Download Zipped Introduced WP 9 SB0219S4.ZIP 16,438 Bytes
[Status][Bill Documents][Fiscal Note][Bills Directory]

Fourth Substitute S.B. 219

Senator Michael G. Waddoups proposes to substitute the following bill:


             1     
CONSTRUCTION CONTRACTS - PROMPT

             2     
PAYMENT ACT

             3     
2001 GENERAL SESSION

             4     
STATE OF UTAH

             5     
Sponsor: Michael G. Waddoups

             6      This act modifies the Commerce and Trade Code by enacting the Utah Construction
             7      Contracts Prompt Payment Act. The act requires progress payments on certain construction
             8      contracts. The act requires the owner to promptly dispute a billing or estimate with which
             9      the owner does not agree and limits the amount that an owner can withhold from a progress
             10      payment. The act requires prompt payment by the owner upon completion of the work. The
             11      act provides for interest on late payments. The act gives subcontractors the right to
             12      notification of progress payments. The act provides for the awarding of costs and attorneys'
             13      fees. The act requires prompt payment by the contractor to subcontractors and suppliers.
             14      The act requires the wavier of mechanics' lien rights by subcontractors and suppliers upon
             15      receipt of payment. The act provides for the interruption of the work on a construction
             16      contract without penalty in cases of an environmental hazard. The act provides for the
             17      interruption of work on a construction contract or the termination of the contract in cases
             18      of nonpayment. The act provides an effective date.
             19      This act affects sections of Utah Code Annotated 1953 as follows:
             20      AMENDS:
             21          58-55-501, as last amended by Chapters 233 and 317, Laws of Utah 2000
             22      ENACTS:
             23          13-33-101, Utah Code Annotated 1953
             24          13-33-102, Utah Code Annotated 1953
             25          13-33-103, Utah Code Annotated 1953


             26          13-33-201, Utah Code Annotated 1953
             27          13-33-202, Utah Code Annotated 1953
             28          13-33-203, Utah Code Annotated 1953
             29          13-33-204, Utah Code Annotated 1953
             30      Be it enacted by the Legislature of the state of Utah:
             31          Section 1. Section 13-33-101 is enacted to read:
             32     
CHAPTER 33. UTAH CONSTRUCTION CONTRACTS PROMPT PAYMENT ACT

             33     
Part 1. General Provisions

             34          13-33-101. Title.
             35          This chapter is known as the "Utah Construction Contracts Prompt Payment Act."
             36          Section 2. Section 13-33-102 is enacted to read:
             37          13-33-102. Definitions.
             38          As used in this chapter:
             39          (1) the terms "construction contract", "contractor", and "subcontractor" have the same
             40      meaning as defined in Section 13-8-4 ;
             41          (2) "construction project bid documents" means the drawings, specifications, invitation
             42      for bids, request for proposals, or any other written document describing the proposed construction
             43      project that requests the submission of bids or prices for furnishing labor, materials, supplies, or
             44      equipment for construction of the project; and
             45          (3) "owner" means a person holding any legal or equitable title or interest in the real
             46      property which is the subject of a construction contract.
             47          Section 3. Section 13-33-103 is enacted to read:
             48          13-33-103. Scope of chapter.
             49          (1) Where there are any conflicts between the provisions of this chapter with the provisions
             50      of Title 15, Chapter 6, Utah Prompt Payment Act, the provisions of this chapter shall govern.
             51          (2) This chapter applies to all construction contracts entered into on or after July 1, 2001.
             52          Section 4. Section 13-33-201 is enacted to read:
             53     
Part 2. Prompt Payment

             54          13-33-201. Progress payments to contractor -- Payment upon completion of work --
             55      Withholdings from payments -- Approval of billings -- Interest on late payments
             56      --Notification to subcontractor of payments by owner -- Costs and attorneys' fees.


