1     
APPROVAL OF NONHAZARDOUS SOLID OR HAZARDOUS

2     
WASTE FACILITIES

3     
2021 GENERAL SESSION

4     
STATE OF UTAH

5     
Chief Sponsor: Timothy D. Hawkes

6     
Senate Sponsor: Scott D. Sandall

7     

8     LONG TITLE
9     General Description:
10          This bill addresses process of obtaining approval of nonhazardous solid or hazardous
11     waste facilities.
12     Highlighted Provisions:
13          This bill:
14          ▸     addresses legislative approval and automatic revocation of that approval; and
15          ▸     makes technical changes.
16     Money Appropriated in this Bill:
17          None
18     Other Special Clauses:
19          None
20     Utah Code Sections Affected:
21     AMENDS:
22          19-6-108, as last amended by Laws of Utah 2020, Chapter 256
23     

24     Be it enacted by the Legislature of the state of Utah:
25          Section 1. Section 19-6-108 is amended to read:
26          19-6-108. New nonhazardous solid or hazardous waste operation plans for
27     facility or site -- Approval required -- Exemptions from legislative and gubernatorial
28     approval -- Time periods for review -- Information required -- Other conditions --
29     Automatic revocation of approval -- Periodic review.

30          (1) For purposes of this section, the following items shall be treated as submission of a
31     new operation plan:
32          (a) the submission of a revised operation plan specifying a different geographic site
33     than a previously submitted plan;
34          (b) an application for modification of a commercial hazardous waste incinerator if the
35     construction or the modification would increase the hazardous waste incinerator capacity above
36     the capacity specified in the operation plan as of January 1, 1990, or the capacity specified in
37     the operation plan application as of January 1, 1990, if no operation plan approval has been
38     issued as of January 1, 1990;
39          (c) an application for modification of a commercial nonhazardous solid waste
40     incinerator if the construction of the modification would cost 50% or more of the cost of
41     construction of the original incinerator or the modification would result in an increase in the
42     capacity or throughput of the incinerator of a cumulative total of 50% above the total capacity
43     or throughput that was approved in the operation plan as of January 1, 1990, or the initial
44     approved operation plan if the initial approval is subsequent to January 1, 1990;
45          (d) an application for modification of a commercial nonhazardous solid or hazardous
46     waste treatment, storage, or disposal facility, other than an incinerator, if the modification
47     would be outside the boundaries of the property owned or controlled by the applicant, as shown
48     in the application or approved operation plan as of January 1, 1990, or the initial approved
49     operation plan if the initial approval is subsequent to January 1, 1990; or
50          (e) a submission of an operation plan to construct a facility, if previous approvals of the
51     operation plan to construct the facility have been revoked pursuant to Subsection (3)(c)(iv) or
52     (v).
53          (2) Capacity under Subsection (1)(b) shall be calculated based on the throughput
54     tonnage specified for the trial burn in the operation plan or the operation plan application if no
55     operation plan approval has been issued as of January 1, 1990, and on annual operations of
56     7,000 hours.
57          (3) (a) (i) Except as specified in Subsection (3)(a)(ii)(C), a person may not own,

58     construct, modify, or operate a facility or site for the purpose of transferring, treating, or
59     disposing of nonhazardous solid waste or treating, storing, or disposing of hazardous waste
60     without first submitting and receiving the approval of the director for an operation plan for that
61     facility or site.
62          (ii) (A) A permittee who is the current owner of a facility or site that is subject to an
63     operation plan may submit to the director information, a report, a plan, or other request for
64     approval for a proposed activity under an operation plan:
65          (I) after obtaining the consent of any other permittee who is a current owner of the
66     facility or site; and
67          (II) without obtaining the consent of any other permittee who is not a current owner of
68     the facility or site.
69          (B) The director may not:
70          (I) withhold an approval of an operation plan requested by a permittee who is a current
71     owner of the facility or site on the grounds that another permittee who is not a current owner of
72     the facility or site has not consented to the request; or
73          (II) give an approval of an operation plan requested by a permittee who is not a current
74     owner before receiving consent of the current owner of the facility or site.
75          (C) A facility referred to in Subsection (3)(a)(i) does not include a facility when the
76     waste from the extraction, beneficiation, and processing of ores and minerals listed in 40
77     C.F.R. Sec. 261.4(b)(7)(ii), or cement kiln dust, is generated and the disposal occurs at an
78     on-site location owned and operated by the generator of the waste.
79          (b) (i) Except for a facility that receives the following wastes solely for the purpose of
80     recycling, reuse, or reprocessing, a person may not own, construct, modify, or operate any
81     commercial facility that accepts for treatment or disposal, with the intent to make a profit, any
82     of the wastes listed in Subsection (3)(b)(ii) without first submitting a request to and receiving
83     the approval of the director for an operation plan for that facility site.
84          (ii) Wastes referred to in Subsection (3)(b)(i) are:
85          (A) fly ash waste, bottom ash waste, slag waste, or flue gas emission control waste

