LAKE POWELL PIPELINE DEVELOPMENT

             2     
ACT

             3     
2006 GENERAL SESSION

             4     
STATE OF UTAH

             5     
Chief Sponsor: Thomas V. Hatch

             6     
House Sponsor: David Clark

             7     
             8      LONG TITLE
             9      General Description:
             10          This bill authorizes the Board of Water Resources to build the Lake Powell Pipeline
             11      project.
             12      Highlighted Provisions:
             13          This bill:
             14          .    enacts the Lake Powell Pipeline Development Act;
             15          .    defines terms;
             16          .    authorizes the Board of Water Resources to:
             17              .    make rules;
             18              .    build the Lake Powell Pipeline project; and
             19              .    contract for the sale of developed water and operation of the project;
             20          .    creates the Project Management Committee;
             21          .    authorizes the building of hydroelectric generating works;
             22          .    authorizes the water districts to use, exchange, or sell developed water; and
             23          .    establishes an enterprise fund for the operation and maintenance of the project.
             24      Monies Appropriated in this Bill:
             25          None
             26      Other Special Clauses:
             27          None



             28      Utah Code Sections Affected:
             29      ENACTS:
             30          73-28-101, Utah Code Annotated 1953
             31          73-28-102, Utah Code Annotated 1953
             32          73-28-103, Utah Code Annotated 1953
             33          73-28-104, Utah Code Annotated 1953
             34          73-28-105, Utah Code Annotated 1953
             35          73-28-201, Utah Code Annotated 1953
             36          73-28-202, Utah Code Annotated 1953
             37          73-28-203, Utah Code Annotated 1953
             38          73-28-301, Utah Code Annotated 1953
             39          73-28-302, Utah Code Annotated 1953
             40          73-28-401, Utah Code Annotated 1953
             41          73-28-402, Utah Code Annotated 1953
             42          73-28-403, Utah Code Annotated 1953
             43          73-28-404, Utah Code Annotated 1953
             44          73-28-405, Utah Code Annotated 1953
             45     
             46      Be it enacted by the Legislature of the state of Utah:
             47          Section 1. Section 73-28-101 is enacted to read:
             48     
CHAPTER 28. LAKE POWELL PIPELINE DEVELOPMENT ACT

             49     
Part 1. General Provisions

             50          73-28-101. Title.
             51          This chapter is known as the "Lake Powell Pipeline Development Act."
             52          Section 2. Section 73-28-102 is enacted to read:
             53          73-28-102. Scope.
             54          Nothing in this chapter may be construed to prevent any person, subject to other
             55      provisions of law, from developing the waters of the Colorado River.
             56          Section 3. Section 73-28-103 is enacted to read:
             57          73-28-103. Definitions.
             58          As used in this chapter:



             59          (1) "Board" means the Board of Water Resources.
             60          (2) "Committee" means the Project Management Committee created in Section
             61      73-28-105 .
             62          (3) (a) "Construction costs" means all costs related to the construction of the project,
             63      including the environmental mitigation costs.
             64          (b) Construction costs include:
             65          (i) acquisition of land and rights-of-way;
             66          (ii) board and division expenses related to the project;
             67          (iii) compensation for impairment of existing water rights;
             68          (iv) construction of the project;
             69          (v) design;
             70          (vi) engineering;
             71          (vii) environmental studies;
             72          (viii) legal work;
             73          (ix) permitting;
             74          (x) planning; and
             75          (xi) rebuilding and relocating highways or other facilities affected by the project.
             76          (4) "Developed waters" means surface water developed by the project.
             77          (5) "District" means:
             78          (a) the Central Iron County Water Conservancy District;
             79          (b) the Kane County Water Conservancy District;
             80          (c) the Washington County Water Conservancy District; or
             81          (d) any combination of those districts listed in Subsections (5)(a) through (c).
             82          (6) "Division" means the Division of Water Resources.
             83          (7) "Environmental mitigation costs" means costs associated with obtaining permits
             84      required by federal, state, or local governmental agencies.
             85          (8) "Preconstruction costs" means any of the following costs incurred before project
             86      construction begins:
             87          (a) planning;
             88          (b) design;
             89          (c) engineering studies;


