H.B. 289

             1     

AUTHORITY FOR DESIGN-BUILD

             2     
CONSTRUCTION

             3     
2005 GENERAL SESSION

             4     
STATE OF UTAH

             5     
Sponsor: Michael T. Morley

             6     
             7      LONG TITLE
             8      General Description:
             9          This bill enacts a provision relating to the procurement of a design-build project.
             10      Highlighted Provisions:
             11          This bill:
             12          .    authorizes the state and certain counties and cities to enter into a design-build
             13      contract for certain capital improvement projects;
             14          .    establishes a process for prequalifying potential bidders on the design-build
             15      contract;
             16          .    establishes a process for issuing requests for proposals and awarding a design-build
             17      contract; and
             18          .    imposes requirements on the successful bidder under a design-build contract.
             19      Monies Appropriated in this Bill:
             20          None
             21      Other Special Clauses:
             22          None
             23      Utah Code Sections Affected:
             24      ENACTS:
             25          63-56-36.2, Utah Code Annotated 1953
             26     
             27      Be it enacted by the Legislature of the state of Utah:



             28          Section 1. Section 63-56-36.2 is enacted to read:
             29          63-56-36.2. Procurement of design-build project contracts.
             30          (1) As used in this section:
             31          (a) "Design-build project" means a capital improvement project that is unique and is
             32      excessively complex or has unusual limitations on completion schedules.
             33          (b) "Design-build project contract":
             34          (i) means the procurement of both the design and construction of a design-build project
             35      in a single contract with a company or combination of companies capable of providing the
             36      necessary engineering and construction services; and
             37          (ii) does not include a design-build transportation project contract, as defined in
             38      Section 63-56-36.1 .
             39          (c) "Procuring agency" means:
             40          (i) the state or a department or other agency of the state;
             41          (ii) a county of the first or second class, as defined in Section 17-50-501 ; or
             42          (iii) a city of the first class, as defined in Section 10-2-301 .
             43          (2) (a) A procuring agency may award a design-build project contract that has an
             44      estimated cost of $1,000,000 or more as provided in this section.
             45          (b) No other governmental or quasi-governmental state entity or political subdivision
             46      of the state may enter into a design-build project contract.
             47          (3) (a) (i) Each procuring agency intending to enter into a design-build project contract
             48      shall assess the qualifications of potential contractors by issuing a request for qualifications.
             49          (ii) Each procuring agency issuing a request for qualifications shall give public notice
             50      of the request in accordance with public contracting requirements.
             51          (b) (i) Before issuing a request for qualifications for a design-build project contract,
             52      each procuring agency intending to enter into a design-build project contract shall:
             53          (A) employ one or more persons experienced in and qualified to manage design-build
             54      projects;
             55          (B) establish a budget for the proposed design-build project; and
             56          (C) establish the criteria upon which the proposals for the design-build project will be
             57      evaluated, including:
             58          (I) price;



             59          (II) schedule for interim and final completion dates; and
             60          (III) architectural design.
             61          (ii) A budget established under Subsection (3)(b)(i)(B) is a protected record under
             62      Subsection 63-2-304 (6).
             63          (c) (i) Each request for qualifications under Subsection (3)(a) shall:
             64          (A) require each potential contractor to demonstrate its:
             65          (I) construction experience;
             66          (II) design experience;
             67          (III) management experience;
             68          (IV) financial, manpower, and equipment resources that are available for the project;
             69      and
             70          (V) experience with other design-build projects with attributes similar to the
             71      design-build project that is the subject of the design-build project contract that the procuring
             72      agency intends to enter into; and
             73          (B) state that the minimum number of potential contractors eligible to propose a bid for
             74      the design-build project contract is three.
             75          (ii) (A) With respect to the experience and resources required to be demonstrated as
             76      provided in Subsection (3)(c)(i)(A), each procuring agency shall establish the minimum
             77      requirements that are reasonably necessary to carry out the design-build project.
             78          (B) In establishing minimum requirements under Subsection (3)(c)(ii)(A), each
             79      procuring agency shall make every reasonable effort to foster competition, include as many
             80      potential contractors as possible, and provide opportunities for potential contractors to diversify
             81      into new types of construction projects.
             82          (d) (i) Each procuring agency shall:
             83          (A) evaluate each response received from the request for qualifications;
             84          (B) select from those submitting responses those qualified to submit proposals for the
             85      design-build project contract; and
             86          (C) invite those selected to submit proposals based on the procuring agency's request
             87      for proposals, as provided in Subsection (4).
             88          (ii) In applying the criteria used to evaluate the responses from a request for
             89      qualifications, the procuring agency:


             90          (A) shall:
             91          (I) consider price to be responsible for at least 50% of the evaluation score; and
             92          (II) consider the schedule for interim and final completion of the design-build project
             93      to be responsible for at least 20% of the evaluation score; and
             94          (B) may not base its selection of those qualified to submit proposals on anything other
             95      than the minimum requirements.
             96          (iii) If a procuring agency receives less than three responses from potential contractors
             97      that the procuring agency determines to be qualified to submit proposals, the procuring agency
             98      shall reissue a request for qualifications as provided in this Subsection (3).
             99          (4) (a) Each procuring agency that receives at least four qualified responses to a request
             100      for qualifications shall issue a request for proposals to the qualified respondents.
             101          (b) Each request for proposals shall:
             102          (i) include a detailed scope of work statement constituting an information for proposal
             103      that shall include:
             104          (A) preliminary design concepts;
             105          (B) design criteria, needs, and objectives;
             106          (C) square footage of the project and specific uses of the project;
             107          (D) type of construction and architectural style;
             108          (E) warranty and quality control requirements;
             109          (F) applicable construction and other standards;
             110          (G) environmental documents;
             111          (H) physical, financial, and other constraints;
             112          (I) time expectations or limitations;
             113          (J) contract incentives or disincentives;
             114          (K) insurance requirements including:
             115          (I) errors and omissions insurance;
             116          (II) liability insurance;
             117          (III) workers' compensation insurance; and
             118          (IV) bonding requirements, including bid bond, payment bond, and performance bond;
             119      and
             120          (L) other special consideration; and


             121          (ii) require each potential contractor submitting a proposal to provide:
             122          (A) a sealed price proposal that includes:
             123          (I) a cost-plus price, with a guaranteed maximum price, for the direct cost of
             124      construction; and
             125          (II) a fixed-price or percentage fee, as the request for proposal directs, for:
             126          (Aa) design cost;
             127          (Bb) management of the project, including job specific overhead;
             128          (Cc) overhead that is not job specific; and
             129          (Dd) profit;
             130          (B) a critical path matrix schedule, including cash flow, manpower, and equipment
             131      requirements;
             132          (C) proposal or bid security; and
             133          (D) other items required by the procuring agency for the design-build project.
             134          (c) A request for proposals may include an award of a stipulated fee to be paid to
             135      potential contractors that submit unsuccessful proposals.
             136          (5) Each procuring agency that receives proposals on a design-build project shall:
             137          (a) open the proposals as provided in Subsection 63-56-20 (4);
             138          (b) evaluate the proposals received in response to the request for proposals from those
             139      qualified to submit proposals;
             140          (c) establish and comply with rules relating to discussion of proposals, best and final
             141      offers, and evaluations of the proposals submitted; and
             142          (d) after considering price and other identified factors, award the design-build project
             143      contract to the responsible bidder whose proposal is most advantageous to the state and its
             144      political subdivisions.
             145          (6) Each successful bidder:
             146          (a) shall:
             147          (i) be subject to and responsible for the enforcement of all of the provisions of this
             148      chapter for the procurement of construction; and
             149          (ii) let subcontracts and supply contracts for portions of the design-build project in
             150      accordance with the public procurement procedure in Section 63-56-20 ; and
             151          (b) may not perform any portion of the work itself unless:


             152          (i) the successful bidder advertises and lets such work out to bid to other
             153      subcontractors as provided in Section 63-56-20 ;
             154          (ii) the successful bidder submits its own bid for the work, prior to the bid opening,
             155      which is priced as if the bid were to be submitted to another contractor in an arms length
             156      transaction; and
             157          (iii) the successful bidder is the successful bidder for that portion of the work.




Legislative Review Note
    as of 2-3-05 11:21 AM


Based on a limited legal review, this legislation has not been determined to have a high
probability of being held unconstitutional.

Office of Legislative Research and General Counsel


[Bill Documents][Bills Directory]