H.B. 115

             1     

MECHANICS' LIENS AMENDMENTS

             2     
2011 GENERAL SESSION

             3     
STATE OF UTAH

             4     
Chief Sponsor: Michael T. Morley

             5     
Senate Sponsor: ____________

             6     
             7      LONG TITLE
             8      General Description:
             9          This bill modifies provisions relating to mechanics' liens.
             10      Highlighted Provisions:
             11          This bill:
             12          .    clarifies the applicability of mechanics' liens provisions;
             13          .    modifies definitions;
             14          .    provides for liens for preconstruction service, establishes a procedure for perfecting
             15      and enforcing the liens, and provides for the priority of the liens;
             16          .    modifies a provision relating to the waiver or limitation of lien rights;
             17          .    provides that a person who knowingly falsifies information for the purpose of
             18      obtaining priority of a preconstruction service lien is guilty of a misdemeanor; and
             19          .    makes technical and conforming changes.
             20      Money Appropriated in this Bill:
             21          None
             22      Other Special Clauses:
             23          None
             24      Utah Code Sections Affected:
             25      AMENDS:
             26          38-1-1, Utah Code Annotated 1953
             27          38-1-4, as last amended by Laws of Utah 1987, Chapter 170


             28          38-1-5, Utah Code Annotated 1953
             29          38-1-7, as last amended by Laws of Utah 2009, Chapter 50
             30          38-1-9, as last amended by Laws of Utah 1987, Chapter 50
             31          38-1-11, as last amended by Laws of Utah 2010, Chapter 31
             32          38-1-19, Utah Code Annotated 1953
             33          38-1-27, as last amended by Laws of Utah 2009, Chapters 183 and 239
             34          38-1-31, as last amended by Laws of Utah 2009, Chapter 50
             35          38-1-32, as last amended by Laws of Utah 2009, Chapter 50
             36          38-1-33, as last amended by Laws of Utah 2010, Chapter 76
             37          38-1-40, as last amended by Laws of Utah 2010, Chapter 31
             38      ENACTS:
             39          38-1-2.1, Utah Code Annotated 1953
             40          38-1-4.7, Utah Code Annotated 1953
             41          38-1-6.5, Utah Code Annotated 1953
             42          38-1-6.7, Utah Code Annotated 1953
             43          38-1-30.5, Utah Code Annotated 1953
             44          76-6-524, Utah Code Annotated 1953
             45      REPEALS AND REENACTS:
             46          38-1-2, as last amended by Laws of Utah 2006, Chapter 297
             47          38-1-3, as last amended by Laws of Utah 1994, Chapter 308
             48          38-1-29, as enacted by Laws of Utah 2001, Chapter 229
             49     
             50      Be it enacted by the Legislature of the state of Utah:
             51          Section 1. Section 38-1-1 is amended to read:
             52           38-1-1. Public improvements not subject to chapter -- Exception.
             53          [The provisions of this]
             54          Except as provided in Sections 38-1-27 , 38-1-30 through 38-1-37 , and 38-1-40 relating
             55      to the State Construction Registry, this chapter [shall] does not apply to any public [building,
             56      structure or] improvement.
             57          Section 2. Section 38-1-2 is repealed and reenacted to read:
             58          38-1-2. Definitions.


             59          As used in this chapter:
             60          (1) "Applicable county recorder" means the office of the recorder of each county in
             61      which any part of the property on which a claimant claims or intends to claim a lien under this
             62      chapter is located.
             63          (2) "Bona fide loan" means a loan to an owner or owner-builder by a lender in which
             64      the owner or owner-builder has no financial or beneficial interest greater than 5% of the voting
             65      shares or other ownership interest.
             66          (3) "Claimant" means a person entitled to claim a lien under this chapter.
             67          (4) "Compensation" means the payment of money for a service rendered or an expense
             68      incurred, whether based on:
             69          (a) time and expense, lump sum, stipulated sum, percentage of cost, cost plus fixed or
             70      percentage fee, or commission; or
             71          (b) a combination of the bases listed in Subsection (4)(a).
             72          (5) "Construction service":
             73          (a) means to provide labor, material, or equipment for the purpose and during the
             74      process of constructing, altering, or repairing an improvement; and
             75          (b) includes the scheduling, estimating, staking, supervising, managing, materials
             76      testing, inspection, observation, and quality control or assurance involved in constructing,
             77      altering, or repairing an improvement.
             78          (6) "Construction service lien" means a lien under this chapter for construction service.
             79          (7) "General preconstruction contractor" means a claimant, whether an original
             80      contractor or subcontractor, who contracts with one or more subcontractors for the
             81      subcontractor or subcontractors to provide preconstruction service that the claimant is under
             82      contract to provide.
             83          (8) "Improvement" means:
             84          (a) a building, infrastructure, utility, or other human-made structure or object
             85      constructed on or for and affixed to real property; or
             86          (b) a repair, modification, or alteration of a building, infrastructure, utility, or object
             87      referred to in Subsection (8)(a).
             88          (9) "Included preconstruction subcontractor" means a subcontractor who is:
             89          (a) under contract with a general preconstruction contractor to provide preconstruction


             90      service; and
             91          (b) included in the general preconstruction contractor's initial or amended notice of
             92      intent to claim a preconstruction service lien under Section 38-1-6.7 .
             93          (10) "Original contract":
             94          (a) means a contract between an owner of real property and an original contractor for
             95      preconstruction service or construction service; and
             96          (b) does not include a contract between an owner-builder and another person.
             97          (11) "Original contractor" means a person who contracts with an owner of real property
             98      to provide preconstruction service or construction service.
             99          (12) "Owner-builder" means an owner of real property who:
             100          (a) contracts with one or more other persons for preconstruction service or construction
             101      service for an improvement on the owner's real property; and
             102          (b) obtains a building permit for the improvement.
             103          (13) "Preconstruction service":
             104          (a) means to plan or design, or to assist in the planning or design of, an improvement or
             105      a proposed improvement:
             106          (i) before construction of the improvement commences; and
             107          (ii) for compensation separate from any compensation paid or to be paid for
             108      construction service for the improvement; and
             109          (b) includes consulting, conducting a site investigation or assessment, programming,
             110      preconstruction cost or quantity estimating, preconstruction scheduling, performing a
             111      preconstruction construction feasibility review, procuring construction services, and preparing
             112      a study, report, rendering, model, boundary or topographic survey, plat, map, design, plan,
             113      drawing, specification, or contract document.
             114          (14) "Preconstruction service lien" means a lien under this chapter for a
             115      preconstruction service.
             116          (15) "Subcontractor" means a person who contracts to provide preconstruction service
             117      or construction service to a person other than the owner of the real property for which the
             118      preconstruction service or construction service is provided.
             119          Section 3. Section 38-1-2.1 is enacted to read:
             120          38-1-2.1. Owner-builder original contract.


