S.B. 93 Enrolled

             1     

RETENTION PROCEEDS REVISIONS

             2     
2012 GENERAL SESSION

             3     
STATE OF UTAH

             4     
Chief Sponsor: Scott K. Jenkins

             5     
House Sponsor: Michael T. Morley

             6     
             7      LONG TITLE
             8      General Description:
             9          This bill modifies provisions in the Utah Code relating to retention proceeds under a
             10      construction contract.
             11      Highlighted Provisions:
             12          This bill:
             13          .    clarifies the meaning of public agency;
             14          .    modifies how retention money is held and accounted for; and
             15          .    limits the amount a local school board may retain until a school construction project
             16      is completed and accepted by the board to 5% of the contract price.
             17      Money Appropriated in this Bill:
             18          None
             19      Other Special Clauses:
             20          None
             21      Utah Code Sections Affected:
             22      AMENDS:
             23          13-8-5, as last amended by Laws of Utah 2001, Chapter 9
             24          53A-20-101, as last amended by Laws of Utah 2008, Chapter 382
             25     
             26      Be it enacted by the Legislature of the state of Utah:
             27          Section 1. Section 13-8-5 is amended to read:
             28           13-8-5. Definitions -- Limitation on retention proceeds withheld -- Deposit in
             29      interest-bearing escrow account -- Release of proceeds -- Payment to subcontractors _


             30      Penalty -- No waiver.
             31          (1) As used in this section:
             32          (a) (i) "Construction contract" means a written agreement between the parties relative
             33      to the design, construction, alteration, repair, or maintenance of a building, structure, highway,
             34      appurtenance, appliance, or other improvements to real property, including moving,
             35      demolition, and excavating for nonresidential commercial or industrial construction projects.
             36          (ii) If the construction contract is for construction of a project that is part residential
             37      and part nonresidential, this section applies only to that portion of the construction project that
             38      is nonresidential as determined pro rata based on the percentage of the total square footage of
             39      the project that is nonresidential.
             40          (b) "Construction lender" means any person, including a bank, trust company, savings
             41      bank, industrial bank, land bank, safe deposit company, private banker, savings and loan
             42      association, credit union, cooperative bank, small loan company, sales finance company,
             43      investment company, or any other financial institution that advances money to a borrower for
             44      the purpose of making alterations or improvements to real property. A construction lender
             45      does not include a person or entity who is acting in the capacity of contractor, original
             46      contractor, or subcontractor.
             47          (c) "Contractor" means a person who, for compensation other than wages as an
             48      employee, undertakes any work in a construction trade, as defined in Section 58-55-102 and
             49      includes:
             50          (i) any person engaged as a maintenance person who regularly engages in activities set
             51      forth in Section 58-55-102 as a construction trade; or
             52          (ii) a construction manager who performs management and counseling services on a
             53      construction project for a fee.
             54          (d) "Original contractor" is as provided in Section 38-1-2 .
             55          (e) "Owner" means the person who holds any legal or equitable title or interest in
             56      property. Owner does not include a construction lender unless the construction lender has an
             57      ownership interest in the property other than solely as a construction lender.


             58          (f) "Public agency" means any state agency or a county, city, town, school district, local
             59      district, special service district, or other political subdivision of the state that enters into a
             60      construction contract for an improvement of public property.
             61          (g) "Retention payment" means release of retention proceeds as defined in Subsection
             62      (1)(h).
             63          (h) "Retention proceeds" means money earned by a contractor or subcontractor but
             64      retained by the owner or public agency pursuant to the terms of a construction contract to
             65      guarantee payment or performance by the contractor or subcontractor of the construction
             66      contract.
             67          (i) "Subcontractor" is as defined in Section 38-1-2 .
             68          (j) "Successful party" has the same meaning as it does under Section 38-1-18 .
             69          (2) (a) This section is applicable to all construction contracts relating to construction
             70      work or improvements entered into on or after July 1, 1999, between:
             71          (i) an owner or public agency and an original contractor;
             72          (ii) an original contractor and a subcontractor; and
             73          (iii) subcontractors under a contract described in Subsection (2)(a)(i) or (ii).
             74          (b) This section does not apply to a construction lender.
             75          (3) (a) Notwithstanding Section 58-55-603 , the retention proceeds withheld and
             76      retained from any payment due under the terms of the construction contract may not exceed 5%
             77      of the payment:
             78          (i) by the owner or public agency to the original contractor;
             79          (ii) by the original contractor to any subcontractor; or
             80          (iii) by a subcontractor.
             81          (b) The total retention proceeds withheld may not exceed 5% of the total construction
             82      price.
             83          (c) The percentage of the retention proceeds withheld and retained pursuant to a
             84      construction contract between the original contractor and a subcontractor or between
             85      subcontractors shall be the same retention percentage as between the owner and the original


