Agency: Transportation

Line Item: TIF Capacity Program

Function

The Transportation Investment Fund Capacity Program enables the Department to manage highway capacity construction programs that were previously designated Centennial Highway Fund, Critical Needs Highway Fund, and Transportation Investment Fund of 2005 as one program. This allows the Department to develop new capacity highways from the design stage through their completion without switching back and forth between line items for accounting tracking purposes.

Statutory Authority

The Construction Program of the Utah Department of Transportation is governed by the Utah Transportation Code 72-06.

The Transportation Investment Fund of 2005 was created under Title 72-2-124. The funds deposited into the Transportation Investment Fund of 2005 are to be used by the Department to pay the costs of maintenance, construction, reconstruction, or renovation to state and federal highways prioritized by the Transportation Commission through the prioritization process for new transportation capacity projects adopted under Section 72-1-304

Funding Detail

For more detail about a particular source of finance or organizational unit, click a linked entry in the left column of the table(s) below.

Sources of Finance
(click linked fund name for more info)
2009
Actual
2010
Actual
2011
Actual
2012
Actual
2013
Approp
Transportation Investment Fund of 2005 $77,092,500 $44,987,600 $14,543,200 $31,061,500 $0
Total
$77,092,500
$44,987,600
$14,543,200
$31,061,500
$0
Programs:
(click linked program name to drill-down)
2009
Actual
2010
Actual
2011
Actual
2012
Actual
2013
Approp
Transportation Investment Fund Capacity Program $77,092,500 $44,987,600 $14,543,200 $31,061,500 $0
Total
$77,092,500
$44,987,600
$14,543,200
$31,061,500
$0
Categories of Expenditure
(mouse-over category name for definition)
2009
Actual
2010
Actual
2011
Actual
2012
Actual
2013
Approp
Capital Outlay $77,092,500 $44,987,600 $14,543,200 $31,061,500 $0
Total
$77,092,500
$44,987,600
$14,543,200
$31,061,500
$0
Subcommittee Table of Contents

Program: Transportation Investment Fund Capacity Program

Function

The Centennial Highway Fund (CHF) was created by action of the Legislature during the 1996 General Session to segregate increased highway construction funding from the regular ongoing funding revenues of the Department of Transportation. The Legislature created revenue sources to fund forty-one new capacity projects costing $3.268 billion. Those projects were completed in 2011, however the primary funding sources of sales taxes and gas taxes statutorily still flowed into the CHF.

The Transportation Investment Fund of 2005 (TIF) was created during the 2005 General Session of the Legislature under Title 72-2-124. General Fund appropriations were the original funding sources for the Transportation Investment Fund of 2005 and were disignated to be used by the Department to pay the costs of maintenance, construction, reconstruction, or renovation to state and federal highways prioritized by the Transportation Commission through the prioritization process for new transportation capacity projects. The Legislature amended the governing statutes of the Centennial Highway Fund, Critical Highway Needs Fund and Transportation Fund of 2005 to allow ongoing revenues from CHF and CHNF not being used for projects or repayment of bonding for those projects to flow into the TIF. With that action the Legislature authorized three major construction projects costing $2.2 billion. December 2012 is the estimated completion of those projects.

Action of the Legislature during the 2007 General Session created the Critical Highway Needs Fund (CHNF). The legislation designated an additional portion of the sales taxes be dedicated to fund thirty-two highway projects at a cost of $1.199 billion. Those projects were completed in FY 2012 and the funding sources were to continue to flow into the CHNF.

Legislative insight to identify needed highway capicity improvements and create funding sources for the CHF, CHNF and TIF has improved or created one hundred thirty-one Utah highways at a cost of $7.261 billion since 1996.

As the projects designated for each of these three programs were completed and the earmarked funding sources started to flow from CHF and CHNF into the TIF, the Legislature saw reasons to streamline the accounting, oversight of bond repayments and future construction projects from the three existing programs into the transportation Investment Fund Capacity Program.

Senate Bill 225 "Transportation Revisions" was enacted during the 2012 General Session. The statute consolidates the revenue streams from the Centennial Highway Program, the Critical Highway Needs Fund, and the Transportation Fund of 2005 into the Transportation Fund of 2005 and creates the Transportation Investment Fund Capacity Program. Enactment of this legislation will enhance transparency of revenue and expenditures for highway capacity programs of the Department of Transportation.

Funding Detail

Sources of Finance
(click linked fund name for more info)
2009
Actual
2010
Actual
2011
Actual
2012
Actual
2013
Approp
Transportation Investment Fund of 2005 $77,092,500 $44,987,600 $14,543,200 $31,061,500 $0
Total
$77,092,500
$44,987,600
$14,543,200
$31,061,500
$0
Categories of Expenditure
(mouse-over category name for definition)
2009
Actual
2010
Actual
2011
Actual
2012
Actual
2013
Approp
Capital Outlay $77,092,500 $44,987,600 $14,543,200 $31,061,500 $0
Total
$77,092,500
$44,987,600
$14,543,200
$31,061,500
$0
Subcommittee Table of Contents
<-Previous Page | Next Page->