9 General Description:
10 This bill modifies provisions relating to the state construction registry.
11 Highlighted Provisions:
12 This bill:
13 . modifies provisions relating to the filing of a notice of construction with respect to
14 the state construction registry.
15 Monies Appropriated in this Bill:
16 None
17 Other Special Clauses:
18 None
19 Utah Code Sections Affected:
20 AMENDS:
21 38-1-31, as last amended by Laws of Utah 2009, Chapter 50
22
23 Be it enacted by the Legislature of the state of Utah:
24 Section 1. Section 38-1-31 is amended to read:
25 38-1-31. Building permit -- Construction -- Notice registry -- Notice of
26 commencement of work.
27 (1) (a) (i) [
28 original contractor or owner-builder, no later than 15 days after the issuance of the building
29 permit:
30 [
31 building permit application and transmit the building permit information to the database
32 electronically by way of the Internet or computer modem or by any other means; [
33 [
34 commencement with the database [
35
36 by the local government entity.
37 [
38
39 (ii) The person to whom a building permit, filed under Subsection (1)(a)(i), is issued is
40 responsible for the accuracy of the information in the building permit.
41 (iii) For the purposes of classifying a record under Title 63G, Chapter 2, Government
42 Records Access and Management Act, building permit information transmitted from a local
43 governmental entity to the database shall be classified in the database by the division
44 notwithstanding the local governmental entity's classification of the building permit
45 information.
46 (b) No later than 15 days after commencement of physical construction work at the
47 project site, the original contractor, owner, or owner-builder [
48 commencement with the database [
49 commencement [
50 (c) An original contractor, owner, or owner-builder may file a notice of
51 commencement with the designated agent prior to the time frames established in Subsections
52 (1)(a) and (b).
53 (d) An owner of construction or an original contractor may file a notice of
54 commencement with the designated agent within the time prescribed by Subsections (1)(a) and
55 (b).
56 (e) (i) If duplicate notices of commencement are filed, they shall be combined into one
57 notice for each project and any notices filed relate back to the date of the earliest-filed notice of
58 commencement for the project.
59 (ii) A duplicate notice of commencement that is untimely filed relates back under
60 Subsection (1)(e)(i) if the earlier filed notice of commencement is timely filed.
61 (iii) Duplicate notices of commencement shall be automatically linked by the
62 designated agent.
63 (f) The designated agent shall assign each construction project a unique project number
64 that:
65 (i) identifies each construction project; and
66 (ii) can be associated with all notices of commencement, preliminary notices, and
67 notices of completion.
68 (g) A notice of commencement is effective only as to any labor, service, equipment,
69 and material furnished to the construction project that is furnished subsequent to the filing of
70 the notice of commencement.
71 (2) (a) A notice of commencement shall include the following:
72 (i) the name and address of the owner of the project;
73 (ii) the name and address of the:
74 (A) original contractor; and
75 (B) surety providing any payment bond for the project, or if none exists, a statement
76 that a payment bond was not required for the work being performed; and
77 (iii) (A) the project address if the project can be reasonably identified by an address; or
78 (B) the name and general description of the location of the project if the project cannot
79 be reasonably identified by an address.
80 (b) A notice of commencement may include:
81 (i) a general description of the project; or
82 (ii) the lot or parcel number, and any subdivision, development, or other project name,
83 of the real property upon which the project is to be constructed if the project is subject to
84 mechanics' liens.
85 (c) A notice of commencement need not include all of the items listed in Subsection
86 (2)(a) if:
87 (i) a building permit is issued for the project; and
88 (ii) all items listed in Subsection (2)(a) that are available on the building permit are
89 included in the notice of commencement.
90 (3) If a notice of commencement for a construction project is not filed within the time
91 [
92 apply:
93 (a) Section 38-1-32 ; and
94 (b) Section 38-1-33 .
95 (4) (a) Unless a person indicates to the division or designated agent that the person
96 does not wish to receive a notice under this section, electronic notice of the filing of a notice of
97 commencement or alternate notice as prescribed in Subsection (1), shall be provided to:
98 (i) all persons who have filed notices of commencement for the project; and
99 (ii) all interested persons who have requested notices concerning the project.
100 (b) (i) A person to whom notice is required under Subsection (4)(a) is responsible for:
101 (A) providing an e-mail address, mailing address, or telefax number to which a notice
102 required by Subsection (4)(a) is to be sent; and
103 (B) the accuracy of any e-mail address, mailing address, or telefax number to which
104 notice is to be sent.
105 (ii) The designated agent fulfills the notice requirement of Subsection (4)(a) when it
106 sends the notice to the e-mail address, mailing address, or telefax number provided to the
107 designated agent whether or not the notice is actually received.
108 (5) (a) The burden is upon any person seeking to enforce a notice of commencement to
109 verify the accuracy of information in the notice of commencement and prove that the notice of
110 commencement is filed timely and meets all of the requirements in this section.
111 (b) A substantial inaccuracy in a notice of commencement renders the notice of
112 commencement unenforceable.
113 (c) A person filing a notice of commencement by alternate filing is responsible for
114 verifying and changing any incorrect information in the notice of commencement before the
115 expiration of the time period during which the notice is required to be filed.
116 (6) At the time a building permit is obtained, each original contractor shall
117 conspicuously post at the project site a copy of the building permit obtained for the project.
Legislative Review Note
as of 2-8-10 5:14 PM