             90          (d) legal work;
             91          (e) permitting;
             92          (f) acquisition of land and rights-of-way;
             93          (g) compensation for impairment of existing water rights;
             94          (h) environmental studies; or
             95          (i) any combination of Subsections (8)(a) through (h).
             96          (9) (a) "Project" means the Lake Powell Pipeline project and associated facilities,
             97      including:
             98          (i) facilities associated with environmental mitigation;
             99          (ii) hydroelectric generating works and incidental electrical facilities;
             100          (iii) pipelines; and
             101          (iv) pumping stations.
             102          (b) Notwithstanding Subsection (9)(a), associated facilities does not include the local
             103      facilities necessary for the treatment and local delivery of the developed water.
             104          (10) "Project costs" include preconstruction costs, construction costs, and project
             105      operation, maintenance, repair, and replacement costs.
             106          Section 4. Section 73-28-104 is enacted to read:
             107          73-28-104. Powers of the board.
             108          (1) The board may contract with:
             109          (a) a district for the sale of developed water;
             110          (b) a qualified entity for the development or construction of the project; or
             111          (c) a district or other qualified entity for the operation, maintenance, repair, or
             112      replacement of the project.
             113          (2) By following the procedures and requirements of Title 63, Chapter 46a, Utah
             114      Administrative Rulemaking Act, the board may make rules to:
             115          (a) establish prices, in consultation with the committee and in accordance with Section
             116      73-28-403 , for:
             117          (i) developed water sold to the districts; and
             118          (ii) electricity made available by the project;
             119          (b) establish procedures for reviewing offers to contract for the sale of developed water
             120      and electricity;


             121          (c) establish the interest rate for repayment of preconstruction and construction costs;
             122          (d) establish a reasonable time period for the districts to offer to purchase water; and
             123          (e) administer and operate the project.
             124          (3) The board may exercise eminent domain, as provided in Title 78, Chapter 34,
             125      Eminent Domain, to construct the project.
             126          Section 5. Section 73-28-105 is enacted to read:
             127          73-28-105. Project Management Committee created.
             128          (1) There is created a Project Management Committee within the division.
             129          (2) (a) The committee shall be comprised of one representative appointed by:
             130          (i) the division director;
             131          (ii) the board; and
             132          (iii) each of the participating districts.
             133          (b) The division representative is the chair of the committee.
             134          (3) (a) The members shall serve a four-year term.
             135          (b) When a vacancy occurs in the membership for any reason, the replacement shall be
             136      appointed for the unexpired term in the same manner as the vacated member was appointed.
             137          (4) (a) A majority of the members of the committee constitute a quorum of the
             138      committee.
             139          (b) The action of a majority of a quorum constitutes the action of the committee.
             140          (5) The committee shall:
             141          (a) consult with the board on a regular basis concerning:
             142          (i) the development and construction of the project;
             143          (ii) the operation, maintenance, repair, and replacement of the project; and
             144          (iii) the prices of developed water and electricity; and
             145          (b) approve all expenditures from the fund created in Section 73-28-404 .
             146          Section 6. Section 73-28-201 is enacted to read:
             147     
Part 2. Board of Water Resources to Construct the Lake Powell Pipeline

             148          73-28-201. Lake Powell Pipeline Project.
             149          (1) The board shall:
             150          (a) construct the project as funded by the Legislature;
             151          (b) own, operate, and maintain the project until the title is transferred under Section