             57          (1) An owner shall make progress payments as provided in Subsection (2) to a contractor
             58      on all construction contracts where the contract performance period exceeds 45 calendar days.
             59          (2) (a) Progress payments shall be made on the basis of a duly certified and approved
             60      billing or estimate of the work performed and the materials supplied during the preceding monthly
             61      billing cycle, or an alternate billing cycle as stated in the construction contract.
             62          (b) If billings or estimates are to be submitted in other than monthly billing cycles, the
             63      construction project bid documents shall specifically identify the alternate billing cycle in a clear
             64      and conspicuous manner as prescribed in Subsection (3).
             65          (c) Except as provided in Subsection (4), the owner shall make progress payments to the
             66      contractor within seven working days after the date the billing or estimate is certified and approved
             67      pursuant to Subsection (5).
             68          (d) The contractor shall provide a waiver of any mechanics' or materialmans' lien
             69      conditioned upon payment for the work completed and materials supplied. The owner may require
             70      that these conditional waivers of lien be notarized.
             71          (3) (a) A construction contract may provide for a billing cycle other than a monthly billing
             72      cycle if:
             73          (i) the construction project bid documents and the construction contract specifically set
             74      forth the alternate billing cycle; and
             75          (ii) the provisions of either Subsection (3)(b) or (3)(c) are satisfied.
             76          (b) The following legend or substantially similar language setting forth the other billing
             77      cycle appears in clear and conspicuous type on the construction project bid documents and the
             78      construction contract:
             79          "Notice of alternate billing cycle.
             80          "This contract allows the owner to require the submission of billings or estimates in billing
             81      cycles other than monthly. Billings or estimates for this contract shall be submitted as follows:
             82      [description of alternate billing cycle]."
             83          (c) The following legend or substantially similar language setting forth the other billing
             84      cycle appears in clear and conspicuous type on the construction project bid documents and the
             85      construction contract:
             86          "Notice of alternate billing cycle.
             87          "This contract allows the owner to require the submission of billings or estimates in billing


             88      cycles other than monthly. A written description of the alternate billing cycle applicable to the
             89      project is available from the owner or the owner's designated agent at [telephone number or
             90      address, or both], and the owner or its designated agent shall provide this written description on
             91      request."
             92          (4) An owner may make progress payments and final payment later than seven working
             93      days after the date the billing or estimate is certified and approved if both:
             94          (a) the construction project bid documents and the construction contract in a clear and
             95      conspicuous manner specifically provide for a later payment defined by a specified number of days
             96      after certification and approval; and
             97          (b) the following legend or substantially similar language setting forth the specified
             98      number of days appears in clear and conspicuous type on the construction project bid documents
             99      and the construction contract:
             100          "Notice of extended payment provision.
             101          "This contract allows the owner to make payment within _____ days after certification and
             102      approval of billings and estimates."
             103          (5) (a) Except as provided in Subsection (7), a billing or estimate shall be considered to
             104      be approved and certified 14 calendar days after the owner receives the billing or estimate, unless
             105      before that time the owner or the owner's agent prepares and issues a written statement detailing
             106      those items in the billing or estimate that are not approved and certified.
             107          (b) An owner may decline to approve and certify a billing or estimate or a portion of a
             108      billing or estimate for:
             109          (i) unsatisfactory job progress;
             110          (ii) defective construction work or materials which have not been remedied;
             111          (iii) disputed work or materials;
             112          (iv) failure to comply with a material provision of the construction contract;
             113          (v) third-party claims filed or reasonable evidence that a claim will be filed;
             114          (vi) failure of the contractor or a subcontractor to make timely payments for labor,
             115      equipment, or materials;
             116          (vii) damage to the owner;
             117          (viii) reasonable evidence that the construction contract cannot be completed for the
             118      unpaid balance of the construction contract sum; or