86     generated primarily from the combustion of coal or other fossil fuels;
87          (B) wastes from the extraction, beneficiation, and processing of ores and minerals; or
88          (C) cement kiln dust wastes.
89          (c) (i) A person may not construct a facility listed under Subsection (3)(c)(ii) until the
90     person receives:
91          (A) local government approval and the approval described in Subsection (3)(a);
92          (B) approval from the Legislature that, on and after May 5, 2021, is required to be
93     obtained after the person submits an application under this section; and
94          (C) after receiving the approvals described in Subsections (3)(c)(i)(A) and (B),
95     approval from the governor.
96          (ii) A facility referred to in Subsection (3)(c)(i) is:
97          (A) a commercial nonhazardous solid waste disposal facility;
98          (B) except for a facility that receives a waste listed in Subsection (3)(c)(iii), solely for
99     the purpose of recycling, reuse, or reprocessing, any commercial facility that accepts for
100     treatment or disposal, with the intent to make a profit; or
101          (C) a commercial hazardous waste treatment, storage, or disposal facility.
102          (iii) Subsection (3)(c)(ii)(B) applies to the following wastes:
103          (A) fly ash waste, bottom ash waste, slag waste, or flue gas emission control waste
104     generated primarily from the combustion of coal or other fossil fuels;
105          (B) wastes from the extraction, beneficiation, and processing of ores and minerals; or
106          (C) cement kiln dust wastes.
107          (iv) The required approvals described in Subsection (3)(c)(i) for a facility described in
108     Subsection (3)(c)(ii)(A) or (B) are automatically revoked if:
109          (A) the governor's approval is received on or after May 10, 2011, and the facility is not
110     operational within five years after the day on which the governor's approval is received; or
111          (B) the governor's approval is received before May 10, 2011, and the facility is not
112     operational on or before May 10, 2016.
113          (v) For legislative approval described in Subsection (3)(c)(i)(B), the required

114     legislative approval for a facility described in Subsection (3)(c)(ii) is automatically revoked if:
115          (A) after receiving the legislative approval, the person seeking to construct the facility
116     withdraws the application submitted under this section by providing the division a written
117     statement of withdrawal for the facility that is the basis of the legislative approval; or
118          (B) after five years from the day on which the required legislative approval takes effect,
119     the application for the facility is not approved by the division.
120          [(v)] (vi) The required approvals described in Subsection (3)(c)(i) for a facility
121     described in Subsection (3)(c)(ii)(A) or (B), including the approved operation plan, are not
122     transferrable to another person for five years after the day on which the governor's approval is
123     received.
124          (d) A person need not obtain gubernatorial or legislative approval for the construction
125     of a hazardous waste facility for which an operating plan has been approved by or submitted
126     for approval to the executive secretary of the board under this section before April 24, 1989,
127     and which has been determined, on or before December 31, 1990, by the executive secretary of
128     the board to be complete, in accordance with state and federal requirements for operating plans
129     for hazardous waste facilities even if a different geographic site is subsequently submitted.
130          (e) A person need not obtain gubernatorial and legislative approval for the construction
131     of a commercial nonhazardous solid waste disposal facility for which an operation plan has
132     been approved by or submitted for approval to the executive secretary of the board under this
133     section on or before January 1, 1990, and which, on or before December 31, 1990, the
134     executive secretary of the board determines to be complete, in accordance with state and
135     federal requirements applicable to operation plans for nonhazardous solid waste facilities.
136          (f) A person owning or operating a facility or site on or before November 19, 1980, who
137     has given timely notification as required by Section 3010 of the Resource Conservation and
138     Recovery Act of 1976, 42 U.S.C. Sec. 6921, et seq., and who has submitted a proposed
139     hazardous waste plan under this section for that facility or site, may continue to operate that
140     facility or site without violating this section until the plan is approved or disapproved under
141     this section.