             152      73-28-405 ; and
             153          (c) consult with the committee on a regular basis concerning the development,
             154      construction, operation, maintenance, repair and replacement of the project.
             155          (2) (a) The board may contract with the state of Arizona to participate in the project to
             156      develop its water rights.
             157          (b) The board shall ensure that the contract requires the state of Arizona to pay for all
             158      project costs represented by its share of the project.
             159          Section 7. Section 73-28-202 is enacted to read:
             160          73-28-202. Construction contingent upon sale of water.
             161          (1) Except as provided in Subsection (3), the board may not expend monies for
             162      construction costs for the project until:
             163          (a) the board has contracted with the districts for the sale of 70% or more of the
             164      developed water; and
             165          (b) all permits required by the environmental impact statement have been obtained.
             166          (2) Construction of the project and implementation of any environmental mitigation
             167      requirements may proceed concurrently.
             168          (3) The board may make expenditures for preconstruction costs if monies are expressly
             169      appropriated or earmarked by statute for that purpose by the Legislature.
             170          Section 8. Section 73-28-203 is enacted to read:
             171          73-28-203. Development of hydroelectric generating works -- Electricity offered to
             172      public utilities or municipalities.
             173          (1) The board may construct and own hydroelectric generating works and incidental
             174      electrical facilities in association with the project.
             175          (2) (a) Except for electricity needed for project operations, the board shall first offer to
             176      sell electricity derived from any hydroelectric generating works owned by it to public utilities
             177      or municipalities providing electricity to consumers in Utah.
             178          (b) The board, in consultation with the committee and in accordance with Section
             179      73-28-403 , shall establish the prices at which the electricity is sold.
             180          (3) In accordance with Section 51-4-1 , the board shall deposit:
             181          (a) revenues received from the sale of electricity designated for the repayment of
             182      preconstruction and construction costs and interest into the Water Resources Conservation and


             183      Development Fund;
             184          (b) revenues received from the sale of electricity designated for project operation,
             185      maintenance, repair, and replacement costs into the Lake Powell Pipeline Project Operation
             186      and Maintenance Fund; and
             187          (c) any additional revenues received from the sale of electricity into the Water
             188      Resources Conservation and Development Fund.
             189          Section 9. Section 73-28-301 is enacted to read:
             190     
Part 3. Allocation of Developed Waters

             191          73-28-301. Entities eligible to receive developed water.
             192          (1) Except for developed water reserved for wildlife or public recreation, the board
             193      shall make the developed water available by contract exclusively to the districts listed in
             194      Subsection 73-28-103 (5).
             195          (2) A district that purchases developed water may:
             196          (a) use the water directly;
             197          (b) exchange the water by following the procedures and requirements of Section
             198      73-3-20 ; or
             199          (c) sell the water to any entity or person.
             200          (3) Districts purchasing developed water shall build any facilities necessary for the
             201      treatment and local delivery of the developed water.
             202          Section 10. Section 73-28-302 is enacted to read:
             203          73-28-302. Limits on amount of water available to any entity or area -- Exception.
             204          (1) Except as provided in Subsection (2), the total amount of developed water that the
             205      board may make available to any district is limited as follows:
             206          (a) The Kane Water Conservancy District may purchase no more than 10,000 acre-feet
             207      of developed water per calendar year.
             208          (b) The Washington County Water Conservancy District may purchase no more than
             209      69,000 acre-feet of developed water per calendar year.
             210          (c) The Central Iron County Water Conservancy District may purchase no more than
             211      the amount of Colorado River water it acquires.
             212          (2) (a) A district may purchase developed water in excess of the limits specified in
             213      Subsection (1) for that calendar year if:


             214          (i) developed water is available; and
             215          (ii) no other district eligible to receive the developed water has offered to purchase it.
             216          (b) The board may expand the size of the project and exceed the limits in Subsection
             217      (1) if the board or a district acquires additional water rights.
             218          (3) Before beginning the final design of the project, the board shall make rules
             219      establishing a reasonable time during which the districts may offer to purchase developed
             220      water.
             221          (4) If Central Iron County Water Conservancy District acquires water rights and
             222      participates in the project, the board shall ensure that:
             223          (a) the project is sized and constructed to transport the Central Iron County Water
             224      Conservancy District's water from Lake Powell; and
             225          (b) facilities from Washington County to Cedar City are included in the project.
             226          Section 11. Section 73-28-401 is enacted to read:
             227     
Part 4. Financing and Cost Recovery

             228          73-28-401. Analysis of benefits and costs -- Allocation of costs.
             229          (1) The board shall allocate project costs based on the economic costs and benefits of
             230      the developed water and electricity among the following water uses:
             231          (a) municipal and industrial;
             232          (b) electricity;
             233          (c) public recreation; and
             234          (d) fish and wildlife.
             235          (2) The state shall pay the nonreimbursable project costs allocated to recreation and
             236      fish and wildlife.
             237          Section 12. Section 73-28-402 is enacted to read:
             238          73-28-402. Agreement for delivery -- Period for repayment of costs.
             239          (1) The board and each district shall establish by contract the timing and amount of
             240      developed water to be delivered to the district.
             241          (2) If a contract was made before the project's completion, the district shall repay the
             242      preconstruction and construction costs within 50 years from the date of:
             243          (a) the delivery of developed water to the district during the first ten years after the
             244      project is completed; or


