2nd Sub.
H.B.
503
CONSTRUCTION AMENDMENTS
House Floor
Amendments
Amendment 2 February 28, 2012 11:25 AM
Representative Michael T. Morley proposes the following amendments:
1. Page 1, Line 21 :
21 . any other entity that provides or collects for labor;
{
and
}
. requires a construction contract to contain a differing site conditions clause; and
2. Page 8, Lines 228 through 239 :
228 53A-20-109. Required contract terms.
229
{
(1) As used in this section," differing site conditions clause" means a clause in a
230 construction contract that provides for an equitable adjustment to the contract in the event that
231 the contractor discovers, and promptly reports to the government entity that contracted for the
232 construction, the existence on the construction site of any of the following that were not known
233 by the contractor at the time the contract was executed:
234 (a) subsurface or latent physical conditions that differ materially from the conditions
235 indicated in the contract; or
236 (b) physical conditions of an unusual nature that differ materially from those ordinarily
237 encountered for the type of construction or for the location of the construction site.
238 (2) A contract for the construction of a school building shall contain a differing site
239 conditions clause. }
A contract for the construction of a school building shall contain a clause that addresses the rights of
the parties when, after the contract is executed, site conditions are discovered that:
(1) the contractor did not know existed, and should not have known existed, at the time that the contract was executed; and
(2) materially impacts the costs of construction.
3. Page 11, Lines 308 through 319 :
308
{
(6) (a) As used in this Subsection (6), "differing site conditions clause" means a clause
309 in a construction contract that provides for an equitable adjustment to the contract in the event
310 that the contractor discovers, and promptly reports to the public procurement unit that
311 contracted for the construction, the existence on the construction site of any of the following
312 that were not known by the contractor at the time the contract was executed:
313 (i) subsurface or latent physical conditions that differ materially from the conditions
314 indicated in the contract; or
315 (ii) physical conditions of an unusual nature that differ materially from those ordinarily
316 encountered for the type of construction or for the location of the construction site.
317 (b) Notwithstanding any provision of this chapter to the contrary, a contract for
318 construction entered into by a public procurement unit shall contain a differing site conditions
319 clause. }
(6) A contract for construction entered into by a public procurement unit shall contain a clause that
addresses the rights of the parties when, after the contract is executed, site conditions are discovered
that:
(a) the contractor did not know existed, and should not have known existed, at the time that the contract was executed; and
(b) materially impacts the costs of construction.
Page 1 of 2
LRGC tomvaughn tomvaughn