             121          For purposes of this chapter, an original contract is considered to exist between an
             122      owner-builder as owner and the owner-builder as original contractor.
             123          Section 4. Section 38-1-3 is repealed and reenacted to read:
             124          38-1-3. Those entitled to lien -- What may be attached.
             125          (1) Subject to the provisions of this chapter, a person who performs preconstruction
             126      service or construction service on or for real property has a lien on the real property for the
             127      reasonable value of the preconstruction service or construction service, respectively, except as
             128      provided in Section 38-11-107 .
             129          (2) A person may claim a preconstruction service lien and a separate construction
             130      service lien on the same real property.
             131          (3) (a) A construction service lien may include an amount claimed for a
             132      preconstruction service.
             133          (b) A preconstruction service lien may not include an amount claimed for construction
             134      service.
             135          (4) A lien under this chapter attaches only to the interest that the owner or
             136      owner-builder has in the real property that is the subject of the lien.
             137          Section 5. Section 38-1-4 is amended to read:
             138           38-1-4. Land covered by lien -- Multiple lots occupied by improvement -- What a
             139      lien attaches to.
             140          [The liens granted by]
             141          (1) A lien under this chapter [shall extend] extends to and [cover so] covers as much of
             142      the land [whereon such building, structure, or] on which the improvement [shall be] is made as
             143      [may be] necessary for the convenient use and occupation of the land. [In case any such
             144      building shall occupy]
             145          (2) If an improvement occupies two or more lots or other subdivisions of land, [such]
             146      the lots or subdivisions [shall be] are considered as one for the purposes of this chapter. [The
             147      liens provided for in]
             148          (3) A lien under this chapter [shall attach] attaches to all franchises, privileges,
             149      appurtenances, [and to all] machinery, and fixtures[,] pertaining to or used in connection with
             150      [any such lands, buildings, structures, or improvements] the improvement.
             151          Section 6. Section 38-1-4.7 is enacted to read:


             152          38-1-4.7. Preconstruction service lien -- Priority.
             153          (1) Except as otherwise provided in this chapter, a preconstruction service lien:
             154          (a) relates back to and takes effect as of the time a notice of intent to claim a
             155      preconstruction service lien under Section 38-1-6.5 is recorded; and
             156          (b) has priority over:
             157          (i) any lien, mortgage, or other encumbrance that attaches after the notice of intent to
             158      claim a preconstruction service lien is recorded; and
             159          (ii) any lien, mortgage, or other encumbrance of which the claimant had no notice and
             160      that was unrecorded at the time the notice of intent to claim a preconstruction service lien is
             161      recorded.
             162          (2) A preconstruction service lien is subordinate to an interest securing a bona fide loan
             163      if and to the extent that the lien covers preconstruction service provided after the interest
             164      securing a bona fide loan is recorded.
             165          (3) Preconstruction service is considered complete for any project, project phase, or bid
             166      package as of the date that construction service for that project, project phase, or bid package,
             167      respectively, commences.
             168          Section 7. Section 38-1-5 is amended to read:
             169           38-1-5. Priority of construction service lien.
             170          [The liens herein provided for shall relate]
             171          A construction service lien:
             172          (1) relates back to, and [take] takes effect as of, the time of the commencement [to do
             173      work or furnish materials] of construction service on the ground for the [structure or]
             174      improvement[,]; and [shall have]
             175          (2) has priority over:
             176          (a) any lien, mortgage, or other encumbrance [which may have attached subsequently
             177      to the time when the building, improvement or structure was commenced, work begun, or first
             178      material furnished] that attaches after the construction service for the improvement commences
             179      on the ground; [also over] and
             180          (b) any lien, mortgage, or other encumbrance of which the [lien holder] claimant had
             181      no notice and [which] that was unrecorded at the time the [building, structure or] construction
             182      service for the improvement [was commenced, work begun, or first material furnished]


             183      commences on the ground.
             184          Section 8. Section 38-1-6.5 is enacted to read:
             185          38-1-6.5. Notice of intent to claim a preconstruction service lien -- Requirements.
             186          (1) (a) On or after the date a claimant first provides a preconstruction service but no
             187      later than the date the claimant completes the service, a claimant shall submit for recording
             188      with the applicable county recorder a notice of intent to claim a preconstruction service lien.
             189          (b) A claimant who is an included preconstruction subcontractor is considered to have
             190      submitted a notice of intent to claim a preconstruction service lien at the same time that the
             191      claimant's general preconstruction contractor submits a notice of intent or amended notice of
             192      intent that includes the claimant as a subcontractor.
             193          (2) A claimant who fails to submit a notice of intent as provided in Subsection (1) may
             194      not claim a preconstruction service lien.
             195          (3) A notice of intent to claim a preconstruction service lien shall include:
             196          (a) the claimant's name, mailing address, and telephone number;
             197          (b) if the claimant is a general preconstruction contractor, the name, mailing address,
             198      and telephone number of each subcontractor under contract with the claimant at the time the
             199      notice is filed;
             200          (c) a statement that the claimant intends to hold and claim a preconstruction service
             201      lien if the claimant is not paid for the preconstruction service the claimant and, if the claimant
             202      is a general contractor, the claimant's subcontractors provide;
             203          (d) a general description of the preconstruction service the claimant and any
             204      subcontractor of the claimant provided or will provide;
             205          (e) the name of the person who employed the claimant;
             206          (f) the name, if known, of the reputed owner of the property on which the
             207      preconstruction service lien is intended to be claimed or, if not known, the name of the record
             208      owner of the property;
             209          (g) a description of the property sufficient for identification;
             210          (h) the claimant's signature or the signature of the claimant's authorized agent; and
             211          (i) an acknowledgment or certificate as required under Title 57, Chapter 3, Recording
             212      of Documents.
             213          (4) A claimant who is a general preconstruction contractor shall submit for recording


             214      with the applicable county recorder an amended notice of intent to claim a preconstruction
             215      service lien that complies with Subsection (3) if, after filing the initial notice of intent, the
             216      claimant contracts with a subcontractor to provide preconstruction service who was not
             217      included in the initial notice of intent.
             218          Section 9. Section 38-1-6.7 is enacted to read:
             219          38-1-6.7. Notice of preconstruction service lien -- Requirements.
             220          (1) (a) Within 90 days after completing a preconstruction service for which a claimant
             221      is not paid in full, the claimant shall submit for recording with the applicable county recorder a
             222      notice of preconstruction service lien.
             223          (b) A claimant who is an included preconstruction subcontractor is considered to have
             224      submitted a notice of preconstruction service lien at the same time that the claimant's general
             225      preconstruction contractor submits a notice of preconstruction service lien that includes the
             226      claimant as a subcontractor.
             227          (2) A claimant who fails to submit a notice of preconstruction service lien as provided
             228      in Subsection (1) may not claim a preconstruction service lien.
             229          (3) A notice of preconstruction service lien shall include:
             230          (a) the claimant's name, mailing address, and telephone number;
             231          (b) if the claimant is a general preconstruction contractor, the name, mailing address,
             232      and telephone number of each included preconstruction subcontractor;
             233          (c) a statement that the claimant claims a preconstruction service lien;
             234          (d) the date the claimant's notice of intent to claim a preconstruction service lien was
             235      recorded and, if the claimant submitted an amended notice of intent to claim a preconstruction
             236      service lien, the date the amended notice of intent was recorded;
             237          (e) the name of the person who employed the claimant;
             238          (f) a general description of the preconstruction service provided by the claimant and
             239      any included preconstruction subcontractor;
             240          (g) the date that the claimant last provided preconstruction service;
             241          (h) the name, if known, of the reputed owner of the property on which the
             242      preconstruction service lien is claimed or, if not known, the name of the record owner of the
             243      property;
             244          (i) a description of the property sufficient for identification;