142          (g) (i) The director shall suspend acceptance of further applications for a commercial
143     nonhazardous solid or hazardous waste facility upon a finding that the director cannot
144     adequately oversee existing and additional facilities for permit compliance, monitoring, and
145     enforcement.
146          (ii) The director shall report any suspension to the Natural Resources, Agriculture, and
147     Environment Interim Committee.
148          (4) The director shall review a proposed nonhazardous solid or hazardous waste
149     operation plan to determine whether that plan complies with this part and the applicable rules
150     of the board.
151          (5) (a) If the facility is a class I or class II facility, the director shall approve or
152     disapprove that plan within 270 days from the date the plan is submitted.
153          (b) Within 60 days after receipt of the plans, specifications, or other information
154     required by this section for a class I or II facility, the director shall determine whether the plan
155     is complete and contains the information necessary to process the plan for approval.
156          (c) (i) If the plan for a class I or II facility is determined to be complete, the director
157     shall issue a notice of completeness.
158          (ii) If the plan is determined by the director to be incomplete, the director shall issue a
159     notice of deficiency, listing the additional information to be provided by the owner or operator
160     to complete the plan.
161          (d) The director shall review information submitted in response to a notice of
162     deficiency within 30 days after receipt.
163          (e) The following time periods may not be included in the 270 day plan review period
164     for a class I or II facility:
165          (i) time awaiting response from the owner or operator to requests for information
166     issued by the director;
167          (ii) time required for public participation and hearings for issuance of plan approvals;
168     and
169          (iii) time for review of the permit by other federal or state government agencies.

170          (6) (a) If the facility is a class III or class IV facility, the director shall approve or
171     disapprove that plan within 365 days from the date the plan is submitted.
172          (b) The following time periods may not be included in the 365 day review period:
173          (i) time awaiting response from the owner or operator to requests for information
174     issued by the director;
175          (ii) time required for public participation and hearings for issuance of plan approvals;
176     and
177          (iii) time for review of the permit by other federal or state government agencies.
178          (7) If, within 365 days after receipt of a modification request or closure plan for any
179     facility, the director determines that the proposed plan or request, or any part of the proposed
180     plan or request, will not comply with applicable rules, the director shall issue an order
181     prohibiting any action under the proposed plan or request for modification or closure in whole
182     or in part.
183          (8) A person who owns or operates a facility or site required to have an approved
184     hazardous waste operation plan under this section and who has pending a permit application
185     before the United States Environmental Protection Agency shall be treated as having an
186     approved plan until final administrative disposition of the permit application is made under this
187     section, unless the director determines that final administrative disposition of the application
188     has not been made because of the failure of the owner or operator to furnish any information
189     requested, or the facility's interim status has terminated under Section 3005 (e) of the Resource
190     Conservation and Recovery Act, 42 U.S.C. Sec. 6925 (e).
191          (9) The director may not approve a proposed nonhazardous solid or hazardous waste
192     operation plan unless the plan contains the information that the board requires, including:
193          (a) estimates of the composition, quantities, and concentrations of any hazardous waste
194     identified under this part and the proposed treatment, storage, or disposal of the hazardous
195     waste;
196          (b) evidence that the transfer, treatment, or disposal of nonhazardous solid waste or
197     treatment, storage, or disposal of hazardous waste will not be done in a manner that may cause

198     or significantly contribute to an increase in mortality, an increase in serious irreversible or
199     incapacitating reversible illness, or pose a substantial present or potential hazard to human
200     health or the environment;
201          (c) consistent with the degree and duration of risks associated with the transfer,
202     treatment, or disposal of nonhazardous solid waste or treatment, storage, or disposal of
203     specified hazardous waste, evidence of financial responsibility in whatever form and amount
204     that the director determines is necessary to ensure continuity of operation and that upon
205     abandonment, cessation, or interruption of the operation of the facility or site, the reasonable
206     measures consistent with the available knowledge will be taken to ensure that the waste
207     subsequent to being treated, stored, or disposed of at the site or facility will not present a
208     hazard to the public or the environment;
209          (d) evidence that the personnel employed at the facility or site have education and
210     training for the safe and adequate handling of nonhazardous solid or hazardous waste;
211          (e) plans, specifications, and other information that the director considers relevant to
212     determine whether the proposed nonhazardous solid or hazardous waste operation plan will
213     comply with this part and the rules of the board;
214          (f) compliance schedules, when applicable, including schedules for corrective action or
215     other response measures for releases from a solid waste management unit at the facility,
216     regardless of the time the waste was placed in the unit;
217          (g) for a proposed operation plan submitted on or after July 1, 2013, for a new solid or
218     hazardous waste facility other than a water treatment facility that treats, stores, or disposes
219     site-generated solid or hazardous waste onsite, a traffic impact study that:
220          (i) takes into consideration the safety, operation, and condition of roadways serving the
221     proposed facility; and
222          (ii) is reviewed and approved by the Department of Transportation or a local highway
223     authority, whichever has jurisdiction over each road serving the proposed facility, with the cost
224     of the review paid by the person who submits the proposed operation plan; and
225          (h) for a proposed operation plan submitted on or after July 1, 2013, for a new