             119          (ix) a reasonable amount for retention as provided in Section 13-8-5 .
             120          (c) The owner is considered to have received the billing or estimate when the billing or
             121      estimate is submitted to any person designated by the owner for the receipt of these submissions
             122      or for review or approval of the billing or estimate.
             123          (6) Except as provided in Section 13-8-5 , an owner may withhold from a progress payment
             124      only an amount that is sufficient to pay the direct expenses the owner reasonably expects to incur
             125      to correct any items set forth in writing pursuant to Subsection (5).
             126          (7) An owner may extend the period within which the billing or estimate is certified and
             127      approved if both:
             128          (a) the construction project bid documents and the construction contract in a clear and
             129      conspicuous manner specifically provide for an extended time period within which a billing or
             130      estimate shall be certified and approved, defined by a specified number of days after the owner has
             131      received the billing or estimate; and
             132          (b) the following legend or substantially similar language, setting forth the specified
             133      number of days, appears in clear and conspicuous type on the construction project bid documents
             134      and the construction contract:
             135          "Notice of extended certification and approval period provision.
             136          "This contract allows the owner to certify and approve billings and estimates within ______
             137      days after the billings and estimates are received from the contractor."
             138          (8) Except as provided in Subsection (4) and in Section 13-8-5 :
             139          (a) when a contractor completes and an owner approves and certifies all work under a
             140      construction contract, the owner shall make payment in full on the construction contract within
             141      seven working days;
             142          (b) when a contractor completes and an owner approves and certifies all work under a
             143      portion of a construction contract for which the construction contract states a separate price, the
             144      owner shall make payment in full on that portion of the construction contract within seven working
             145      days; and
             146          (c) on construction projects that require a federal agency's final approval or certification,
             147      the owner shall make payment in full on the construction contract within seven working days of
             148      the federal agency's final approval or certification.
             149          (9) Payment shall not be required pursuant to this section unless the contractor provides


             150      the owner with a billing or estimate for the work performed or the material supplied in accordance
             151      with the terms of the construction contract between the parties.
             152          (10) Except as otherwise specifically provided in this chapter, a construction contract shall
             153      not alter the rights of any contractor, subcontractor, or material supplier to receive prompt and
             154      timely progress payments.
             155          (11) If an owner or a third party designated by an owner as the person responsible for
             156      making progress payments on a construction contract does not make a timely payment pursuant
             157      to this section, the owner shall pay the contractor interest at the rate of 1.5% per month or fraction
             158      of a month on the unpaid balance, or at a higher rate as the parties to the construction contract
             159      agree.
             160          (12) On the written request of a subcontractor, the owner shall notify the subcontractor
             161      within five working days after the issuance of a progress payment to the contractor or final
             162      payment to the contractor on the construction contract.
             163          (13) In any action or arbitration brought to collect payments or interest pursuant to this
             164      section, the successful party shall be awarded its costs and reasonable attorneys' fees.
             165          (14) If the owner and contractor on a construction project are a single entity, that entity
             166      shall pay its subcontractors and material suppliers within 14 calendar days after the billing or
             167      estimate is certified and approved unless the deadlines for approval and certification or for
             168      payment have been modified pursuant to Subsection (4) or (7).
             169          (15) For purposes of this chapter, payment shall be considered to have been made at the
             170      time the payment is sent.
             171          Section 5. Section 13-33-202 is enacted to read:
             172          13-33-202. Progress payments to subcontractor or supplier -- Waiver of liens --
             173      Withholdings from a payment -- Interest on late payments -- Costs and attorneys' fees.
             174          (1) Notwithstanding any other provision of this section, performance by a contractor,
             175      subcontractor, or material supplier in accordance with the provisions of a construction contract
             176      entitles the contractor, subcontractor, or material supplier to payment from the party with whom
             177      the contractor, subcontractor, or material supplier contracts.
             178          (2) (a) If a subcontractor or material supplier has performed in accordance with the
             179      provisions of a construction contract, the contractor shall pay to its subcontractors or material
             180      suppliers and each subcontractor shall pay to its subcontractors or material suppliers, within seven