             245          (j) the principal amount, excluding interest, costs, and attorney fees, claimed by the
             246      claimant and by each included preconstruction subcontractor;
             247          (k) the claimant's signature or the signature of the claimant's authorized agent;
             248          (l) an acknowledgment or certificate as required under Title 57, Chapter 3, Recording
             249      of Documents; and
             250          (m) if the lien is against an owner-occupied residence, as defined in Section 38-11-102 ,
             251      a statement meeting the requirements that the Division of Occupational and Professional
             252      Licensing has established in accordance with Title 63G, Chapter 3, Utah Administrative
             253      Rulemaking Act, describing the steps an owner may take to require a claimant to remove the
             254      lien as provided in Section 38-11-107 .
             255          (4) A general preconstruction contractor's notice of lien may include an amount
             256      claimed by a subcontractor, regardless of tier, who was required under Subsection
             257      38-1-6.5 (3)(a) to be listed in the general preconstruction contractor's notice of intent to claim a
             258      preconstruction service lien only if the subcontractor was listed in the notice of intent.
             259          (5) (a) Within 30 days after a claimant's notice of preconstruction service lien is
             260      recorded, the claimant shall send by certified mail a copy of the notice to the reputed or record
             261      owner of the real property.
             262          (b) If the record owner's address is not readily available to the claimant, the claimant
             263      may mail a copy of the notice to the owner's last-known address as it appears on the last
             264      completed assessment roll of the county in which the property is located.
             265          (c) A claimant's failure to mail a copy of the notice as required in this Subsection (5)
             266      precludes the claimant from being awarded costs and attorney fees against the reputed or record
             267      owner in an action to enforce the lien.
             268          (6) Nothing in this section may be construed to prohibit a claimant from recording a
             269      notice of preconstruction services lien before completing the preconstruction service the
             270      claimant contracted to provide.
             271          Section 10. Section 38-1-7 is amended to read:
             272           38-1-7. Notice of claim for construction service lien -- Contents -- Recording --
             273      Service on owner of property.
             274          (1) (a) (i) Except as modified in Section 38-1-27 , a person claiming [benefits under this
             275      chapter] a construction service lien shall file for record with the applicable county recorder [of


             276      the county in which the property, or some part of the property, is situated,] a written notice to
             277      hold and claim a lien no later than:
             278          (A) 180 days after the day on which occurs final completion of the original contract if
             279      no notice of completion is filed under Section 38-1-33 ; or
             280          (B) 90 days after the day on which a notice of completion is filed under Section
             281      38-1-33 but not later than the time frame established in Subsection (1)(a)(i)(A).
             282          (ii) For purposes of this Subsection (1), final completion of the original contract, and
             283      for purposes of Section 38-1-33 , final completion of the project, means:
             284          (A) if as a result of work performed under the original contract a permanent certificate
             285      of occupancy is required for the work, the date of issuance of a permanent certificate of
             286      occupancy by the local government entity having jurisdiction over the construction project;
             287          (B) if no certificate of occupancy is required by the local government entity having
             288      jurisdiction over the construction project, but as a result of the work performed under the
             289      original contract an inspection is required as per state-adopted building codes for the work, the
             290      date of the final inspection for the work by the local government entity having jurisdiction over
             291      the construction project;
             292          (C) if with regard to work performed under the original contract no certificate of
             293      occupancy and no final inspection are required as per state-adopted building codes by the local
             294      government entity having jurisdiction over the construction project, the date on which there
             295      remains no substantial work to be completed to finish the work on the original contract; or
             296          (D) if as a result of termination of the original contract prior to the completion of the
             297      work defined by the original contract, the compliance agency does not issue a certificate of
             298      occupancy or final inspection, the last date on which substantial work was performed under the
             299      original contract.
             300          (b) Notwithstanding Section 38-1-2 , [where] if a subcontractor performs substantial
             301      work after the applicable dates established by Subsections (1)(a)(ii)(A) and (B), that
             302      subcontractor's subcontract shall be considered an original contract for the sole purpose of
             303      determining:
             304          (i) the subcontractor's time frame to file a notice of intent to hold and claim a lien
             305      under this Subsection (1); and
             306          (ii) the original contractor's time frame to file a notice of intent to hold and claim a lien


             307      under this Subsection (1) for that subcontractor's work.
             308          (c) For purposes of this chapter, the term "substantial work" does not include:
             309          (i) repair work; or
             310          (ii) warranty work.
             311          (d) Notwithstanding Subsection (1)(a)(ii)(C), final completion of the original contract
             312      does not occur if work remains to be completed for which the owner is holding payment to
             313      ensure completion of that work.
             314          (2) (a) The notice required by Subsection (1) shall contain a statement setting forth:
             315          (i) the name of the reputed owner if known or, if not known, the name of the record
             316      owner;
             317          (ii) the name of the person:
             318          (A) by whom the [lien] claimant was employed; or
             319          (B) to whom the [lien] claimant furnished the equipment or material;
             320          (iii) the time when:
             321          (A) the first and last labor or service was performed; or
             322          (B) the first and last equipment or material was furnished;
             323          (iv) a description of the property, sufficient for identification;
             324          (v) the name, current address, and current phone number of the [lien] claimant;
             325          (vi) the amount of the lien claim;
             326          (vii) the signature of the [lien] claimant or the [lien] claimant's authorized agent;
             327          (viii) an acknowledgment or certificate as required under Title 57, Chapter 3,
             328      Recording of Documents; and
             329          (ix) if the lien is on an owner-occupied residence, as defined in Section 38-11-102 , a
             330      statement describing what steps an owner, as defined in Section 38-11-102 , may take to require
             331      a lien claimant to remove the lien in accordance with Section 38-11-107 .
             332          (b) Substantial compliance with the requirements of this chapter is sufficient to hold
             333      and claim a lien.
             334          (3) (a) Within 30 days after filing the notice of lien, the [lien] claimant shall deliver or
             335      mail by certified mail a copy of the notice of lien to:
             336          (i) the reputed owner of the real property; or
             337          (ii) the record owner of the real property.


