H.B. 365

             1     

UNENFORCEABLE AGREEMENTS - LIMITS

             2     
ON RETENTION PROCEEDS

             3     
2000 GENERAL SESSION

             4     
STATE OF UTAH

             5     
Sponsor: Susan J. Koehn

             6      AN ACT RELATING TO COMMERCE AND TRADE; AMENDING CERTAIN
             7      CONSTRUCTION CONTRACT RETENTION PROVISIONS RELATED TO CONSTRUCTION
             8      LENDERS.
             9      This act affects sections of Utah Code Annotated 1953 as follows:
             10      AMENDS:
             11          13-8-5, as enacted by Chapter 365, Laws of Utah 1999
             12      Be it enacted by the Legislature of the state of Utah:
             13          Section 1. Section 13-8-5 is amended to read:
             14           13-8-5. Definitions -- Limitation on retention proceeds withheld -- Deposit in
             15      interest-bearing escrow account -- Release of proceeds -- Payment to subcontractors --
             16      Penalty -- No waiver.
             17          (1) As used in this section:
             18          (a) (i) "Construction contract" means a written agreement between the parties relative to
             19      the design, construction, alteration, repair, or maintenance of a building, structure, highway,
             20      appurtenance, appliance, or other improvements to real property, including moving, demolition,
             21      and excavating for nonresidential commercial or industrial construction projects.
             22          (ii) If the construction contract is for construction of a project that is part residential and
             23      part non-residential, this section applies only to that portion of the construction project that is
             24      non-residential as determined pro-rata based on the percentage of the total square footage of the
             25      project that is nonresidential.
             26          (b) "Contractor" means a person who, for compensation other than wages as an employee,
             27      undertakes any work in a construction trade, as defined in Section 58-55-102 and includes:


             28          (i) any person engaged as a maintenance person who regularly engages in activities set
             29      forth in Section 58-55-102 as a construction trade; or
             30          (ii) a construction manager who performs management and counseling services on a
             31      construction project for a fee.
             32          (c) "Construction lender" means any person, including a bank, trust company, savings
             33      bank, industrial bank, land bank, safe deposit company, private banker, savings and loan
             34      association, credit union, cooperative bank, small loan company, sales finance company,
             35      investment company, or any other financial institution that advances monies to a borrower for the
             36      purpose of making alterations or improvements to real property. A construction lender does not
             37      include a person or entity who is acting in the capacity of contractor, original contractor, or
             38      subcontractor.
             39          [(c)] (d) "Original contractor" is as provided in Section 38-1-2 .
             40          [(d)] (e) "Owner" means the person who holds any legal or equitable title or interest in
             41      property. Owner does not include a construction lender unless the construction lender has an
             42      ownership interest in the property other than solely as a construction lender.
             43          [(e)] (f) "Public agency" means any state agency or political subdivision of the state that
             44      enters into a construction contract for an improvement of public property.
             45          [(f)] (g) "Retention payment" means release of retention proceeds as defined in Subsection
             46      (1)(g).
             47          [(g)] (h) "Retention proceeds" means monies earned by a contractor or subcontractor but
             48      retained by the owner or public agency pursuant to the terms of a construction contract to
             49      guarantee payment or performance by the contractor or subcontractor of the construction contract.
             50          [(h)] (i) "Subcontractor" is as defined in Section 38-1-2 .
             51          [(i)] (j) "Successful party" has the same meaning as it does under Section 38-1-18 .
             52          (2) (a) This section is applicable to all construction contracts relating to construction work
             53      or improvements entered into on or after July 1, 1999, between:
             54          [(a)] (i) an owner or public agency and an original contractor;
             55          [(b)] (ii) an original contractor and a subcontractor; and
             56          [(c)] (iii) subcontractors under a contract described in Subsection (2)(a) or (b).
             57          (b) This section does not apply to a construction lender.
             58          (3) (a) Notwithstanding Section 58-55-603 , the retention proceeds withheld and retained