             181      working days of receipt by the contractor or subcontractor of each progress payment or final
             182      payment, the full amount received for that subcontractor's work and materials supplied based on
             183      work completed or materials supplied under the subcontract.
             184          (b) Payment shall not be required pursuant to this Subsection (2) unless the subcontractor
             185      or material supplier provides to the contractor or subcontractor a billing or invoice for the work
             186      performed or material supplied in compliance with the terms of the contract between the parties.
             187          (c) Each subcontractor or material supplier shall provide a waiver of any mechanics' or
             188      materialmans' lien conditioned upon payment for the work completed or material supplied. The
             189      contractor or subcontractor may require that these conditional waivers of lien be notarized.
             190          (3) Nothing in this section prevents the contractor or subcontractor, at the time of
             191      application or certification to the owner or contractor, from withholding the application or
             192      certification to the owner or contractor for payment to the subcontractor or material supplier for:
             193          (a) unsatisfactory job progress;
             194          (b) defective construction work or materials which have not been remedied;
             195          (c) disputed work or materials;
             196          (d) failure to comply with a material provision of the subcontract;
             197          (e) third-party claims filed or reasonable evidence that a claim will be filed;
             198          (f) failure of the subcontractor to make timely payments for labor, equipment, or materials;
             199          (g) damage to the contractor or another subcontractor or material supplier;
             200          (h) reasonable evidence that the subcontract cannot be completed for the unpaid balance
             201      of the subcontract sum; or
             202          (i) a reasonable amount for retention as provided in Section 13-8-5 that does not exceed
             203      the actual percentage retained by the owner.
             204          (4) If a periodic or final payment to a subcontractor or material supplier is delayed by more
             205      than seven working days after receipt of periodic or final payment by the contractor or
             206      subcontractor, the contractor or subcontractor shall pay its subcontractor or material supplier
             207      interest, except for periods of time during which payment is withheld pursuant to Subsection (3),
             208      at the rate of 1.5% per month or a fraction of a month on the unpaid balance or at a higher rate as
             209      the parties agree.
             210          (5) In any action or arbitration brought to collect payments or interest pursuant to this
             211      section, the successful party shall be awarded costs and reasonable attorneys' fees.


             212          Section 6. Section 13-33-203 is enacted to read:
             213          13-33-203. Interruption of work for environmental hazard -- Termination of
             214      contract.
             215          (1) A contractor may interrupt the performance of a construction contract without penalty
             216      or liability for breach of contract if:
             217          (a) (i) any applicable law or rule requires the cessation of work; or
             218          (ii) (A) the contractor encounters any hazardous substance or hazardous material which
             219      is required to be removed or contained by any applicable law or rule; and
             220          (B) (I) any applicable law or rule prohibits the contractor from proceeding to remove or
             221      contain the hazardous material or hazardous substance unless the contractor is duly licensed and
             222      the contractor is not so licensed; or
             223          (II) the removal or containment of the hazardous material or hazardous substance cannot
             224      be accomplished without a cessation of work; and
             225          (b) the situation which resulted in the cessation of work under Subsection (1)(a) was not:
             226          (i) caused by the contractor or any agent, employee, subcontractor, or supplier of the
             227      contractor; or
             228          (ii) part of the scope of the work under the construction contract.
             229          (2) A contractor whose work is impaired, impeded, or prohibited under Subsection (1) may
             230      interrupt performance of the construction contract as provided in this section only to the extent of
             231      the area affected by the hazardous materials or hazardous substances removed or contained by the
             232      owner or as otherwise required by applicable statute or rule.
             233          (3) The owner may terminate the construction contract on payment to the contractor,
             234      subcontractor, or other person whose work is delayed under Subsection (1) of the amount of any
             235      services or materials supplied or expended which conform to the contract terms and specifications.
             236          (4) A contractor who interrupts the performance of a construction contract under this
             237      section is entitled to recover any costs incurred for mobilization resulting from the shutdown and
             238      restart of the project.
             239          Section 7. Section 13-33-204 is enacted to read:
             240          13-33-204. Suspension or termination of work for nonpayment -- Notice -- Costs and
             241      attorneys' fees.
             242          (1) (a) A contractor may suspend performance under a construction contract or terminate


