Download Zipped Enrolled WordPerfect HB0057.ZIP
[Introduced][Status][Bill Documents][Fiscal Note] [Bills Directory]

H.B. 57 Enrolled

             1     

EXTENSION OF SUNSET FOR

             2     
DESIGN-BUILD CONTRACT AWARD

             3     
AUTHORIZATION

             4     
2010 GENERAL SESSION

             5     
STATE OF UTAH

             6     
Chief Sponsor: Julie Fisher

             7     
Senate Sponsor: Kevin T. Van Tassell

             8     
             9      LONG TITLE
             10      General Description:
             11          This bill amends provisions relating to the procurement of design-build transportation
             12      project contracts.
             13      Highlighted Provisions:
             14          This bill:
             15          .    extends until July 1, 2015, the sunset of the provision authorizing a transportation
             16      agency to award a design-build contract for a transportation project that has an
             17      estimated cost of $5,000,000 or less to a qualified eligible proposer if:
             18              .    only a single proposal is received; and
             19              .    the transportation agency determines that the proposal is advantageous to the
             20      state and the proposal price is reasonable; and
             21          .    makes technical changes.
             22      Monies Appropriated in this Bill:
             23          None
             24      Other Special Clauses:
             25          None
             26      Utah Code Sections Affected:
             27      AMENDS:
             28          63G-6-502, as renumbered and amended by Laws of Utah 2008, Chapter 382
             29          63I-1-263, as last amended by Laws of Utah 2009, Chapters 334 and 356


             30     
             31      Be it enacted by the Legislature of the state of Utah:
             32          Section 1. Section 63G-6-502 is amended to read:
             33           63G-6-502. Procurement of design-build transportation project contracts.
             34          (1) As used in this section:
             35          (a) "Design-build transportation project contract" means the procurement of both the
             36      design and construction of a transportation project in a single contract with a company or
             37      combination of companies capable of providing the necessary engineering services and
             38      construction.
             39          (b) "Transportation agency" means:
             40          (i) the Department of Transportation;
             41          (ii) a county of the first or second class, as defined in Section 17-50-501 ;
             42          (iii) a municipality of the first class, as defined in Section 10-2-301 ;
             43          (iv) a public transit district that has more than 200,000 people residing within its
             44      boundaries; and
             45          (v) a public airport authority.
             46          (2) Except as provided in Subsection (3), a transportation agency may award a
             47      design-build transportation project contract for any transportation project that has an estimated
             48      cost of at least $50,000,000 by following the requirements of this section.
             49          (3) (a) The Department of Transportation:
             50          (i) may award a design-build transportation project contract for any transportation
             51      project by following the requirements of this section; and
             52          (ii) shall make rules, by following the procedures and requirements of Title 63G,
             53      Chapter 3, Utah Administrative Rulemaking Act, establishing requirements for the
             54      procurement of its design-build transportation project contracts in addition to those required
             55      by this section.
             56          (b) A public transit district that has more than 200,000 people residing within its
             57      boundaries:


             58          (i) may award a design-build transportation project contract for any transportation
             59      project by following the requirements of this section; and
             60          (ii) shall pass ordinances or a resolution establishing requirements for the procurement
             61      of its design-build transportation project contracts in addition to those required by this section.
             62          (c) A design-build transportation project contract authorized under this Subsection (3)
             63      is not subject to the estimated cost threshold under Subsection (2).
             64          (4) (a) Before entering a design-build transportation project contract, a transportation
             65      agency may issue a request for qualifications to prequalify potential contractors.
             66          (b) Public notice of the request for qualifications shall be given in accordance with
             67      policy board rules.
             68          (c) A transportation agency shall require, as part of the qualifications specified in the
             69      request for qualifications, that potential contractors at least demonstrate their:
             70          (i) construction experience;
             71          (ii) design experience;
             72          (iii) financial, manpower, and equipment resources available for the project; and
             73          (iv) experience in other design-build transportation projects with attributes similar to
             74      the project being procured.
             75          (d) The request for qualifications shall identify the number of eligible competing
             76      proposers that the transportation agency will select to submit a proposal, which must be at
             77      least two.
             78          (5) (a) The transportation agency shall:
             79          (i) evaluate the responses received from the request for qualifications;
             80          (ii) select from their number those qualified to submit proposals; and
             81          (iii) invite those respondents to submit proposals based upon the transportation
             82      agency's request for proposals.
             83          (b) (i) Except as provided in Subsection (5)(b)(ii), if the transportation agency fails to
             84      receive at least two qualified eligible competing proposers, the transportation agency shall
             85      readvertise the project.


