENDS:
23          73-1-4, as last amended by Laws of Utah 2015, Chapters 249 and 282
24     

25     Be it enacted by the Legislature of the state of Utah:
26          Section 1. Section 73-1-4 is amended to read:
27          73-1-4. Reversion to the public by abandonment or forfeiture for nonuse within
28     seven years -- Nonuse application.
29          (1) As used in this section:

30          (a) "Public entity" means:
31          (i) the United States;
32          (ii) an agency of the United States;
33          (iii) the state;
34          (iv) a state agency;
35          (v) a political subdivision of the state; or
36          (vi) an agency of a political subdivision of the state.
37          (b) "Public water supplier" means an entity that:
38          (i) supplies water, directly or indirectly, to the public for municipal, domestic, or
39     industrial use; and
40          (ii) is:
41          (A) a public entity;
42          (B) a water corporation, as defined in Section 54-2-1, that is regulated by the Public
43     Service Commission;
44          (C) a community water system:
45          (I) that:
46          (Aa) supplies water to at least 100 service connections used by year-round residents; or
47          (Bb) regularly serves at least 200 year-round residents; and
48          (II) whose voting members:
49          (Aa) own a share in the community water system;
50          (Bb) receive water from the community water system in proportion to the member's
51     share in the community water system; and
52          (Cc) pay the rate set by the community water system based on the water the member
53     receives; or
54          (D) a water users association:
55          (I) in which one or more public entities own at least 70% of the outstanding shares; and
56          (II) that is a local sponsor of a water project constructed by the United States Bureau of
57     Reclamation.

58          (c) "Shareholder" means the same as that term is defined in Section 73-3-3.5.
59          (d) "Water company" means the same as that term is defined in Section 73-3-3.5.
60          (e) "Water supply entity" means an entity that supplies water as a utility service or for
61     irrigation purposes and is also:
62          (i) a municipality, water conservancy district, metropolitan water district, irrigation
63     district, or other public agency;
64          (ii) a water company regulated by the Public Service Commission; or
65          (iii) any other owner of a community water system.
66          (2) (a) Except as provided in Subsection (2)(b) or (e), when an appropriator or the
67     appropriator's successor in interest abandons or ceases to use all or a portion of a water right for
68     a period of seven years, the water right or the unused portion of that water right is subject to
69     forfeiture in accordance with Subsection (2)(c).
70          (b) (i) An appropriator or the appropriator's successor in interest may file an
71     application for nonuse with the state engineer.
72          (ii) If a person described in Subsection (2)(b)(i) files and receives approval on a nonuse
73     application, nonuse of the water right subject to the application is not counted toward a
74     seven-year period described in Subsection (2)(a) during the period of time beginning on the day
75     on which the person files the application and ending on the day on which the application
76     expires without being renewed.
77          (iii) If a person described in Subsection (2)(b)(i) files and receives approval on
78     successive, overlapping nonuse applications, nonuse of the water right subject to the
79     applications is not counted toward a seven-year period described in Subsection (2)(a) during
80     the period of time beginning on the day on which the person files the first application and
81     ending on the day on which the last application expires without being renewed.
82          (iv) Approval of [a] one or more nonuse [application] applications, or successive
83     overlapping nonuse applications, does not protect a water right that is already subject to
84     forfeiture under Subsection (2)(a) for full or partial nonuse of the water right, nor does the
85     approval of one or more nonuse applications constitute beneficial use of the water for purposes

86     of calculating the 15-year period in Subsection (2)(c)(i).
87          (v) A nonuse application may be filed on all or a portion of the water right, including
88     water rights held by a water company.
89          (vi) After giving written notice to the water company, a shareholder may file a nonuse
90     application with the state engineer on the water represented by the stock.
91          (c) (i) Except as provided in Subsection (2)(c)(ii), a water right or a portion of the water
92     right may not be forfeited unless a judicial action to declare the right forfeited is commenced
93     within 15 years from the end of the latest period of nonuse of at least seven years.
94          (ii) (A) The state engineer, in a proposed determination of rights prepared in
95     accordance with Section 73-4-11, may not assert that a water right was forfeited unless a period
96     of nonuse of seven years ends or occurs during the 15 years immediately preceding the day on
97     which the state engineer files the proposed determination of rights with the court.
98          (B) After the day on which a proposed determination of rights is filed with the court a
99     person may not assert that a water right subject to that determination was forfeited during the
100     15-year period described in Subsection (2)(c)(ii)(A), unless the state engineer asserts forfeiture
101     in the proposed determination, or a person makes, in accordance with Section 73-4-11, an
102     objection to the proposed determination that asserts forfeiture.
103          (iii) A water right, found to be valid in a decree entered in an action for general
104     determination of rights under Chapter 4, Determination of Water Rights, is subject to a claim
105     of forfeiture based on a seven-year period of nonuse that begins after the day on which the state
106     engineer filed the related proposed determination of rights with the court, unless the decree
107     provides otherwise.
108          (iv) If in a judicial action a court declares a water right forfeited, on the date on which
109     the water right is forfeited:
110          (A) the right to use the water reverts to the public; and
111          (B) the water made available by the forfeiture:
112          (I) first, satisfies other water rights in the hydrologic system in order of priority date;
113     and

