S.B. 4002 Enrolled
John L. ValentineEd P. Mayne This act modifies the Public Utilities title to enact the Industrial Electric Infrastructure Act
including the definition of terms. The act establishes what is a covered expense of an electrical
corporation for new industrial electric infrastructure and how customers become eligible to
participate in infrastructure agreements. The act provides the requirements for infrastructure
agreements and certain electric service contracts. The act provides that covered expenses will
be recovered by the electrical corporation from its customers in Utah. The act provides for the
accounting treatment of covered expenses. The act provides direction regarding how recovery
of covered expenses are to be apportioned amongst customers should an eligible customer fail
to pay amounts owed under an infrastructure agreement.
This act affects sections of Utah Code Annotated 1953 as follows:
ENACTS:
54-16-101, Utah Code Annotated 1953
54-16-102, Utah Code Annotated 1953
54-16-201, Utah Code Annotated 1953
54-16-202, Utah Code Annotated 1953
54-16-203, Utah Code Annotated 1953
54-16-301, Utah Code Annotated 1953
54-16-302, Utah Code Annotated 1953
Be it enacted by the Legislature of the state of Utah:
Section 1. Section 54-16-101 is enacted to read:
54-16-101. Title.
This chapter is known as the "Industrial Electric Infrastructure Act."
Section 2. Section 54-16-102 is enacted to read:
54-16-102. Definitions.
As used in this chapter:
(1) "Covered expense" means an expense classified as a covered expense in accordance with
Section 54-16-201 .
(2) "Eligible customer" means a person that is an eligible customer under Section 54-16-202 .
(3) "Expense" means an expense incurred by an electrical corporation in connection with new
industrial electric infrastructure, including:
(a) design and engineering;
(b) acquisition of rights-of-way;
(c) purchase of new industrial electric infrastructure;
(d) construction of new industrial electric infrastructure;
(e) capital overhead charges, such as labor and other charges, that:
(i) have been identified as capital; and
(ii) are general in nature and not directly related to the new industrial electric infrastructure; and
(f) an expense similar to an expense listed in Subsections (3)(a) through (e).
(4) "Infrastructure agreement" means an agreement that:
(a) is required by Section 54-16-201 ; and
(b) complies with Subsections 54-16-203 (1) through (3).
(5) (a) "New industrial electric infrastructure" means a facility or equipment that is:
(i) constructed, expanded, installed, or upgraded:
(A) under an infrastructure agreement; and
(B) after the day on which the infrastructure agreement is executed; and
(ii) reasonably necessary or appropriate to provide electric service to a new industrial facility.
(b) "New industrial electric infrastructure" includes any of the following that meet the conditions
listed in Subsection (5)(a):
(i) the construction, expansion, or upgrading of:
(A) an electric substation;
(B) an electric transformer;
(C) a switching gear;
(D) a facility related to a facility described in Subsections (5)(b)(i)(A) through (C); or
(E) from an electric substation to a new industrial facility:
(I) a transmission or distribution line;
(II) a transmission or distribution pole; or
(III) a facility related to a facility described in Subsection (5)(b)(i)(E)(I) or (II); or
(ii) any necessary or appropriate upgrading of an electric line or facility affected by the
construction, expansion, installation, or upgrading of other industrial electric infrastructure.
(6) "New industrial facility" means one or more buildings, machinery, equipment, or other facilities
that:
(a) in the aggregate will be used:
(i) in a manufacturing process within the state; or
(ii) for activities related to the manufacturing process described in Subsection (6)(a)(i); and
(b) the construction or acquisition of which will require capital investment by the eligible customer:
(i) after the day on which a statement of eligibility is filed under Section 54-16-202 ; and
(ii) in an amount equal to or in excess of the capital costs required by Subsection 54-16-202 (2).
Section 3. Section 54-16-201 is enacted to read:
54-16-201. Classifying an expense as a covered expense.
