2
3
4
5
6 Cosponsors:
7 Cheryl K. Acton
8 Carl R. Albrecht
9 Melissa G. Ballard
10 Stewart E. Barlow
11 Kera Birkeland
12 Bridger Bolinder
13 Brady Brammer
14 Walt Brooks
15 Jefferson S. Burton
16 Scott H. Chew
17 Kay J. Christofferson
18 Tyler Clancy
19 Joseph Elison
20 Stephanie Gricius
Matthew H. Gwynn
Katy Hall
Jon Hawkins
Colin W. Jack
Tim Jimenez
Dan N. Johnson
Marsha Judkins
Michael L. Kohler
Quinn Kotter
Trevor Lee
Karianne Lisonbee
Anthony E. Loubet
Steven J. Lund
Phil Lyman
A. Cory Maloy
Jefferson Moss
Michael J. Petersen
Thomas W. Peterson
Candice B. Pierucci
Judy Weeks Rohner
Mike Schultz
Rex P. Shipp
Keven J. Stratton
Mark A. Strong
Jordan D. Teuscher
R. Neil Walter
Stephen L. Whyte
Brad R. Wilson
21
22 LONG TITLE
23 General Description:
24 This bill modifies provisions related to the regulation of energy.
25 Highlighted Provisions:
26 This bill:
27 ▸ defines terms;
28 ▸ requires a project entity to provide notice to the Legislative Management Committee
29 180 days prior to:
30 • the disposal or sale of any project entity asset; and
31 • the decommissioning of a coal-powered electrical generation facility;
32 ▸ requires the Office of Energy Development to:
33 • conduct a study of a project entity; and
34 • report the results of the study to the Public Utilities, Energy, and Technology
35 Interim Committee;
36 ▸ modifies the state energy policy to promote the state's energy independence by:
37 • promoting the use of energy resources generated within the state; and
38 • promoting the use of clean energy sources by considering the emissions of an
39 energy resource throughout the entire life cycle of the energy resource;
40 ▸ provides legislative findings;
41 ▸ requires a qualified utility to inform the Office of the Attorney General when a
42 proposed federal regulation would result in the early retirement of an electrical
43 generation facility;
44 ▸ authorizes the Office of the Attorney General to take any action to defend the state's
45 interests with respect to electricity generation by a qualified utility facing a
46 proposed federal regulation that would result in the early retirement of an electrical
47 generation facility; and
48 ▸ makes technical changes.
49 Money Appropriated in this Bill:
50 None
51 Other Special Clauses:
52 None
53 Utah Code Sections Affected:
54 AMENDS:
55 79-6-301, as last amended by Laws of Utah 2021, Chapter 383 and renumbered and
56 amended by Laws of Utah 2021, Chapter 280
57 ENACTS:
58 11-13-318, Utah Code Annotated 1953
59 11-13-319, Utah Code Annotated 1953
60 79-6-303, Utah Code Annotated 1953
61
62 Be it enacted by the Legislature of the state of Utah:
63 Section 1. Section 11-13-318 is enacted to read:
64 11-13-318. Notice of decommissioning or disposal of project entity assets.
65 (1) As used in this section:
66 (a) "Disposal" means the sale, transfer, or other disposition of a project entity's assets.
67 (b) (i) "Project entity asset" means a project entity's:
68 (A) land;
69 (B) buildings; or
70 (C) essential equipment, including turbines, generators, transformers, and transmission
71 lines.
72 (ii) "Project entity asset" does not include an asset that is not essential for the
73 generation of electricity in the project entity's coal-powered electrical generation facility.
74 (2) A project entity shall provide a notice of decommissioning or disposal to the
75 Legislative Management Committee at least 180 days before:
76 (a) the disposal of any project entity assets; or
77 (b) the decommissioning of the project entity's coal-powered electrical generation
78 facility.
79 (3) The notice of decommissioning or disposal described in Subsection (2) shall
80 include:
81 (a) the date of the intended decommissioning or disposal;
82 (b) a description of the project entity's coal-powered electrical generation facility
83 intended for decommissioning or any project entity asset intended for disposal; and
84 (c) the reasons for the decommissioning or disposal.