             86      contractor if:
             87          (i) the retention percentage in the original construction contract between an owner and
             88      the original contractor is less than 5%; or
             89          (ii) after the original construction contract is executed but before completion of the
             90      construction contract the retention percentage is reduced to less than 5%.
             91          (4) (a) If any payment on a contract with a private contractor, firm, or corporation to do
             92      work for an owner or public agency is retained or withheld by the owner or the public agency,
             93      as retention proceeds, it shall be placed in an interest-bearing account and accounted for
             94      separately from other amounts paid under the contract.
             95          (b) The interest accrued under Subsection (4)(a) shall be:
             96          (i) for the benefit of the contractor and subcontractors; and
             97          (ii) paid after the project is completed and accepted by the owner or the public agency.
             98          (c) The contractor shall ensure that any interest accrued on the retainage is distributed
             99      by the contractor to subcontractors on a pro rata basis.
             100          (d) Retention proceeds and accrued interest retained by an owner or public agency:
             101          (i) are considered to be in a constructive trust for the benefit of the contractor and
             102      subcontractors who have earned the proceeds; and
             103          (ii) are not subject to assignment, encumbrance, attachment, garnishment, or execution
             104      levy for the debt of any person holding the retention proceeds and accrued interest.
             105          (5) Any retention proceeds retained or withheld pursuant to this section and any
             106      accrued interest shall be released pursuant to a billing statement from the contractor within 45
             107      days from the later of:
             108          (a) the date the owner or public agency receives the billing statement from the
             109      contractor;
             110          (b) the date that a certificate of occupancy or final acceptance notice is issued to:
             111          (i) the original contractor who obtained the building permit from the building inspector
             112      or public agency;
             113          (ii) the owner or architect; or


             114          (iii) the public agency;
             115          (c) the date that a public agency or building inspector having authority to issue its own
             116      certificate of occupancy does not issue the certificate but permits partial or complete occupancy
             117      of a newly constructed or remodeled building; or
             118          (d) the date the contractor accepts the final pay quantities.
             119          (6) If only partial occupancy of a building is permitted, any retention proceeds withheld
             120      and retained pursuant to this section and any accrued interest shall be partially released within
             121      45 days under the same conditions as provided in Subsection (5) in direct proportion to the
             122      value of the part of the building occupied.
             123          (7) The billing statement from the contractor as provided in Subsection (5)(a) shall
             124      include documentation of lien releases or waivers.
             125          (8) (a) Notwithstanding Subsection (3):
             126          (i) if a contractor or subcontractor is in default or breach of the terms and conditions of
             127      the construction contract documents, plans, or specifications governing construction of the
             128      project, the owner or public agency may withhold from payment for as long as reasonably
             129      necessary an amount necessary to cure the breach or default of the contractor or subcontractor;
             130      or
             131          (ii) if a project or a portion of the project has been substantially completed, the owner
             132      or public agency may retain until completion up to twice the fair market value of the work of
             133      the original contractor or of any subcontractor that has not been completed:
             134          (A) in accordance with the construction contract documents, plans, and specifications;
             135      or
             136          (B) in the absence of plans and specifications, to generally accepted craft standards.
             137          (b) An owner or public agency that refuses payment under Subsection (8)(a) shall
             138      describe in writing within 45 days of withholding such amounts what portion of the work was
             139      not completed according to the standards specified in Subsection (8)(a).
             140          (9) (a) Except as provided in Subsection (9)(b), an original contractor or subcontractor
             141      who receives retention proceeds shall pay each of its subcontractors from whom retention has