For purposes of this chapter, an electrical corporation may classify an expense incurred by the
electrical corporation as a covered expense if:
(1) prior to the expense being incurred:
(a) the electrical corporation executes:
(i) an infrastructure agreement that complies with Subsections 54-16-203 (1) through (3); and
(ii) a contract for electric services as provided in Subsection 54-16-203 (4); and
(b) the eligible customer has secured financing for the construction of the new industrial facility; and
(2) the expense is:
(a) reasonable; and
(b) directly related to the new industrial electric infrastructure specified in the infrastructure
agreement required by Subsection (1)(a).
Section 4. Section 54-16-202 is enacted to read:
54-16-202. Eligible customer.
(1) A person becomes an eligible customer:
(a) 15 days after the day on which the person files with the commission a statement of eligibility
that complies with Subsection (2) if no request for findings is filed in accordance with Subsection (3); or
(b) the day on which the commission makes a finding in accordance with Subsection (3) that the
person is an eligible customer if:
(i) the person files with the commission a statement of eligibility that complies with Subsection (2);
and
(ii) a request for findings on the statement of eligibility is filed in accordance with Subsection (3).
(2) A statement of eligibility filed under this section shall certify that:
(a) the person filing the statement is a customer of the electrical corporation on the day on which
the statement of eligibility is filed;
(b) the person filing the statement of eligibility reasonably believes that within five years from the
day on which the statement of eligibility is filed the person will begin operating a new industrial facility:
(i) that requires new industrial electric infrastructure;
(ii) operation of which will require peak electric loads that exceed the person's peak electric loads
during the calendar year in which the person files the statement of eligibility by at least 50 megawatts;
(iii) for which during the five year period beginning on the day on which the person files the
statement of eligibility the person will have capital costs that equal or exceed $50,000,000; and
(iv) operation of which will require the creation or retention of at least 500 jobs:
(A) within the state; and
(B) that are:
(I) related to the operation of the new industrial facility;
(II) full-time positions; and
(III) anticipated to be filled for not less than one year; and
(c) the person filing the statement of eligibility reasonably believes that the new industrial electric
infrastructure described in Subsection (2)(b)(i):
(i) will have a cost to the electrical corporation equal to or in excess of $20,000,000; and
(ii) but for the operation of the new industrial facility:
(A) would not be built by the electrical corporation; or
(B) would be built by the electrical corporation at a time that would unreasonably delay the
construction or operation of the new industrial facility.
(3) (a) Within 15 days of the day on which a person files a statement of eligibility under this section,
a person may file a request for findings by the commission if that person believes that there is clear and
convincing evidence that:
(i) the person filing the statement of eligibility is not a customer of the electrical corporation on the
day on which the statement of eligibility is filed; or
(ii) one or more of the reasonable beliefs included in the statement of eligibility is not supportable.
(b) If a request for findings is filed in accordance with Subsection (3)(a), the commission shall:
(i) issue an order stating the commission's findings no later than 45 days from the day on which the
statement of eligibility is filed with the commission; and
(ii) find that the person is an eligible customer unless the commission finds that there is clear and
convincing evidence that:
(A) the person filing the statement of eligibility is not a customer of the electrical corporation on
the day on which the statement of eligibility is filed; or
(B) one or more of the reasonable beliefs included in the statement of eligibility is not supportable.
Section 5. Section 54-16-203 is enacted to read:
54-16-203. Infrastructure agreement -- Electric services contract.
(1) An infrastructure agreement required by Section 54-16-201 shall:
(a) specify the new industrial facility that requires new industrial electric infrastructure;
(b) specify the new industrial electric infrastructure that under the infrastructure agreement the
electrical corporation will provide the new industrial facility;
(c) subject to Subsection (2), state the amount the eligible customer shall pay the electrical
corporation for the portion of the new industrial electric infrastructure that is attributable to electric services
to be provided to the new industrial facility;
(d) subject to Subsection (3), state the time period during which the eligible customer is required
to pay the amount described in Subsection (1)(c); and
(e) be subject to approval by the commission in accordance with this title.