226     nonhazardous solid waste facility owned or operated by a local government, financial
227     information that discloses the costs of establishing and operating the facility, including:
228          (i) land acquisition and leasing;
229          (ii) construction;
230          (iii) estimated annual operation;
231          (iv) equipment;
232          (v) ancillary structures;
233          (vi) roads;
234          (vii) transfer stations; and
235          (viii) using other operations that are not contiguous to the proposed facility but are
236     necessary to support the facility's construction and operation.
237          (10) The director may not approve a commercial nonhazardous solid or hazardous
238     waste operation plan that meets the requirements of Subsection (9) unless the operation plan
239     contains the information required by the board, including:
240          (a) evidence that the proposed commercial facility has a proven market of
241     nonhazardous solid or hazardous waste, including:
242          (i) information on the source, quantity, and price charged for treating, storing, and
243     disposing of potential nonhazardous solid or hazardous waste in the state and regionally;
244          (ii) a market analysis of the need for a commercial facility given existing and potential
245     generation of nonhazardous solid or hazardous waste in the state and regionally; and
246          (iii) a review of other existing and proposed commercial nonhazardous solid or
247     hazardous waste facilities regionally and nationally that would compete for the treatment,
248     storage, or disposal of the nonhazardous solid or hazardous waste;
249          (b) a description of the public benefits of the proposed facility, including:
250          (i) the need in the state for the additional capacity for the management of nonhazardous
251     solid or hazardous waste;
252          (ii) the energy and resources recoverable by the proposed facility;
253          (iii) the reduction of nonhazardous solid or hazardous waste management methods, that

254     are less suitable for the environment, that would be made possible by the proposed facility; and
255          (iv) whether any other available site or method for the management of hazardous waste
256     would be less detrimental to the public health or safety or to the quality of the environment;
257     and
258          (c) compliance history of an owner or operator of a proposed commercial
259     nonhazardous solid or hazardous waste treatment, storage, or disposal facility, that may be
260     applied by the director in a nonhazardous solid or hazardous waste operation plan decision,
261     including any plan conditions.
262          (11) The director may not approve a commercial nonhazardous solid or hazardous
263     waste facility operation plan unless based on the application, and in addition to the
264     determination required in Subsections (9) and (10), the director determines that:
265          (a) the probable beneficial environmental effect of the facility to the state outweighs
266     the probable adverse environmental effect; and
267          (b) there is a need for the facility to serve industry within the state.
268          (12) Approval of a nonhazardous solid or hazardous waste operation plan may be
269     revoked, in whole or in part, if the person to whom approval of the plan has been given fails to
270     comply with that plan.
271          (13) The director shall review approved nonhazardous solid and hazardous waste
272     operation plans at least once every five years.
273          (14) Subsections (10) and (11) do not apply to a hazardous waste facility in existence or
274     to an application filed or pending in the department before April 24, 1989, that are determined
275     by the executive secretary of the board on or before December 31, 1990, to be complete, in
276     accordance with state and federal requirements applicable to operation plans for hazardous
277     waste facilities.
278          (15) Subsections (9), (10), and (11) do not apply to a nonhazardous solid waste facility
279     in existence or to an application filed or pending in the department before January 1, 1990, that
280     is determined by the director, on or before December 31, 1990, to be complete in accordance
281     with state and federal requirements applicable to operation plans for nonhazardous solid waste

282     facilities.
283          (16) Nonhazardous solid waste generated outside of this state that is defined as
284     hazardous waste in the state where the nonhazardous solid waste is generated and that is
285     received for disposal in this state may not be disposed of at a nonhazardous waste disposal
286     facility owned and operated by local government or a facility under contract with a local
287     government solely for disposal of nonhazardous solid waste generated within the boundaries of
288     the local government, unless disposal is approved by the director.
289          (17) This section may not be construed to exempt a facility from applicable regulation
290     under the federal Atomic Energy Act, 42 U.S.C. Sec. 2014 and 2021 through 2114.