             86          (ii) [Until July 1, 2010, a] A transportation agency may award a contract for a
             87      transportation project that has an estimated cost of $5,000,000 or less to a qualified eligible
             88      proposer if:
             89          (A) only a single proposal is received; and
             90          (B) the transportation agency determines that:
             91          (I) the proposal is advantageous to the state; and
             92          (II) the proposal price is reasonable.
             93          [(iii) The Transportation Interim Committee and Government Operations Interim
             94      Committee of the Legislature shall review Subsection (5)(b)(ii) prior to November 30, 2009.]
             95          (6) The transportation agency shall issue a request for proposals to those qualified
             96      respondents that:
             97          (a) includes a scope of work statement constituting an information for proposal that
             98      may include:
             99          (i) preliminary design concepts;
             100          (ii) design criteria, needs, and objectives;
             101          (iii) warranty and quality control requirements;
             102          (iv) applicable standards;
             103          (v) environmental documents;
             104          (vi) constraints;
             105          (vii) time expectations or limitations;
             106          (viii) incentives or disincentives; and
             107          (ix) other special considerations;
             108          (b) requires submitters to provide:
             109          (i) a sealed cost proposal;
             110          (ii) a critical path matrix schedule, including cash flow requirements;
             111          (iii) proposal security; and
             112          (iv) other items required by the department for the project; and
             113          (c) may include award of a stipulated fee to be paid to submitters who submit


             114      unsuccessful proposals.
             115          (7) The transportation agency shall:
             116          (a) evaluate the submissions received in response to the request for proposals from the
             117      prequalified proposers;
             118          (b) comply with rules relating to discussion of proposals, best and final offers, and
             119      evaluations of the proposals submitted; and
             120          (c) after considering price and other identified factors, award the contract to the
             121      responsible proposer whose proposal is most advantageous to the state.
             122          Section 2. Section 63I-1-263 is amended to read:
             123           63I-1-263. Repeal dates, Titles 63 to 63M.
             124          (1) Section 63A-4-204 , authorizing the Risk Management Fund to provide coverage to
             125      any public school district which chooses to participate, is repealed July 1, 2016.
             126          (2) Section 63A-5-603 , State Facility Energy Efficiency Fund, is repealed July 1,
             127      2016.
             128          (3) Section 63C-8-106 , Rural residency training program, is repealed July 1, 2015.
             129          (4) Subsection 63G-6-502 (5)(b)(ii) authorizing certain transportation agencies to
             130      award a contract for a design-build transportation project in certain circumstances, is repealed
             131      July 1, 2015.
             132          [(4)] (5) The Resource Development Coordinating Committee, created in Section
             133      63J-4-501 , is repealed July 1, 2015.
             134          [(5)] (6) Title 63M, Chapter 1, Part 4, Enterprise Zone Act, is repealed July 1, 2018.
             135          [(6)] (7) (a) Title 63M, Chapter 1, Part 11, Recycling Market Development Zone Act,
             136      is repealed July 1, 2010.
             137          (b) Sections 59-7-610 and 59-10-1007 regarding tax credits for certain persons in
             138      recycling market development zones, are repealed for taxable years beginning on or after
             139      January 1, 2011.
             140          (c) Notwithstanding Subsection [(6)] (7)(b), a person may not claim a tax credit under
             141      Section 59-7-610 or 59-10-1007 :


             142          (i) for the purchase price of machinery or equipment described in Section 59-7-610 or
             143      59-10-1007 , if the machinery or equipment is purchased on or after July 1, 2010; or
             144          (ii) for an expenditure described in Subsection 59-7-610 (1)(b) or 59-10-1007 (1)(b), if
             145      the expenditure is made on or after July 1, 2010.
             146          (d) Notwithstanding Subsections [(6)] (7)(b) and (c), a person may carry forward a tax
             147      credit in accordance with Section 59-7-610 or 59-10-1007 if:
             148          (i) the person is entitled to a tax credit under Section 59-7-610 or 59-10-1007 ; and
             149          (ii) (A) for the purchase price of machinery or equipment described in Section
             150      59-7-610 or 59-10-1007 , the machinery or equipment is purchased on or before June 30,
             151      2010; or
             152          (B) for an expenditure described in Subsection 59-7-610 (1)(b) or 59-10-1007 (1)(b),
             153      the expenditure is made on or before June 30, 2010.
             154          [(7)] (8) Title 63M, Chapter 7, Part 4, Sentencing Commission, is repealed January 1,
             155      2012.
             156          [(8)] (9) The Crime Victim Reparations Board, created in Section 63M-7-504 , is
             157      repealed July 1, 2017.
             158          [(9)] (10) Title 63M, Chapter 8, Utah Commission for Women and Families Act, is
             159      repealed July 1, 2011.
             160          [(10)] (11) Title 63M, Chapter 9, Families, Agencies, and Communities Together for
             161      Children and Youth At Risk Act, is repealed July 1, 2016.
             162          [(11)] (12) Title 63M, Chapter 11, Utah Commission on Aging, is repealed July 1,
             163      2012.


[Bill Documents][Bills Directory]