             1     

FILING LIENS

             2     
2006 GENERAL SESSION

             3     
STATE OF UTAH

             4     
Chief Sponsor: Stephen D. Clark

             5     
Senate Sponsor: Scott K. Jenkins

             6     
             7      LONG TITLE
             8      General Description:
             9          This bill modifies a provision related to filing a lien.
             10      Highlighted Provisions:
             11          This bill:
             12          .    provides that mechanics' liens be filed within 90 days after the date of final
             13      completion of the original contract;
             14          .    clarifies a cross reference; and
             15          .    makes technical changes.
             16      Monies Appropriated in this Bill:
             17          None
             18      Other Special Clauses:
             19          None
             20      Utah Code Sections Affected:
             21      AMENDS:
             22          38-1-7, as last amended by Chapter 64, Laws of Utah 2005
             23          38-11-107, as last amended by Chapter 42, Laws of Utah 2004
             24     
             25      Be it enacted by the Legislature of the state of Utah:
             26          Section 1. Section 38-1-7 is amended to read:
             27           38-1-7. Notice of claim -- Contents -- Recording -- Service on owner of property.
             28          (1) (a) Except as modified in Section 38-1-27 , a person claiming benefits under this
             29      chapter shall file for record with the county recorder of the county in which the property, or


             30      some part of the property, is situated, a written notice to hold and claim a lien within 90 days
             31      [from] after the date of final completion of the original contract under which the claimant
             32      claims a lien under this chapter.
             33          (b) For purposes of this Subsection (1), final completion of the original contract means:
             34          (i) if as a result of work performed under the original contract a permanent certificate
             35      of occupancy is required for such work, the date of issuance of a permanent certificate of
             36      occupancy by the local government entity having jurisdiction over the construction project;
             37          (ii) if no certificate of occupancy is required by the local government entity having
             38      jurisdiction over the construction project, but as a result of the work performed under the
             39      original contract an inspection is required for such work, the date of the final inspection for
             40      such work by the local government entity having jurisdiction over the construction project; or
             41          (iii) if with regard to work performed under the original contract no certificate of
             42      occupancy and no final inspection are required by the local government entity having
             43      jurisdiction over the construction project, the date on which there remains no substantial work
             44      to be completed to finish such work on the original contract.
             45          [(b)] (c) Notwithstanding Section 38-1-2 , where a subcontractor performs substantial
             46      work after the applicable dates established by Subsections (1)[(a)](b)(i) and (ii), that
             47      subcontractor's subcontract shall be considered an original contract for the sole purpose of
             48      determining:
             49          (i) the subcontractor's time frame to file a notice of intent to hold and claim a lien
             50      under this Subsection (1); and
             51          (ii) the original contractor's time frame to file a notice of intent to hold and claim a lien
             52      under this Subsection (1) for that subcontractor's work.
             53          [(c)] (d) For purposes of this section, the term "substantial work" does not include:
             54          (i) repair work; or
             55          (ii) warranty work.
             56          [(d)] (e) Notwithstanding Subsection (1)[(a)](b)(iii), final completion of the original
             57      contract does not occur if work remains to be completed for which the owner is holding


             58      payment to ensure completion of that work.
             59          (2) (a) The notice required by Subsection (1) shall contain a statement setting forth:
             60          (i) the name of the reputed owner if known or, if not known, the name of the record
             61      owner;
             62          (ii) the name of the person:
             63          (A) by whom the lien claimant was employed; or
             64          (B) to whom the lien claimant furnished the equipment or material;
             65          (iii) the time when:
             66          (A) the first and last labor or service was performed; or
             67          (B) the first and last equipment or material was furnished;
             68          (iv) a description of the property, sufficient for identification;
             69          (v) the name, current address, and current phone number of the lien claimant;
             70          (vi) the amount of the lien claim;
             71          (vii) the signature of the lien claimant or the lien claimant's authorized agent;
             72          (viii) an acknowledgment or certificate as required under Title 57, Chapter 3,
             73      Recording of Documents; and
             74          (ix) if the lien is on an owner-occupied residence, as defined in Section 38-11-102 , a
             75      statement describing what steps an owner, as defined in Section 38-11-102 , may take to require
             76      a lien claimant to remove the lien in accordance with Section 38-11-107 .
             77          (b) Substantial compliance with the requirements of this Subsection (2) is sufficient to
             78      hold and claim a lien.
             79          (3) (a) Within 30 days after filing the notice of lien, the lien claimant shall deliver or
             80      mail by certified mail a copy of the notice of lien to:
             81          (i) the reputed owner of the real property; or
             82          (ii) the record owner of the real property.
             83          (b) If the record owner's current address is not readily available to the lien claimant, the
             84      copy of the claim may be mailed to the last-known address of the record owner, using the
             85      names and addresses appearing on the last completed real property assessment rolls of the


             86      county where the affected property is located.
             87          (c) Failure to deliver or mail the notice of lien to the reputed owner or record owner
             88      precludes the lien claimant from an award of costs and attorneys' fees against the reputed
             89      owner or record owner in an action to enforce the lien.
             90          (4) The Division of Occupational and Professional Licensing shall make rules
             91      governing the form of the statement required under Subsection (2)(a)(ix).
             92          Section 2. Section 38-11-107 is amended to read:
             93           38-11-107. Restrictions upon maintaining a lien against residence or owner's
             94      interest in the residence.
             95          (1) A person qualified to file a lien upon an owner-occupied residence and the real
             96      property associated with that residence under the provisions of Title 38, Chapter 1, Mechanics'
             97      Liens, who provides qualified services under an agreement effective on or after January 1,
             98      1995, other than directly with the owner, shall be barred after January 1, 1995, from
             99      maintaining a lien upon that residence and real property or recovering a judgment in any civil
             100      action against the owner or the owner-occupied residence to recover monies owed for qualified
             101      services provided by that person if:
             102          (a) an owner meets the conditions described in Subsections 38-11-204 (4)(a) and (4)(b);
             103      or
             104          (b) (i) a subsequent owner purchases a residence from an owner;
             105          (ii) the subsequent owner who purchased the residence under Subsection (1)(b)(i)
             106      occupies the residence as a primary or secondary residence within 180 days from the date of
             107      transfer or the residence is occupied by the subsequent owner's tenant or lessee as a primary or
             108      secondary residence within 180 days from the date of transfer; and
             109          (iii) the owner from whom the subsequent owner purchased the residence met the
             110      conditions described in Subsections 38-11-204 (4)(a) and (4)(b).
             111          (2) If a residence is constructed under conditions that do not meet all of the provisions
             112      of Subsection (1), that residence and the real property associated with that residence as
             113      [defined] provided in Section 38-1-4 , shall be subject to any mechanics' lien as provided in


             114      Section 38-1-3 .
             115          (3) A lien claimant who files a mechanics' lien or foreclosure action upon an
             116      owner-occupied residence is not liable for costs and attorneys' fees under Sections 38-1-17 and
             117      38-1-18 or for any damages arising from a civil action related to the lien filing or foreclosure
             118      action if the lien claimant removes the lien within 15 days from the date the owner obtains a
             119      certificate of compliance and mails a copy of the certificate of compliance by certified mail to
             120      the lien claimant at the address provided for by Subsection 38-1-7 (2)[(e)](a)(v). The 15-day