85 (4) A project entity may not intentionally prevent the functionality of the project
86 entity's existing coal-powered electrical generation facility.
87 (5) Notwithstanding the requirements in Subsections (2) through (4), a project entity
88 may take any action necessary to transition to a new electrical generation facility powered by
89 natural gas, hydrogen, or a combination of natural gas and hydrogen, including any action that
90 has been approved by a permitting authority.
91 Section 2. Section 11-13-319 is enacted to read:
92 11-13-319. Project entity continued operation study.
93 (1) The Office of Energy Development shall conduct a study to:
94 (a) evaluate all environmental regulations and permits to be filed to continue operation
95 of a project entity's existing coal-powered electrical generation facility;
96 (b) identify best available technology to implement additional environmental controls
97 for continued operation of a project entity's existing coal-powered electrical generation facility;
98 (c) identify the transmission capacity of the project entity;
99 (d) coordinate with state and local economic development agencies to evaluate
100 economic opportunities for continued use of a project entity's existing coal-powered electrical
101 generation facility;
102 (e) analyze the financial assets and liabilities of a project entity;
103 (f) identify the best interests of the local economies, local tax base, and the state in
104 relation to a project entity;
105 (g) evaluate the viability of the continued operation of a project entity's existing
106 coal-powered electrical generation facility:
107 (i) under ownership of the state; or
108 (ii) in a public private partnership; and
109 (h) identify the steps necessary for the state to obtain first right of refusal for ownership
110 of a project entity's existing coal-powered electrical generation facility.
111 (2) A project entity shall cooperate and provide timely assistance and information to
112 the Office of Energy Development in the preparation of the study described in Subsection (1).
113 (3) The Office of Energy Development shall report to the Public Utilities, Energy, and
114 Technology Interim Committee and the Legislative Management Committee on or before the
115 Public Utilities, Energy, and Technology Interim Committee's September 2023 interim
116 committee meeting.
117 (4) The report described in Subsection (3) shall include:
118 (a) the results of the study described in Subsection (1);
119 (b) recommendations for continued operation of a project entity's existing
120 coal-powered electrical generation facility;
121 (c) environmental controls that need to be implemented for the continued operation of
122 a project entity's existing coal-powered electrical generation facility;
123 (d) recommendations to increase local and state tax revenue through the continued
124 operation of a project entity's existing coal-powered electrical generation facility; and
125 (e) recommendations for legislation to be introduced in the 2024 General Session to
126 enable the continued operation of a project entity's existing coal-powered electrical generation
127 facility.
128 Section 3. Section 79-6-301 is amended to read:
129 79-6-301. State energy policy.
130 (1) It is the policy of the state that:
131 (a) Utah shall have adequate, reliable, affordable, sustainable, and clean energy
132 resources;
133 (b) Utah [
134 (i) nonrenewable energy resources, including natural gas, coal, oil, oil shale, and oil
135 sands;
136 (ii) renewable energy resources, including geothermal, solar, wind, biomass, biofuel,
137 and hydroelectric;
138 (iii) nuclear power generation technologies certified for use by the United States
139 Nuclear Regulatory Commission including molten salt reactors producing medical isotopes;
140 (iv) alternative transportation fuels and technologies;
141 (v) infrastructure to facilitate energy development, diversified modes of transportation,
142 greater access to domestic and international markets for Utah's resources, and advanced
143 transmission systems;
144 (vi) energy storage, pumped storage, and other advanced energy systems, including
145 hydrogen from all sources;
146 (vii) electricity systems that can be controlled at the request of grid operators to meet
147 system load demands, to ensure an adequate supply of dispatchable energy generation
148 resources; and
149 (viii) increased refinery capacity;
150 (c) Utah [
151 to meet the state's growing demand, while contributing to the regional and national energy
152 supply, thus reducing dependence on international energy sources;
153 (d) Utah [
154 enhance the state's ability to:
155 (i) respond effectively to significant disruptions to the state's energy generation, energy
156 delivery systems, or fuel supplies; [
157 (ii) maintain adequate supply, including reserves of proven and cost-effective