             338          (b) If the record owner's current address is not readily available to the [lien] claimant,
             339      the copy of the claim may be mailed to the last-known address of the record owner, using the
             340      names and addresses appearing on the last completed real property assessment rolls of the
             341      county where the affected property is located.
             342          (c) Failure to deliver or mail the notice of lien to the reputed owner or record owner
             343      precludes the [lien] claimant from an award of costs and [attorneys'] attorney fees against the
             344      reputed owner or record owner in an action to enforce the lien.
             345          (4) The Division of Occupational and Professional Licensing shall make rules
             346      governing the form of the statement required under Subsection (2)(a)(ix).
             347          Section 11. Section 38-1-9 is amended to read:
             348           38-1-9. Notice imparted by record.
             349          (1) The recorder [must] shall record [the claim] each notice of intent under Subsection
             350      38-1-6.5 (1), notice of preconstruction service lien under Section 38-1-6.7 , and notice to hold
             351      and claim a construction service lien under Section 38-1-7 in an index maintained for that
             352      purpose.
             353          (2) From the time [the claim] a notice described in Subsection (1) is filed for record, all
             354      persons are considered to have notice of [the claim] it.
             355          Section 12. Section 38-1-11 is amended to read:
             356           38-1-11. Enforcement -- Time for -- Lis pendens -- Action for debt not affected --
             357      Instructions and form affidavit and motion.
             358          (1) As used in this section:
             359          (a) "Owner" is as defined in Section 38-11-102 .
             360          (b) "Residence" is as defined in Section 38-11-102 .
             361          (2) A [lien] claimant shall file an action to enforce the lien filed under this chapter:
             362          (a) except as provided in Subsection (2)(b), within 180 days after the day on which the
             363      [lien] claimant [filed] files:
             364          (i) a notice of preconstruction service lien under Section 38-1-6.7 , for a preconstruction
             365      service lien; or
             366          (ii) a notice of claim under Section 38-1-7 , for a construction service lien; or
             367          (b) if an owner files for protection under the bankruptcy laws of the United States
             368      before the expiration of the 180-day period under Subsection (2)(a), within 90 days after the


             369      automatic stay under the bankruptcy proceeding is lifted or expires.
             370          (3) (a) Within the time period provided for filing in Subsection (2) the [lien] claimant
             371      shall file for record with the county recorder of each county in which the lien is recorded a
             372      notice of the pendency of the action, in the manner provided in actions affecting the title or
             373      right to possession of real property, or the lien shall be void, except as to persons who have
             374      been made parties to the action and persons having actual knowledge of the commencement of
             375      the action.
             376          (b) The burden of proof is upon the [lien] claimant and those claiming under the [lien]
             377      claimant to show actual knowledge under Subsection (3)(a).
             378          (4) (a) A lien filed under this chapter is automatically and immediately void if an action
             379      to enforce the lien is not filed within the time required by this section.
             380          (b) Notwithstanding Section 78B-2-111 , a court has no subject matter jurisdiction to
             381      adjudicate a lien that becomes void under Subsection (4)(a).
             382          (5) This section may not be interpreted to impair or affect the right of any person to
             383      whom a debt may be due for any work done or materials furnished to maintain a personal
             384      action to recover the debt.
             385          (6) (a) If a [lien] claimant files an action to enforce a lien filed under this chapter
             386      involving a residence, the lien claimant shall include with the service of the complaint on the
             387      owner of the residence:
             388          (i) instructions to the owner of the residence relating to the owner's rights under Title
             389      38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act; and
             390          (ii) a form to enable the owner of the residence to specify the grounds upon which the
             391      owner may exercise available rights under Title 38, Chapter 11, Residence Lien Restriction and
             392      Lien Recovery Fund Act.
             393          (b) The instructions and form required by Subsection (6)(a) shall meet the requirements
             394      established by rule by the Division of Occupational and Professional Licensing in accordance
             395      with Title 63G, Chapter 3, Utah Administrative Rulemaking Act.
             396          (c) If a [lien] claimant fails to provide to the owner of the residence the instructions
             397      and form required by Subsection (6)(a), the [lien] claimant [shall be] is barred from
             398      maintaining or enforcing the lien upon the residence.
             399          (d) Judicial determination of the rights and liabilities of the owner of the residence


             400      under this chapter and Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery
             401      Fund Act, and Title 14, Chapter 2, Private Contracts, shall be stayed until after the owner is
             402      given a reasonable period of time to establish compliance with Subsections 38-11-204 (4)(a)
             403      and (4)(b) through an informal proceeding, as set forth in Title 63G, Chapter 4, Administrative
             404      Procedures Act, commenced within 30 days of the owner being served summons in the
             405      foreclosure action, at the Division of Occupational and Professional Licensing and obtain a
             406      certificate of compliance or denial of certificate of compliance, as defined in Section
             407      38-11-102 .
             408          (e) An owner applying for a certificate of compliance under Subsection (6)(d) shall
             409      send by certified mail to all lien claimants:
             410          (i) a copy of the application for a certificate of compliance; and
             411          (ii) all materials filed in connection with the application.
             412          (f) The Division of Occupational and Professional Licensing shall notify all [lien]
             413      claimants listed in an owner's application for a certificate of compliance under Subsection
             414      (6)(d) of the issuance or denial of a certificate of compliance.
             415          (7) The written notice requirement applies to liens filed on or after July 1, 2004.
             416          Section 13. Section 38-1-19 is amended to read:
             417           38-1-19. Payment by owner to contractor -- Subcontractor's lien not affected.
             418          [When any] (1) If a subcontractor [shall have] has actually begun to furnish [labor or
             419      materials] preconstruction service or construction service for which [he] the subcontractor is
             420      entitled to a lien [no], a payment to the original contractor [shall] may not impair or defeat
             421      [such] the lien[; and no].
             422          (2) An alteration of [any] a contract [shall] may not affect [any] a lien acquired under
             423      [the provisions of] this chapter.
             424          Section 14. Section 38-1-27 is amended to read:
             425           38-1-27. State Construction Registry -- Form and contents of notice of
             426      commencement, preliminary notice, and notice of completion.
             427          (1) As used in this section, Sections 38-1-30 through 38-1-37 , and Section 38-1-40 :
             428          (a) "Alternate filing" means a legible and complete filing made in a manner established
             429      by the division under Subsection (2)(e) other than an electronic filing.
             430          (b) "Cancel" means to indicate that a filing is no longer given effect.


             431          (c) "Construction project," "project," or "improvement" means all labor, equipment,
             432      and materials provided:
             433          (i) under an original contract; or
             434          (ii) by, or under contracts with, an owner-builder.
             435          (d) "Database" means the State Construction Registry created in this section.
             436          (e) (i) "Designated agent" means the third party the Division of Occupational and
             437      Professional Licensing contracts with to create and maintain the State Construction Registry.
             438          (ii) The designated agent is not an agency, instrumentality, or a political subdivision of
             439      the state.
             440          (f) "Division" means the Division of Occupational and Professional Licensing.
             441          (g) "Interested person" means a person who may be affected by a construction project.
             442          (h) "Program" means the State Construction Registry Program created in this section.
             443          (2) Subject to receiving adequate funding through a legislative appropriation and
             444      contracting with an approved third party vendor who meets the requirements of Sections
             445      38-1-30 through 38-1-37 , there is created the State Construction Registry Program that shall:
             446          (a) (i) assist in protecting public health, safety, and welfare; and
             447          (ii) promote a fair working environment;
             448          (b) be overseen by the division with the assistance of the designated agent;
             449          (c) provide a central repository for notices of commencement, preliminary notices, and
             450      notices of completion filed in connection with all privately owned construction projects as well
             451      as all state and local government owned construction projects throughout Utah;
             452          (d) [be] make accessible [for filing and review], by way of the program Internet
             453      website, the filing and review of:
             454          (i) notices of retention;
             455          [(i)] (ii) notices of commencement;
             456          [(ii)] (iii) preliminary notices;
             457          [(iii)] (iv) a notice of intent to file notice of final completion;
             458          [(iv)] (v) a notice for remaining amounts due to complete the contract; and
             459          [(v)] (vi) notices of completion;
             460          (e) accommodate:
             461          (i) electronic filing of the notices described in Subsection (2)(d); and