             245          (b) the project's completion for any developed water delivered to the district after the
             246      tenth anniversary date of the project's completion.
             247          (3) If a contract was made after the project's completion date, the district shall repay
             248      the preconstruction and construction costs within a period not to exceed 50 years from the date
             249      that the contract was made.
             250          (4) The board shall establish and charge a reasonable interest rate for the unpaid
             251      balance of reimbursable preconstruction and construction costs.
             252          Section 13. Section 73-28-403 is enacted to read:
             253          73-28-403. Water and electricity charges.
             254          The board, in consultation with the committee, shall establish prices for the developed
             255      water sold to the districts and electricity sufficient to:
             256          (1) recover the reimbursable preconstruction costs, construction costs, and interest on
             257      those costs within the time period specified in Section 73-28-402 ;
             258          (2) pay for operation and maintenance costs;
             259          (3) accumulate an adequate reserve for repair and replacement; and
             260          (4) allocate the proportionate cost of the project facilities required to deliver the
             261      developed water to each district.
             262          Section 14. Section 73-28-404 is enacted to read:
             263          73-28-404. Repayments returned to Water Resources Conservation and
             264      Development Fund -- Establishment of an enterprise fund.
             265          (1) The board shall deposit, in accordance with Section 51-4-1 , into the Water
             266      Resources Conservation and Development Fund:
             267          (a) repayments of preconstruction and construction costs; and
             268          (b) the interest charged.
             269          (2) (a) There is created an enterprise fund, as defined in Subsection 51-5-4 (8), entitled
             270      the "Lake Powell Pipeline Project Operation and Maintenance Fund."
             271          (b) The fund consists of:
             272          (i) revenues received from the sale of developed water that is designated for project
             273      operation, maintenance, repair, and replacement costs;
             274          (ii) revenues received from the sale of electricity that are deposited in the fund in
             275      accordance with Subsection 73-28-203 (3); and


             276          (iii) all interest earned by the fund.
             277          (3) (a) Any unexpended monies remaining in the fund at the end of the fiscal year are
             278      nonlapsing.
             279          (b) Notwithstanding Section 63-38-3.6 , the Legislature may not appropriate any monies
             280      from the Lake Powell Pipeline Project Operation and Maintenance Fund.
             281          (4) The state treasurer shall:
             282          (a) invest the monies in the enterprise fund by following the procedures and
             283      requirements of Title 51, Chapter 7, State Money Management Act; and
             284          (b) deposit all interest or other earnings derived from those investments into the Lake
             285      Powell Pipeline Operation and Maintenance Fund.
             286          (5) The committee shall approve the expenditure of fund monies to cover the project
             287      operation, maintenance, repair and replacement costs, subject to:
             288          (a) monies available in the fund; and
             289          (b) rules established by the board under Subsection 73-28-104 (2)(d).
             290          (6) If title to the project is transferred under Section 73-28-405 , the agreement shall
             291      direct the disposition of the monies remaining in the fund.
             292          Section 15. Section 73-28-405 is enacted to read:
             293          73-28-405. Transfer of title to project and water rights to districts.
             294          (1) The board shall convey the project's title and its associated water rights to the
             295      districts if:
             296          (a) the state has been fully compensated for all of its reimbursable costs;
             297          (b) the board finds that the conveyance of the project's title would be in the best interest
             298      of the state, the districts, and those receiving developed water; and
             299          (c) the districts enter into an agreement with each other and the board that would
             300      ensure the continued operation, maintenance, repair, and replacement of the project.
             301          (2) The board shall convey the project's title and its associated water rights to the
             302      districts in proportion to the amount each district paid for the developed water it received.





Legislative Review Note
    as of 11-28-05 6:46 AM


Based on a limited legal review, this legislation has not been determined to have a high
probability of being held unconstitutional.

Office of Legislative Research and General Counsel


Interim Committee Note
    as of 12-20-05 1:54 PM


The Natural Resources, Agriculture, and Environment Interim Committee recommended this
bill.


[Bill Documents][Bills Directory]