             243      a construction contract for failure by the owner to make timely payment of the amount certified
             244      and approved pursuant to Subsection 13-33-201 (5).
             245          (b) A contractor shall provide written notice to the owner at least seven working days
             246      before the contractor's intended suspension or termination unless a shorter notice period is
             247      prescribed in the construction contract between the owner and contractor. A construction contract
             248      may not extend the time period for a contractor to suspend performance or terminate a construction
             249      contract under this Subsection (1).
             250          (c) The suspension of performance or termination of a construction contract pursuant to
             251      this Subsection (1) does not constitute a breach of contract by the contractor.
             252          (2) (a) A subcontractor may suspend performance under a construction contract or
             253      terminate a construction contract if the owner fails to make timely payment of amounts certified
             254      and approved pursuant to Subsection 13-33-201 (5) for the subcontractor's work and the contractor
             255      fails to pay the subcontractor for the certified and approved work.
             256          (b) A subcontractor shall provide written notice to the contractor and owner at least seven
             257      working days before the subcontractor's intended suspension or termination unless a shorter notice
             258      period is prescribed in the construction contract between the contractor and subcontractor. A
             259      construction contract may not extend the time period for a subcontractor to suspend performance
             260      or terminate a construction contract under this Subsection (2).
             261          (c) The suspension of performance or termination of a subcontract pursuant to this
             262      Subsection (2) does not constitute a breach of contract by the subcontractor.
             263          (3) (a) A subcontractor may suspend performance under a construction contract or
             264      terminate a construction contract if the owner makes timely payment of amounts certified and
             265      approved pursuant to Subsection 13-33-201 (5) for the subcontractor's work but the contractor fails
             266      to pay the subcontractor for the certified and approved work.
             267          (b) A subcontractor shall provide written notice to the contractor and owner at least seven
             268      working days before the subcontractor's intended suspension or termination unless a shorter notice
             269      period is prescribed in the construction contract between the contractor and subcontractor. A
             270      construction contract may not extend the time period for a subcontractor to suspend performance
             271      or terminate a construction contract under this Subsection (3).
             272          (c) The suspension of performance or termination of a subcontract pursuant to this
             273      Subsection (3) does not constitute a breach of contract by the subcontractor.


             274          (4) (a) A subcontractor may suspend performance under a construction contract or
             275      terminate a construction contract if the owner declines to approve and certify portions of the
             276      contractor's billing or estimate pursuant to Subsection 13-33-201 (5) for that subcontractor's work
             277      but the reasons for that failure by the owner to approve and certify are not the fault of or directly
             278      related to the subcontractor's work.
             279          (b) A subcontractor shall provide written notice to the contractor and owner at least seven
             280      working days before the subcontractor's intended suspension or termination unless a shorter notice
             281      period is prescribed in the construction contract between the contractor and subcontractor. A
             282      construction contract may not extend the time period for a subcontractor to suspend performance
             283      or terminate a construction contract under this Subsection (4).
             284          (c) The suspension of performance or termination of a subcontract pursuant to this
             285      Subsection (4) does not constitute a breach of contract by the subcontractor.
             286          (5) A contractor or subcontractor that suspends performance as provided in this section
             287      is not required to furnish further labor, materials, or services until the contractor or subcontractor
             288      is paid the amount that was certified and approved, together with any costs incurred for
             289      mobilization resulting from the shutdown or start-up of a project.
             290          (6) In any action or arbitration brought pursuant to this section, the successful party shall
             291      be awarded costs and reasonable attorneys' fees.
             292          (7) Written notice required under this section shall be provided by:
             293          (a) delivery of a written notice in person to the individual or a member of the entity or to
             294      an officer of the corporation for which it was intended; or
             295          (b) sending the written notice by any means that provides written, third-party verification
             296      of delivery to the last business address known to the party giving notice.
             297          Section 8. Section 58-55-501 is amended to read:
             298           58-55-501. Unlawful conduct.
             299          Unlawful conduct includes:
             300          (1) engaging in a construction trade, acting as a contractor, an alarm business or company,
             301      or an alarm company agent, or representing oneself to be engaged in a construction trade or to be
             302      acting as a contractor in a construction trade requiring licensure, unless the person doing any of
             303      these is appropriately licensed or exempted from licensure under this chapter;
             304          (2) acting in a construction trade, as an alarm business or company, or as an alarm