             462          (ii) alternate filing of the notices described in Subsection (2)(d) by U.S. mail, telefax,
             463      or any other alternate method as provided by rule made by the division in accordance with Title
             464      63G, Chapter 3, Utah Administrative Rulemaking Act;
             465          (f) (i) provide electronic notification for up to three email addresses for each interested
             466      person or company who requests notice from the construction notice registry; and
             467          (ii) provide alternate means of notification for a person who makes an alternate filing,
             468      including U.S. mail, telefax, or any other method as prescribed by rule made by the division in
             469      accordance with Title 63G, Chapter 3, Utah Administrative Rulemaking Act; and
             470          (g) provide hard-copy printing of electronic receipts for an individual filing evidencing
             471      the date and time of the individual filing and the content of the individual filing.
             472          (3) (a) The designated agent shall provide notice of all other filings for a project to any
             473      person who files a notice of commencement, preliminary notice, or notice of completion for
             474      that project, unless the person:
             475          (i) requests that the person not receive notice of other filings; or
             476          (ii) does not provide the designated agent with the person's contact information in a
             477      manner that adequately informs the designated agent.
             478          (b) An interested person may request notice of filings related to a project.
             479          (c) The database shall be indexed by:
             480          (i) owner name;
             481          (ii) original contractor name;
             482          (iii) subdivision, development, or other project name, if any;
             483          (iv) project address;
             484          (v) lot or parcel number;
             485          (vi) unique project number assigned by the designated agent; and
             486          (vii) any other identifier that the division considers reasonably appropriate in
             487      collaboration with the designated agent.
             488          (4) (a) In accordance with the process required by Section 63J-1-504 , the division shall
             489      establish the fees for:
             490          (i) a notice of retention;
             491          [(i)] (ii) a notice of commencement;
             492          [(ii)] (iii) a preliminary notice;


             493          [(iii)] (iv) a notice of intent to file notice of final completion;
             494          [(iv)] (v) a notice for remaining amounts due to complete the contract;
             495          [(v)] (vi) a notice of completion;
             496          [(vi)] (vii) a request for notice;
             497          [(vii)] (viii) providing a required notice by an alternate method of delivery;
             498          [(viii)] (ix) a duplicate receipt of a filing; and
             499          [(ix)] (x) account setup for a person who wishes to be billed periodically for filings
             500      with the database.
             501          (b) The fees allowed under Subsection (4)(a) may not exceed the amount reasonably
             502      necessary to create and maintain the database.
             503          (c) The fees established by the division may vary by method of filing if one form of
             504      filing is more costly to process than another form of filing.
             505          (d) The division may provide by contract that the designated agent may retain all fees
             506      collected by the designated agent except that the designated agent shall remit to the division the
             507      cost of the division's oversight under Subsection (2)(b).
             508          (5) (a) The database is classified as a public record under Title 63G, Chapter 2,
             509      Government Records Access and Management Act, unless otherwise classified by the division.
             510          (b) A request for information submitted to the designated agent is not subject to Title
             511      63G, Chapter 2, Government Records Access and Management Act.
             512          (c) Information contained in a public record contained in the database shall be
             513      requested from the designated agent.
             514          (d) The designated agent may charge a commercially reasonable fee allowed by the
             515      designated agent's contract with the division for providing information under Subsection (5)(c).
             516          (e) Notwithstanding Title 63G, Chapter 2, Government Records Access and
             517      Management Act, if information is available in a public record contained in the database, a
             518      person may not request the information from the division.
             519          (f) (i) A person may request information that is not a public record contained in the
             520      database from the division in accordance with Title 63G, Chapter 2, Government Records
             521      Access and Management Act.
             522          (ii) The division shall inform the designated agent of how to direct inquiries made to
             523      the designated agent for information that is not a public record contained in the database.


             524          (6) The following are not an adjudicative proceeding under Title 63G, Chapter 4,
             525      Administrative Procedures Act:
             526          (a) the filing of a notice permitted by this chapter;
             527          (b) the rejection of a filing permitted by this chapter; or
             528          (c) other action by the designated agent in connection with a filing of any notice
             529      permitted by this chapter.
             530          (7) The division and the designated agent need not determine the timeliness of any
             531      notice before filing the notice in the database.
             532          (8) (a) A person who is delinquent on the payment of a fee established under
             533      Subsection (4) may not file a notice with the database.
             534          (b) A determination that a person is delinquent on the payment of a fee for filing
             535      established under Subsection (4) shall be made in accordance with Title 63G, Chapter 4,
             536      Administrative Procedures Act.
             537          (c) Any order issued in a proceeding described in Subsection (8)(b) may prescribe the
             538      method of that person's payment of fees for filing notices with the database after issuance of the
             539      order.
             540          (9) If a notice is filed by a third party on behalf of another, the notice is considered to
             541      be filed by the person on whose behalf the notice is filed.
             542          (10) A person filing a notice of commencement, preliminary notice, or notice of
             543      completion is responsible for verifying the accuracy of information entered into the database,
             544      whether the person files electronically or by alternate or third party filing.
             545          Section 15. Section 38-1-29 is repealed and reenacted to read:
             546          38-1-29. No waiver of rights.
             547          (1) (a) A right or privilege under this chapter may not be waived or limited by contract.
             548          (b) A provision of a contract purporting to waive or limit a right or privilege under this
             549      chapter is void.
             550          (2) Notwithstanding Subsection (1), a claimant may waive or limit, in whole or in part,
             551      a lien right under this chapter in consideration of payment as provided in Section 38-1-39 .
             552          (3) Unless an agreement waiving or limiting a lien right expressly provides that a
             553      payment is required to be applied to a specific lien, mortgage, or encumbrance, a payment to a
             554      person claiming or included within a preconstruction service lien and a construction service