             142      been withheld each subcontractor's share of the retention received within 10 days from the day
             143      that all or any portion of the retention proceeds is received:
             144          (i) by the original contractor from the owner or public agency; or
             145          (ii) by the subcontractor from:
             146          (A) the original contractor; or
             147          (B) a subcontractor.
             148          (b) Notwithstanding Subsection (9)(a), if a retention payment received by the original
             149      contractor is specifically designated for a particular subcontractor, payment of the retention
             150      shall be made to the designated subcontractor.
             151          (10) (a) In any action for the collection of the retained proceeds withheld and retained
             152      in violation of this section, the successful party is entitled to:
             153          (i) attorney's fees; and
             154          (ii) other allowable costs.
             155          (b) (i) Any owner, public agency, original contractor, or subcontractor who knowingly
             156      and wrongfully withholds a retention shall be subject to a charge of 2% per month on the
             157      improperly withheld amount, in addition to any interest otherwise due.
             158          (ii) The charge described in Subsection (10)(b)(i) shall be paid to the contractor or
             159      subcontractor from whom the retention proceeds have been wrongfully withheld.
             160          (11) A party to a construction contract may not require any other party to waive any
             161      provision of this section.
             162          Section 2. Section 53A-20-101 is amended to read:
             163           53A-20-101. Construction and alteration of schools and plants -- Advertising for
             164      bids -- Payment and performance bonds -- Contracts -- Bidding limitations on local
             165      school boards -- Interest of local school board members.
             166          (1) As used in this section, the word "sealed" does not preclude acceptance of
             167      electronically sealed and submitted bids or proposals in addition to bids or proposals manually
             168      sealed and submitted.
             169          (2) (a) Prior to the construction of any school or the alteration of any existing school


             170      plant, if the total estimated accumulative building project cost exceeds $80,000, a local school
             171      board shall advertise for bids on the project at least 10 days before the bid due date.
             172          (b) The board shall have the advertisement published in a newspaper having general
             173      circulation throughout the state and in appropriate construction trade publications that offer
             174      free listings.
             175          (c) A similar advertisement is required in a newspaper published or having general
             176      circulation in any city or county that would be affected by the proposed project.
             177          (d) The advertisement shall:
             178          (i) require sealed proposals for the building project in accordance with plans and
             179      specifications furnished by the local school board;
             180          (ii) state where and when the proposals will be opened and shall reserve the right of the
             181      board to reject any and all proposals; and
             182          (iii) require a certified check or bid bond of not less than 5% of the bid to accompany
             183      the bid.
             184          (3) (a) The board shall meet at the time and place specified in the advertisement and
             185      publicly open and read all received proposals.
             186          (b) If satisfactory bids are received, the board shall award the contract to the lowest
             187      responsible bidder.
             188          (c) If none of the proposals are satisfactory, all shall be rejected.
             189          (d) The board shall again advertise in the manner provided in this section.
             190          (e) If, after advertising a second time no satisfactory bid is received, the board may
             191      proceed under its own direction with the required project.
             192          (4) (a) The check or bond required under Subsection (2)(d) shall be drawn in favor of
             193      the local school board.
             194          (b) If the successful bidder fails or refuses to enter into the contract and furnish the
             195      additional bonds required under this section, then the bidder's check or bond is forfeited to the
             196      district.
             197          (5) A local school board shall require payment and performance bonds of the


             198      successful bidder as required in Section 63G-6-505 .
             199          (6) (a) A local school board may require in the proposed contract that [at least 10%] up
             200      to 5% of the contract price be withheld until the project is completed and accepted by the
             201      board.
             202          (b) If money is withheld, the board shall place it in an interest bearing account, and the
             203      interest accrues for the benefit of the contractor and subcontractors.
             204          (c) This money shall be paid upon completion of the project and acceptance by the
             205      board.
             206          (7) (a) A local school board may not bid on projects within the district if the total
             207      accumulative estimated cost exceeds $80,000.
             208          (b) The board may use its resources if no satisfactory bids are received under this
             209      section.
             210          (8) If the local school board determines in accordance with Section 63G-6-501 to use a
             211      construction manager/general contractor as its method of construction contracting management
             212      on projects where the total estimated accumulative cost exceeds $80,000, it shall select the
             213      construction manager/general contractor using one of the source selection methods provided
             214      for in Sections 63G-6-401 through 63G-6-501 .
             215          (9) A local school board member may not have a direct or indirect financial interest in
             216      the construction project contract.


[Bill Documents][Bills Directory]