114          (II) second, may be appropriated as provided in this title.
115          (d) Except as provided in Subsection (2)(e), this section applies whether the unused or
116     abandoned water or a portion of the water is:
117          (i) permitted to run to waste; or
118          (ii) used by others without right with the knowledge of the water right holder.
119          (e) This section does not apply to:
120          (i) the use of water according to a lease or other agreement with the appropriator or the
121     appropriator's successor in interest;
122          (ii) a water right if its place of use is contracted under an approved state agreement or
123     federal conservation fallowing program;
124          (iii) those periods of time when a surface water or groundwater source fails to yield
125     sufficient water to satisfy the water right;
126          (iv) a water right when water is unavailable because of the water right's priority date;
127          (v) a water right to store water in a surface reservoir or an aquifer, in accordance with
128     Title 73, Chapter 3b, Groundwater Recharge and Recovery Act, if:
129          (A) the water is stored for present or future use; or
130          (B) storage is limited by a safety, regulatory, or engineering restraint that the
131     appropriator or the appropriator's successor in interest cannot reasonably correct;
132          (vi) a water right if a water user has beneficially used substantially all of the water right
133     within a seven-year period, provided that this exemption does not apply to the adjudication of a
134     water right in a general determination of water rights under Chapter 4, Determination of Water
135     Rights;
136          (vii) except as provided by Subsection (2)(g), a water right:
137          (A) (I) owned by a public water supplier;
138          (II) represented by a public water supplier's ownership interest in a water company; or
139          (III) to which a public water supplier owns the right of use; and
140          (B) conserved or held for the reasonable future water requirement of the public, which
141     is determined according to Subsection (2)(f);

142          (viii) a supplemental water right during a period of time when another water right
143     available to the appropriator or the appropriator's successor in interest provides sufficient water
144     so as to not require use of the supplemental water right; or
145          (ix) a period of nonuse of a water right during the time the water right is subject to an
146     approved change application where the applicant is diligently pursuing certification.
147          (f) (i) The reasonable future water requirement of the public is the amount of water
148     needed in the next 40 years by:
149          (A) the persons within the public water supplier's reasonably anticipated service area
150     based on reasonably anticipated population growth; or
151          (B) other water use demand.
152          (ii) For purposes of Subsection (2)(f)(i), a community water system's reasonably
153     anticipated service area:
154          (A) is the area served by the community water system's distribution facilities; and
155          (B) expands as the community water system expands the distribution facilities in
156     accordance with Title 19, Chapter 4, Safe Drinking Water Act.
157          (g) For a water right acquired by a public water supplier on or after May 5, 2008,
158     Subsection (2)(e)(vii) applies if:
159          (i) the public water supplier submits a change application under Section 73-3-3; and
160          (ii) the state engineer approves the change application.
161          (3) (a) The state engineer shall furnish a nonuse application form requiring the
162     following information:
163          (i) the name and address of the applicant;
164          (ii) a description of the water right or a portion of the water right, including the point of
165     diversion, place of use, and priority;
166          (iii) the quantity of water;
167          (iv) the period of use;
168          (v) the extension of time applied for;
169          (vi) a statement of the reason for the nonuse of the water; and

170          (vii) any other information that the state engineer requires.
171          (b) (i) Upon receipt of the application, the state engineer shall publish a notice of the
172     application once a week for two successive weeks:
173          (A) in a newspaper of general circulation in the county in which the source of the water
174     supply is located and where the water is to be used; and
175          (B) as required in Section 45-1-101.
176          (ii) The notice shall:
177          (A) state that an application has been made; and
178          (B) specify where the interested party may obtain additional information relating to the
179     application.
180          (c) Any interested person may file a written protest with the state engineer against the
181     granting of the application:
182          (i) within 20 days after the notice is published, if the adjudicative proceeding is
183     informal; and
184          (ii) within 30 days after the notice is published, if the adjudicative proceeding is
185     formal.
186          (d) In any proceedings to determine whether the nonuse application should be
187     approved or rejected, the state engineer shall follow the procedures and requirements of Title
188     63G, Chapter 4, Administrative Procedures Act.
189          (e) After further investigation, the state engineer may approve or reject the application.
190          (4) (a) The state engineer shall grant a nonuse application on all or a portion of a water
191     right for a period of time not exceeding seven years if the applicant shows a reasonable cause
192     for nonuse.
193          (b) A reasonable cause for nonuse includes:
194          (i) a demonstrable financial hardship or economic depression;
195          (ii) physical causes or changes that render use beyond the reasonable control of the
196     water right owner so long as the water right owner acts with reasonable diligence to resume or
197     restore the use;

198          (iii) the initiation of water conservation or efficiency practices, or the operation of a
199     groundwater recharge recovery program approved by the state engineer;
200          (iv) operation of legal proceedings;
201          (v) the holding of a water right or stock in a mutual water company without use by any
202     water supply entity to meet the reasonable future requirements of the public;
203          (vi) situations where, in the opinion of the state engineer, the nonuse would assist in
204     implementing an existing, approved water management plan; or
205          (vii) the loss of capacity caused by deterioration of the water supply or delivery
206     equipment if the applicant submits, with the application, a specific plan to resume full use of
207     the water right by replacing, restoring, or improving the equipment.
208          (5) (a) Sixty days before the expiration of a nonuse application, the state engineer shall
209     notify the applicant by mail or by any form of electronic communication through which receipt
210     is verifiable, of the date when the nonuse application will expire.
211          (b) An applicant may file a subsequent nonuse application in accordance with this
212     section.