             555      lien shall be applied first to the preconstruction service lien until paid in full.
             556          Section 16. Section 38-1-30.5 is enacted to read:
             557          38-1-30.5. Notice of retention.
             558          (1) A person under contract to provide a preconstruction service may file a notice of
             559      retention with the database.
             560          (2) A notice of retention shall include:
             561          (a) the name, mailing address, email address, and telephone number of the person filing
             562      the notice;
             563          (b) a general description of the preconstruction service the person is under contract to
             564      provide; and
             565          (c) (i) the street address of the property for which the person is under contract to
             566      provide preconstruction service; or
             567          (ii) if the property cannot reasonably be identified by a street address, a general
             568      description of the location of the property sufficient for reasonable identification of its location.
             569          Section 17. Section 38-1-31 is amended to read:
             570           38-1-31. Building permit -- Construction -- Notice registry -- Notice of
             571      commencement of work.
             572          (1) (a) (i) (A) For a construction project where a building permit is issued to an original
             573      contractor or owner-builder, no later than 15 days after the issuance of the building permit:
             574          (I) the local government entity issuing that building permit shall input the building
             575      permit application and transmit the building permit information to the database electronically
             576      by way of the Internet or computer modem or by any other means; or
             577          (II) the original contractor for construction service, owner, or owner-builder may file a
             578      notice of commencement with the database whether or not a building permit is issued or a
             579      notice of commencement is filed under Subsection (1)(a)(i)(A)(I).
             580          (B) The information submitted under Subsection (1)(a)(i)(A) forms the basis of a
             581      notice of commencement.
             582          (ii) The person to whom a building permit, filed under Subsection (1)(a)(i), is issued is
             583      responsible for the accuracy of the information in the building permit.
             584          (iii) For the purposes of classifying a record under Title 63G, Chapter 2, Government
             585      Records Access and Management Act, building permit information transmitted from a local


             586      governmental entity to the database shall be classified in the database by the division
             587      notwithstanding the local governmental entity's classification of the building permit
             588      information.
             589          (b) No later than 15 days after commencement of physical construction work at the
             590      project site, the original contractor for construction service, owner, or owner-builder may file a
             591      notice of commencement with the database whether or not a building permit is issued or a
             592      notice of commencement is filed under Subsection (1)(a).
             593          (c) An original contractor for construction service, owner, or owner-builder may file a
             594      notice of commencement with the designated agent prior to the time frames established in
             595      Subsections (1)(a) and (b).
             596          (d) An owner of construction or an original contractor for construction service may file
             597      a notice of commencement with the designated agent within the time prescribed by Subsections
             598      (1)(a) and (b).
             599          (e) (i) If duplicate notices of commencement are filed, they shall be combined into one
             600      notice for each project and any notices filed relate back to the date of the earliest-filed notice of
             601      commencement for the project.
             602          (ii) A duplicate notice of commencement that is untimely filed relates back under
             603      Subsection (1)(e)(i) if the earlier filed notice of commencement is timely filed.
             604          (iii) Duplicate notices of commencement shall be automatically linked by the
             605      designated agent.
             606          (f) The designated agent shall assign each construction project a unique project number
             607      that:
             608          (i) identifies each construction project; and
             609          (ii) can be associated with all notices of commencement, preliminary notices, and
             610      notices of completion.
             611          (g) A notice of commencement is effective only as to any labor, service, equipment,
             612      and material furnished to the construction project that is furnished subsequent to the filing of
             613      the notice of commencement.
             614          (2) (a) A notice of commencement shall include the following:
             615          (i) the name and address of the owner of the project;
             616          (ii) the name and address of the:


             617          (A) original contractor for construction service; and
             618          (B) surety providing any payment bond for the project, or if none exists, a statement
             619      that a payment bond was not required for the work being performed; and
             620          (iii) (A) the project address if the project can be reasonably identified by an address; or
             621          (B) the name and general description of the location of the project if the project cannot
             622      be reasonably identified by an address.
             623          (b) A notice of commencement may include:
             624          (i) a general description of the project; or
             625          (ii) the lot or parcel number, and any subdivision, development, or other project name,
             626      of the real property upon which the project is to be constructed if the project is subject to
             627      mechanics' liens.
             628          (c) A notice of commencement need not include all of the items listed in Subsection
             629      (2)(a) if:
             630          (i) a building permit is issued for the project; and
             631          (ii) all items listed in Subsection (2)(a) that are available on the building permit are
             632      included in the notice of commencement.
             633          (3) If a notice of commencement for a construction project is not filed within the time
             634      set forth in Subsections(1)(a) and (b), the following do not apply:
             635          (a) Section 38-1-32 ; and
             636          (b) Section 38-1-33 .
             637          (4) (a) Unless a person indicates to the division or designated agent that the person
             638      does not wish to receive a notice under this section, electronic notice of the filing of a notice of
             639      commencement or alternate notice as prescribed in Subsection (1), shall be provided to:
             640          (i) all persons who have filed notices of commencement for the project; and
             641          (ii) all interested persons who have requested notices concerning the project.
             642          (b) (i) A person to whom notice is required under Subsection (4)(a) is responsible for:
             643          (A) providing an email address, mailing address, or telefax number to which a notice
             644      required by Subsection (4)(a) is to be sent; and
             645          (B) the accuracy of any email address, mailing address, or telefax number to which
             646      notice is to be sent.
             647          (ii) The designated agent fulfills the notice requirement of Subsection (4)(a) when it


             648      sends the notice to the email address, mailing address, or telefax number provided to the
             649      designated agent whether or not the notice is actually received.
             650          (5) (a) The burden is upon any person seeking to enforce a notice of commencement to
             651      verify the accuracy of information in the notice of commencement and prove that the notice of
             652      commencement is filed timely and meets all of the requirements in this section.
             653          (b) A substantial inaccuracy in a notice of commencement renders the notice of
             654      commencement unenforceable.
             655          (c) A person filing a notice of commencement by alternate filing is responsible for
             656      verifying and changing any incorrect information in the notice of commencement before the
             657      expiration of the time period during which the notice is required to be filed.
             658          (6) At the time a building permit is obtained, each original contractor for construction
             659      service shall conspicuously post at the project site a copy of the building permit obtained for
             660      the project.
             661          Section 18. Section 38-1-32 is amended to read:
             662           38-1-32. Preliminary notice by subcontractor.
             663          (1) (a) (i) Except for a person who has a contract with an owner or an owner-builder or
             664      a laborer compensated with wages, a subcontractor for construction service shall file a
             665      preliminary notice with the database by the later of:
             666          (A) 20 days after commencement of its own work or the commencement of furnishing
             667      labor, service, equipment, and material to a construction project; or
             668          (B) 20 days after the filing of a notice of commencement if the subcontractor's work
             669      commences before the filing of the first notice of commencement.
             670          (ii) A preliminary notice filed within the period described in Subsection (1)(a)(i) is
             671      effective as to all labor, service, equipment, and material furnished to the construction project,
             672      including labor, service, equipment, and material provided to more than one contractor or
             673      subcontractor.
             674          (iii) (A) If more than one notice of commencement is filed for a project, a person may
             675      attach a preliminary notice to any notice of commencement filed for the project by a party
             676      authorized in Section 38-1-31 .
             677          (B) A preliminary notice attached to an untimely notice of commencement is valid if
             678      there is also a valid and timely notice of commencement for the project filed by a party


