Link to Zipped WordPerfect Minutes 9K bytes

MINUTES OF THE SENATE BUSINESS & LABOR
STANDING COMMITTEE
WEDNESDAY, JANUARY 28, 2004, 8:00 A.M.
ROOM 403, STATE CAPITOL BUILDING


Members Present:    Sen. Parley G. Hellewell, Chair
        Sen. Curtis Bramble
        Sen. Dan Eastman
        Sen. Thomas V. Hatch         Sen. Ed Mayne
        Sen. Carlene M. Walker
        Sen. Michael Waddoups

Members Excused:    Sen. Gene Davis
    
Staff Present:    Mark Steinagel, Policy Analyst
        Karen Allred, Committee Secretary

A list of visitors and a copy of handouts are filed with the committee minutes.

Committee Chair Hellewell called the meeting to order at 8:10 a.m.

     MOTION: Sen. Walker moved to approve the revised minutes of January 26, 2004.

    The motion passed unanimously with Sens. Eastman, Hatch, Waddoups and Mayne absent     for the vote.
        
1.     H.B. 17 Captive Insurance Companies Act Amentments (J. Dunnigan)

    
Rep. Dunnigan explained the bill.
    
    Neal Gooch, Deputy Insurance Commissioner, answered questions about the bill.

     MOTION: Sen. Bramble moved to pass the bill out favorably.

    The motion passed unanimously.

2.    S.B. 129 Community Associations (M. Waddoups)

    Sen. Waddoups explained the bill.

     MOTION: Sen. Walker moved to pass the bill out favorably.

    The motion passed unanimously.



3. H.B. 20 Construction Bonding Statutes (M. Morely)

    
Rep. Morley explained the bill.

     MOTION: Sen. Hatch moved to pass the bill out favorably.

    The motion passed unanimously.

4.    H.B. 32 Lien Amendments (M. Morley)

    
Rep. Morely explained the bill and the following amendments were distributed:

1.    Page 2, Lines 35 through 50 :    

             35          (1) A person claiming benefits under this chapter shall file for record with the county
             36      recorder of the county in which the property, or some part of the property, is situated, a written
             37      notice to hold and claim a lien within 90 days from the date[: (a) the person last performed
             38      labor or service or last furnished equipment or material on a project or improvement for a
             39      residence as defined in Section 38-11-102 ; or (b)] of final completion of [an] the original
             40      contract [not involving a residence as defined in Section 38-11-102 ]
  under which the claimant claims a lien under this chapter       . For purposes of this

             41      Subsection (1), final completion of the original contract means:
             42          (a)
  if as a result of work performed under the original contract a permanent certificate of occupancy is required for such work,       the date of issuance of a permanent certificate of occupancy by the local

             43      government entity having jurisdiction over the construction project;
             44          (b) if no certificate of occupancy is required
[[   for the construction project   ]] by the local

             45      government entity having jurisdiction over the construction project,
  but as a result of the work performed under the original contract an inspection is required for such work,       the date of the final

             46      inspection
  for such work       by the local government entity having jurisdiction over the construction project; or




             47          (c) if
  with regard to work performed under the original contract       no certificate of occupancy      [[   is required   ]] and no final inspection      [[   is conducted   ]]        are required       by the

             48      local government entity having jurisdiction over the construction project, the date on which
             49      there remains no substantial work to be completed to finish
[[   the   ]]        such       work on the      [[   construction

             50      project.  
]]
  original contract      


2.    Page 3, Line 89 through Page 4, Line 94 :    

             89          (1) A lien claimant shall file an action to enforce the lien filed under this chapter
             90      within[: (a) 12 months] 180 days
[[   from the date of final completion of the original contract   ]]        from the day on which the lien claimant filed a notice of claim under Section 38-1-7       [not

             91      involving a residence as defined in Section 38-11-102 ; or (b) 180 days from the date the lien
             92      claimant last performed labor and services or last furnished equipment or material for a
             93      residence, as defined in Section 38-11-102 ].
[[   For purposes of this Subsection (1), final

             94      completion of the original contract is as defined in Subsection 38-1-7 (1).  
]]


3.    Page 5, Lines 137 through 140 :    

             137          (b) (i) For the purposes of this section, residential construction means:
             138          (A) single family detached housing; and
             139          (B) multifamily attached housing up to and including [fourplexes, and]
[[   duplexes, as

             140      defined in Section 38-11-102  
]]
  fourplexes       .

    

     MOTION: Sen. Bramble moved to adopt the amendments.

    The motion passed unanimously.

     MOTION: Sen. Walker moved to pass the bill out favorably as amended.

    The motion passed unanimously.





    MOTION: Sen. Eastman moved to adjourn.

    The motion passed unanimously.

    Chair Hellewell adjourned the meeting at 8:45 a.m.


    



         Sen. Parley G. Hellewell, Chair