             59      from any payment due under the terms of the construction contract may not exceed 5% of the
             60      payment:
             61          (i) by the owner or public agency to the original contractor;
             62          (ii) by the original contractor to any subcontractor; or
             63          (iii) by a subcontractor.
             64          (b) The total retention proceeds withheld may not exceed 5% of the total construction
             65      price.
             66          (c) The percentage of the retention proceeds withheld and retained pursuant to a
             67      construction contract between the original contractor and a subcontractor or between
             68      subcontractors shall be the same retention percentage as between the owner and the original
             69      contractor if:
             70          (i) the retention percentage in the original construction contract between an owner and the
             71      original contractor is less than 5%; or
             72          (ii) after the original construction contract is executed but before completion of the
             73      construction contract the retention percentage is reduced to less than 5%.
             74          (4) (a) If any payment on a contract with a private contractor, firm, or corporation to do
             75      work for an owner or public agency is retained or withheld by the owner or the public agency, as
             76      retention proceeds, it shall be placed in an interest-bearing account.
             77          (b) The interest accrued under Subsection (4)(a) shall be:
             78          (i) for the benefit of the contractor and subcontractors; and
             79          (ii) paid after the project is completed and accepted by the owner or the public agency.
             80          (c) The contractor shall ensure that any interest accrued on the retainage is distributed by
             81      the contractor to subcontractors on a pro rata basis.
             82          (5) Any retention proceeds retained or withheld pursuant to this section and any accrued
             83      interest shall be released pursuant to a billing statement from the contractor within 45 days from
             84      the later of:
             85          (a) the date the owner or public agency receives the billing statement from the contractor;
             86          (b) the date that a certificate of occupancy or final acceptance notice is issued to:
             87          (i) the original contractor who obtained the building permit from the building inspector
             88      or public agency;
             89          (ii) the owner or architect; or


             90          (iii) the public agency;
             91          (c) the date that a public agency or building inspector having authority to issue its own
             92      certificate of occupancy does not issue the certificate but permits partial or complete occupancy
             93      of a newly constructed or remodeled building; or
             94          (d) the date the contractor accepts the final pay quantities.
             95          (6) If only partial occupancy of a building is permitted, any retention proceeds withheld
             96      and retained pursuant to this section and any accrued interest shall be partially released within 45
             97      days under the same conditions as provided in Subsection (5) in direct proportion to the value of
             98      the part of the building occupied.
             99          (7) The billing statement from the contractor as provided in Subsection (5)(a) shall include
             100      documentation of lien releases or waivers.
             101          (8) (a) Notwithstanding Subsection (3):
             102          (i) if a contractor or subcontractor is in default or breach of the terms and conditions of the
             103      construction contract documents, plans, or specifications governing construction of the project, the
             104      owner or public agency may withhold from payment for as long as reasonably necessary an amount
             105      necessary to cure the breach or default of the contractor or subcontractor; or
             106          (ii) if a project or a portion of the project has been substantially completed, the owner or
             107      public agency may retain until completion up to twice the fair market value of the work of the
             108      original contractor or of any subcontractor that has not been completed:
             109          (A) in accordance with the construction contract documents, plans, and specifications; or
             110          (B) in the absence of plans and specifications, to generally accepted craft standards.
             111          (b) An owner or public agency that refuses payment under Subsection (8)(a) shall describe
             112      in writing within 45 days of withholding such amounts what portion of the work was not
             113      completed according to the standards specified in Subsection (8)(a).
             114          (9) (a) Except as provided in Subsection (9)(b), an original contractor or subcontractor
             115      who receives retention proceeds shall pay each of its subcontractors from whom retention has been
             116      withheld each subcontractor's share of the retention received within ten days from the day that all
             117      or any portion of the retention proceeds is received:
             118          (i) by the original contractor from the owner or public agency; or
             119          (ii) by the subcontractor from:
             120          (A) the original contractor; or


             121          (B) a subcontractor.
             122          (b) Notwithstanding Subsection (9)(a), if a retention payment received by the original
             123      contractor is specifically designated for a particular subcontractor, payment of the retention shall
             124      be made to the designated subcontractor.
             125          (10) (a) In any action for the collection of the retained proceeds withheld and retained in
             126      violation of this section, the successful party is entitled to:
             127          (i) attorney's fees; and
             128          (ii) other allowable costs.
             129          (b) (i) Any owner, public agency, original contractor, or subcontractor who knowingly and
             130      wrongfully withholds a retention shall be subject to a charge of 2% per month on the improperly
             131      withheld amount, in addition to any interest otherwise due.
             132          (ii) The charge described in Subsection (10)(b)(i) shall be paid to the contractor or
             133      subcontractor from whom the retention proceeds have been wrongfully withheld.
             134          (11) [It is against public policy for any] A party to a construction contract may not require
             135      any other party to waive any provision of this section.




Legislative Review Note
    as of 2-10-00 11:39 AM


A limited legal review of this legislation raises no obvious constitutional or statutory concerns.

Office of Legislative Research and General Counsel


[Bill Documents][Bills Directory]