             679      authorized in Section 38-1-31 .
             680          (b) If a person files a preliminary notice after the period prescribed by Subsection
             681      (1)(a), the preliminary notice becomes effective five days after the day on which the
             682      preliminary notice is filed.
             683          (c) Except as provided in Subsection (1)(e), failure to file a preliminary notice within
             684      the period required by Subsection (1)(a) precludes a person from maintaining any claim for
             685      compensation earned for performance of labor or service or supply of materials or equipment
             686      furnished to the construction project before the expiration of five days after the late filing of a
             687      preliminary notice, except as against the person with whom the person contracted.
             688          (d) (i) (A) If a person who is required to file a preliminary notice under this chapter
             689      fails to file the preliminary notice, that person may not hold a valid lien under this chapter.
             690          (B) A county recorder need not verify that a valid preliminary notice is filed when a
             691      person files a notice to hold and claim a lien under Section 38-1-7 .
             692          (ii) The content of a preliminary notice shall include:
             693          (A) the building permit number for the project, or the number assigned to the project
             694      by the designated agent;
             695          (B) the name, address, and telephone number of the person furnishing the labor,
             696      service, equipment, or material;
             697          (C) the name and address of the person who contracted with the claimant for the
             698      furnishing of the labor, service, equipment, or material;
             699          (D) the name of the record or reputed owner of the project;
             700          (E) the name of the original contractor for construction service under which the
             701      claimant is performing or will perform its work; and
             702          (F) the address of the project or a description of the location of the project.
             703          (iii) Upon request by person identified in Subsection (1)(a)(i), an original contractor for
             704      construction service shall provide the person with the building permit number for the project,
             705      or the number assigned to the project by the designated agent.
             706          (e) If a person provides labor, service, equipment, or material before the filing of a
             707      notice of commencement and the notice of commencement is filed more than 15 days after the
             708      day on which the person providing labor, service, equipment, or material begins work on the
             709      project, the person providing labor, service, equipment, or material need not file a preliminary


             710      notice to maintain the person's right to hold a lien under this chapter or any other right,
             711      including a right referenced under Subsection (1)(c).
             712          (2) (a) (i) Unless a person indicates to the division or designated agent that the person
             713      does not wish to receive a notice under this section, electronic notification of the filing of a
             714      preliminary notice or alternate notice as prescribed in Subsection (1), shall be provided to:
             715          (A) the person filing the preliminary notice;
             716          (B) each person that filed a notice of commencement for the project; and
             717          (C) all interested persons who have requested notices concerning the project.
             718          (ii) A person to whom notice is required under Subsection (2)(a)(i) is responsible for:
             719          (A) providing an email address, mailing address, or telefax number to which a notice
             720      required by Subsection (2)(a) is to be sent; and
             721          (B) the accuracy of any email address, mailing address, or telefax number to which
             722      notice is to be sent.
             723          (iii) The designated agent fulfills the notice requirement of Subsection (2)(a)(i) when it
             724      sends the notice to the email address, mailing address, or telefax number provided to the
             725      designated agent whether or not the notice is actually received.
             726          (b) The burden is upon the person filing the preliminary notice to prove that the person
             727      has substantially complied with the requirements of this section.
             728          (c) Subject to Subsection (2)(d), a person required by this section to give preliminary
             729      notice is only required to give one notice for each project.
             730          (d) If the labor, service, equipment, or material is furnished pursuant to contracts under
             731      more than one original contract for construction service, the notice requirements must be met
             732      with respect to the labor, service, equipment, or material furnished under each original contract.
             733          (3) (a) If a construction project owner, original contractor, or subcontractor for
             734      construction service, or other interested person believes that a preliminary notice has been filed
             735      erroneously, that owner, original contractor, subcontractor, or other interested person can
             736      request from the person who filed the preliminary notice evidence establishing the validity of
             737      the preliminary notice.
             738          (b) Within 10 days after the request described in Subsection (3)(a), the person or entity
             739      that filed the preliminary notice shall provide the requesting person or entity proof that the
             740      preliminary notice is valid.


             741          (c) If the person or entity that filed the preliminary notice does not provide proof of the
             742      validity of the preliminary notice, that person or entity shall immediately cancel the preliminary
             743      notice from the database in any manner prescribed by the division pursuant to rule.
             744          (4) A person filing a preliminary notice by alternate filing is responsible for verifying
             745      and changing any incorrect information in the preliminary notice before the expiration of the
             746      time period during which the notice is required to be filed.
             747          (5) Until June 1, 2008, nothing in this section affects a person's rights under Title 38,
             748      Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act.
             749          Section 19. Section 38-1-33 is amended to read:
             750           38-1-33. Notice of completion.
             751          (1) (a) Upon final completion of a construction project, and in accordance with Section
             752      38-1-40 , the following with a construction project registered with the database may file a notice
             753      of completion with the database:
             754          (i) an owner of the construction project;
             755          (ii) an original contractor [of the] for construction [project] service;
             756          (iii) a lender that has provided financing for the construction project;
             757          (iv) a surety that has provided bonding for the construction project; or
             758          (v) a title company issuing a title insurance policy on the construction project.
             759          (b) Notwithstanding Section 38-1-2 , if a subcontractor for construction service
             760      performs substantial work after the applicable dates established by Subsection (1)(a), that
             761      subcontractor's subcontract is considered an original contract for construction service for the
             762      sole purpose of determining:
             763          (i) the subcontractor's time frame to file a notice to hold and claim a lien under
             764      Subsection 38-1-7 (1); and
             765          (ii) the original contractor's time frame to file a notice to hold and claim a lien under
             766      Subsection 38-1-7 (1) for that subcontractor's work.
             767          (c) A notice of completion shall include:
             768          (i) the building permit number for the project, or the number assigned to the project by
             769      the designated agent;
             770          (ii) the name, address, and telephone number of the person filing the notice of
             771      completion;


             772          (iii) the name of the original contractor for [the project] construction service;
             773          (iv) the address of the project or a description of the location of the project;
             774          (v) the date on which final completion is alleged to have occurred; and
             775          (vi) the method used to determine final completion.
             776          (d) For purposes of this section, final completion of the original contract does not occur
             777      if work remains to be completed for which the owner is holding payment to ensure completion
             778      of the work.
             779          (e) (i) Unless a person indicates to the division or designated agent that the person does
             780      not wish to receive a notice under this section, electronic notification of the filing of a notice of
             781      completion or alternate notice as prescribed in Subsection (1)(a), shall be provided to:
             782          (A) each person that filed a notice of commencement for the project;
             783          (B) each person that filed preliminary notice for the project; and
             784          (C) all interested persons who have requested notices concerning the project.
             785          (ii) A person to whom notice is required under this Subsection (1)(e) is responsible for:
             786          (A) providing an email address, mailing address, or telefax number to which a notice
             787      required by this Subsection (1)(e) is to be sent; and
             788          (B) the accuracy of any email address, mailing address, or telefax number to which
             789      notice is to be sent.
             790          (iii) The designated agent fulfills the notice requirement of Subsection (1)(e)(i) when it
             791      sends the notice to the email address, mailing address, or telefax number provided to the
             792      designated agent, whether or not the notice is actually received.
             793          (iv) Upon the filing of a notice of completion, the time periods for filing preliminary
             794      notices stated in Section 38-1-27 are modified such that all preliminary notices shall be filed
             795      subsequent to the notice of completion and within 10 days from the day on which the notice of
             796      completion is filed.
             797          (f) A subcontract that is considered an original contract for construction service for
             798      purposes of this section does not create a requirement for an additional preliminary notice if a
             799      preliminary notice has already been given for the labor, service, equipment, and material
             800      furnished to the subcontractor who performs substantial work.
             801          (2) (a) If a construction project owner, original contractor, or subcontractor for
             802      construction service, or other interested person believes that a notice of completion has been