             305      company agent beyond the scope of the license held;
             306          (3) hiring or employing in any manner an unlicensed person, other than an employee for
             307      wages who is not required to be licensed under this chapter, to engage in a construction trade for
             308      which licensure is required or to act as a contractor or subcontractor in a construction trade
             309      requiring licensure;
             310          (4) applying for or obtaining a building permit either for oneself or another when not
             311      licensed or exempted from licensure as a contractor under this chapter;
             312          (5) issuing a building permit to any person for whom there is no evidence of a current
             313      license or exemption from licensure as a contractor under this chapter;
             314          (6) applying for or obtaining a building permit for the benefit of or on behalf of any other
             315      person who is required to be licensed under this chapter but who is not licensed or is otherwise not
             316      entitled to obtain or receive the benefit of the building permit;
             317          (7) failing to obtain a building permit when required by law or rule;
             318          (8) submitting a bid for any work for which a license is required under this chapter by a
             319      person not licensed or exempted from licensure as a contractor under this chapter;
             320          (9) willfully or deliberately misrepresenting or omitting a material fact in connection with
             321      an application to obtain or renew a license under this chapter;
             322          (10) allowing one's license to be used by another except as provided by statute or rule;
             323          (11) doing business under a name other than the name appearing on the license, except as
             324      permitted by statute or rule;
             325          (12) if licensed as a specialty contractor in the electrical trade or plumbing trade,
             326      journeyman plumber, residential journeyman plumber, journeyman electrician, master electrician,
             327      or residential electrician, failing to directly supervise an apprentice under one's supervision or
             328      exceeding the number of apprentices one is allowed to have under his supervision;
             329          (13) if licensed as a contractor or representing oneself to be a contractor, receiving any
             330      funds in payment for a specific project from an owner or any other person, which funds are to pay
             331      for work performed or materials and services furnished for that specific project, and after receiving
             332      the funds to exercise unauthorized control over the funds by failing to pay the full amounts due and
             333      payable to persons who performed work or furnished materials or services within a reasonable
             334      period of time;
             335          (14) employing as an alarm company an unlicensed individual as an alarm company agent,


             336      except as permitted under the exemption from licensure provisions under Section 58-1-307 ;
             337          (15) if licensed as an alarm company or alarm company agent, filing with the division
             338      fingerprint cards for an applicant which are not those of the applicant, or are in any other way false
             339      or fraudulent and intended to mislead the division in its consideration of the applicant for
             340      licensure;
             341          (16) if licensed under this chapter, willfully or deliberately disregarding or violating:
             342          (a) the building or construction laws of this state or any political subdivision;
             343          (b) the safety and labor laws applicable to a project;
             344          (c) any provision of the health laws applicable to a project;
             345          (d) the workers' compensation insurance laws of the state applicable to a project;
             346          (e) the laws governing withholdings for employee state and federal income taxes,
             347      unemployment taxes, FICA, or other required withholdings; or
             348          (f) reporting, notification, and filing laws of this state or the federal government;
             349          (17) aiding or abetting any person in evading the provisions of this chapter or rules
             350      established under the authority of the division to govern this chapter; [or]
             351          (18) engaging in the construction trade or as a contractor for the construction of residences
             352      of up to two units when not currently registered or exempt from registration as a qualified
             353      beneficiary under Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act[.];
             354      or
             355          (19) violating the provisions of Section 13-33-202 .
             356          Section 9. Effective date.
             357          This act takes effect on July 1, 2001.


[Bill Documents][Bills Directory]