158 dispatchable electricity reserves to meet grid demand; and
159 (iii) ensure the state's energy independence by promoting the use of energy resources
160 generated within the state;
161 (e) Utah [
162 although incentives and other methods may be used to ensure the state's optimal development
163 and use of energy resources in the short- and long-term;
164 (f) Utah [
165 quality;
166 (g) Utah shall promote the development of a secure supply chain from resource
167 extraction to energy production and consumption;
168 [
169 with the level of review necessary to ensure protection of the state's various interests; and
170 (ii) where federal action is required, Utah will encourage expedited federal action and
171 will collaborate with federal agencies to expedite review;
172 [
173 prices that are as low as possible while providing producers and suppliers a fair return on
174 investment, recognizing that:
175 (i) economic prosperity is linked to the availability, reliability, and affordability of
176 consumer energy supplies; and
177 (ii) investment will occur only when adequate financial returns can be realized; [
178 [
179 developing a comprehensive understanding of energy, including:
180 (i) programs addressing:
181 (A) energy conservation;
182 (B) energy efficiency;
183 (C) supply and demand; and
184 (D) energy related workforce development; and
185 (ii) energy education programs in grades [
186 (k) Utah shall promote the use of clean energy sources by considering the emissions of
187 an energy resource throughout the entire life cycle of the energy resource.
188 (2) State agencies are encouraged to conduct agency activities consistent with
189 Subsection (1).
190 (3) A person may not file suit to challenge a state agency's action that is inconsistent
191 with Subsection (1).
192 Section 4. Section 79-6-303 is enacted to read:
193 79-6-303. Legislative findings -- Forced retirement of electrical generation
194 facilities.
195 (1) As used in this section:
196 (a) "Dispatchable" means available for use on demand and generally available to be
197 delivered at a time and quantity of the operator's choosing.
198 (b) "Electrical generation facility" means a facility that generates electricity for
199 provision to customers.
200 (c) "Forced retirement" means the closure of an electrical generation facility as a result
201 of a federal regulation that either directly mandates the closure of an electrical generation
202 facility or where the costs of compliance are so high as to effectively force the closure of an
203 electrical generation facility.
204 (d) "Qualified utility" means the same as that term is defined in Section 54-17-801.
205 (e) "Reliable" means supporting a system generally able to provide a continuous supply
206 of electricity at the proper voltage and frequency and the resiliency to withstand sudden or
207 unexpected disturbances.
208 (f) "Secure" means protected against disruption, tampering, and external interference.
209 (2) The Legislature finds that:
210 (a) affordable, reliable, dispatchable, and secure energy resources are important to the
211 health, safety, and welfare of the state's citizens;
212 (b) the state has invested substantial resources in the development of affordable,
213 reliable, dispatchable, and secure energy resources within the state;
214 (c) the early retirement of an electrical generation facility that provides affordable,
215 reliable, dispatchable, and secure energy is a threat to the health, safety, and welfare of the
216 state's citizens;
217 (d) the state's police powers, reserved to the state by the United States Constitution,
218 provide the state with sovereign authority to make and enforce laws for the protection of the
219 health, safety, and welfare of the state's citizens;
220 (e) the state has a duty to defend the production and supply of affordable, reliable,
221 dispatchable, and secure energy from external regulatory interference; and
222 (f) the state's sovereign authority with respect to the retirement of an electrical
223 generation facility for the protection of the health, safety, and welfare of the state's citizens is
224 primary and takes precedence over any attempt from an external regulatory body to mandate,
225 restrict, or influence the early retirement of an electrical generation facility in the state.
226 (3) A qualified utility that receives notice of any federal regulation that may result in
227 the forced retirement of the qualified utility's electrical generation facility shall inform the
228 Office of the Attorney General of the regulation within 30 days after the receipt of notice.
229 (4) After being informed as described in Subsection (3), the Office of the Attorney
230 General may take any action necessary to defend the interest of the state with respect to
231 electricity generation by the qualified utility, including filing an action in court or participating