             803      filed erroneously, that owner, original contractor, subcontractor, or other interested person can
             804      request from the person who filed the notice of completion evidence establishing the validity of
             805      the notice of completion.
             806          (b) Within 10 days after the request described in Subsection (2)(a), the person who
             807      filed the notice of completion shall provide the requesting person proof that the notice of
             808      completion is valid.
             809          (c) If the person that filed the notice of completion does not provide proof of the
             810      validity of the notice of completion, that person shall immediately cancel the notice of
             811      completion from the database in any manner prescribed by the division pursuant to rule.
             812          (3) A person filing a notice of completion by alternate filing is responsible for verifying
             813      and changing any incorrect information in the notice of completion before the expiration of the
             814      time period during which the notice is required to be filed.
             815          Section 20. Section 38-1-40 is amended to read:
             816           38-1-40. Notice of intent to obtain final completion.
             817          (1) An owner, as defined in Section 14-2-1 , of a nonresidential construction project
             818      that is registered with the database, or a contractor of a commercial nonresidential construction
             819      project that is registered with the database under Section 38-1-33 , shall file with the database a
             820      notice of intent to obtain final completion as provided in this section if:
             821          (a) the completion of performance time under the original contract for construction
             822      service is greater than 120 days;
             823          (b) the total original construction contract price exceeds $500,000; and
             824          (c) the contractor or owner has not obtained a payment bond in accordance with
             825      Section 14-2-1 .
             826          (2) The notice of intent described in Subsection (1) shall be filed at least 45 days before
             827      the day on which the owner or contractor of a commercial nonresidential construction project
             828      files or could have filed a notice of completion under Section 38-1-33 .
             829          (3) A person supplying labor, materials, or services to an owner, a contractor, or
             830      subcontractor who files a notice of intent in accordance with Subsection (1) shall file an
             831      amendment to the person's preliminary notice previously filed by the person as required in
             832      Section 38-1-32 :
             833          (a) that includes:


             834          (i) a good faith estimate of the total amount remaining due to complete the contract,
             835      purchase order, or agreement relating to the person's approved labor, approved materials, and
             836      approved services;
             837          (ii) the identification of each contractor or subcontractor with whom the person has a
             838      contract or contracts for supplying project labor, materials, or services; and
             839          (iii) a separate statement of all known amounts or categories of work in dispute; and
             840          (b) no later than 20 days after the day on which the owner or contractor files a notice of
             841      intent.
             842          (4) (a) A person identified in accordance with Subsection (3)(a)(i) who has complied
             843      with, or is exempt from, the provisions of Section 38-1-22 , may demand a statement of
             844      adequate assurance from the owner, contractor, or subcontractor with whom the person has
             845      privity of contract no later than 10 days after the day on which the person files a balance
             846      statement in accordance with Subsection (3) from an owner, contractor, or subcontractor who is
             847      in privity of contract with the person.
             848          (b) A demand for adequate assurance as described in Subsection (4)(a) may include a
             849      request for a statement from the owner, contractor, or subcontractor that the owner, contractor,
             850      or subcontractor has sufficient funds dedicated and available to pay for all sums due to the
             851      person filing for the adequate assurances or that will become due in order to complete a
             852      construction project.
             853          (c) A person who demands adequate assurance under Subsection (4)(a) shall deliver
             854      copies of the demand to the owner and contractor:
             855          (i) by hand delivery with a responsible party's acknowledgment of receipt;
             856          (ii) by certified mail with a return receipt; or
             857          (iii) as provided under Rule 4, Utah Rules of Civil Procedure.
             858          (5) (a) A person identified in accordance with Subsection (3)(a)(i) who has complied
             859      with, or is exempt from, the provisions of Section 38-1-32 may bring a legal action against a
             860      party with whom the person is in privity of contract, including a request for injunctive or
             861      declaratory relief, to determine the adequacy of an owner's, with whom the demanding person
             862      contracted, contractor's, with whom the demanding person contracted, or subcontractor's, with
             863      whom the demanding person contracted, funds if, after the person demands adequate assurance
             864      in accordance with the requirements of this section:


             865          (i) the owner, contractor, or subcontractor fails to provide adequate assurance that the
             866      owner, contractor, or subcontractor has sufficient available funds, or access to financing or
             867      other sufficient available funds, to pay for the completion of the demanding person's approved
             868      work on the construction project; or
             869          (ii) the parties disagree, in good faith, as to whether there are adequate funds, or access
             870      to financing or other sufficient available funds, to pay for the completion of the demanding
             871      person's approved work on the construction project.
             872          (b) If a court finds that an owner, contractor, or subcontractor has failed to provide
             873      adequate assurance in accordance with Subsection (4)(a), the court may require the owner,
             874      contractor, or subcontractor to post adequate security with the court sufficient to assure timely
             875      payment of the remaining contract balance for the approved work of the person seeking
             876      adequate assurance, including:
             877          (i) cash;
             878          (ii) a bond;
             879          (iii) an irrevocable letter of credit;
             880          (iv) property;
             881          (v) financing; or
             882          (vi) another form of security approved by the court.
             883          (6) (a) A person is subject to the civil penalty described in Subsection (6)(b), if the
             884      person files a balance statement described in Subsection (3):
             885          (i) that misrepresents the amount due under the contract; and
             886          (ii) with the intent to:
             887          (A) charge an owner, contractor, or subcontractor more than the actual amount due; or
             888          (B) procure any other unfair advantage or benefit on the person's behalf.
             889          (b) The civil penalty described in Subsection (6)(a) is the greater of:
             890          (i) twice the amount by which the balance statement filed under Subsection (3) exceeds
             891      the amount actually remaining due under the contract for completion of construction; or
             892          (ii) the actual damages incurred by the owner, contractor, or subcontractor.
             893          (7) A court shall award reasonable attorney fees to a prevailing party for an action
             894      brought under this section.
             895          (8) Failure to comply with the requirements established in this section does not affect


             896      any other requirement or right under this chapter.
             897          (9) A person who has not complied with, or is not exempt from, the provisions of
             898      Section 38-1-32 may not be entitled to a right or a remedy provided in this section.
             899          (10) This section does not create a cause of action against a person with whom the
             900      demanding party is not in privity of contract.
             901          Section 21. Section 76-6-524 is enacted to read:
             902          76-6-524. Falsifying information for preconstruction service lien purposes.
             903          A person who knowingly falsifies information for the purpose of obtaining priority of a
             904      preconstruction service lien under Title 38, Chapter 1, Mechanics' Liens, is guilty of a class B
             905      misdemeanor.




Legislative Review Note
    as of 2-3-11 9:47 AM


Office of Legislative Research and General Counsel


[Bill Documents][Bills Directory]