(2) The amount an eligible customer is required to pay under Subsection (1)(c) may not be less
than an amount calculated by:
(a) estimating as of the day on which the infrastructure agreement is executed the covered
expenses that the electrical corporation will incur for the new industrial electric infrastructure; and
(b) determining the portion of the covered expenses estimated under Subsection (2)(a) that are
properly the responsibility of the eligible customer under:
(i) applicable tariffs;
(ii) applicable rules of the commission; and
(iii) the standard practices of the electrical corporation on the day on which the infrastructure
agreement is executed.
(3) (a) The time period described in Subsection (1)(d) may not be longer than seven years from
the day on which the infrastructure agreement is executed.
(b) The time period described in Subsection (1)(d) may not affect the time period over which the
new industrial electric infrastructure is amortized.
(4) The contract for electric services required by Section 54-16-201 shall:
(a) require the eligible customer to purchase electric services:
(i) from the electrical corporation;
(ii) to be used by the eligible customer for operation of the new industrial facility; and
(iii) for a time period that may be shorter than the time period described in Subsection (1)(d); and
(b) provide the rates, terms, and conditions under which the eligible customer shall purchase the
electric services described in Subsection (4)(a) subject to approval by the commission in accordance with
this title.
Section 6. Section 54-16-301 is enacted to read:
54-16-301. Covered expenses to be recovered by customers in the state.
(1) In accordance with this section an electrical corporation shall recover the entire amount of a
covered expense:
(a) in rates, except to the extent that the covered expense is paid for by an eligible customer under
an infrastructure agreement;
(b) solely from the electrical corporation's customers located within the state; and
(c) in the manner determined by the commission in accordance with this title.
(2) Subsection (1) applies whether or not:
(a) the covered expense is specifically identified as being paid by the eligible customer;
(b) the eligible customer:
(i) purchases electric services from the electrical corporation after the day on which the
infrastructure agreement is executed;
(ii) operates the new industrial facility; or
(iii) continues to engage in business in this state;
(c) once a person becomes an eligible customer under Section 54-16-202 , the eligible customer
actually achieves one or more of the reasonable beliefs included in the eligible customer's statement of
eligibility filed under Section 54-16-202 ;
(d) the new industrial electric infrastructure includes transmission facilities;
(e) any portion of the new industrial electric infrastructure is used by a customer of the electrical
corporation other than an eligible customer; or
(f) the electric corporation takes any action to recover monies owed by an eligible customer under
an infrastructure agreement in the case of a breach of the infrastructure agreement.
(3) Notwithstanding the other provisions of this section, the commission may determine whether
for any purpose under this title an expense qualifies as a covered expense under Section 54-16-201 .
Section 7. Section 54-16-302 is enacted to read:
54-16-302. Accounting treatment of covered expenses.
(1) An electrical corporation that has entered into an infrastructure agreement shall maintain an
account for covered expenses:
(a) that permits the electrical corporation to account for a covered expense at the time the covered
expense is incurred;
(b) that includes a carrying charge on the unamortized balance of the account at a rate equal to the
electrical corporation's weighted average cost of capital as approved by the commission at the time the
covered expense is incurred; and
(c) to which the electrical corporation will credit any payments from an eligible customer received
by the electrical corporation under the infrastructure agreement.
(2) In the first general rate case of the electrical corporation that begins on or after a covered
expense is incurred, the commission shall provide for the recovery by the electrical corporation:
(a) of all amounts in the account described in Subsection (1), including accrued carrying charges;
and
(b) solely from the customers of the electrical corporation located in the state.
(3) (a) For purposes of this Subsection (3), "eligible customer's share that is in default" means the
portion of the amount in the account described in Subsection (1) that the commission finds is attributable
to the eligible customer failing to pay monies that:
(i) are owed by the eligible customer:
(A) under an infrastructure agreement; and
(B) at the time the general rate case described in Subsection (2) is filed; and
(ii) but for the eligible customer failing to pay the monies, would have been credited to the account
as provided in Subsection (1)(c).
(b) In the general rate case described in Subsection (2), the commission shall provide for the
apportionment of the eligible customer's share that is in default:
(i) to all customer classes; and
(ii) in a manner so that the rate impacts of the apportionment is reasonably equivalent for each of
the customer classes.